Jamuna rail bridge: East part progressing but west lags behind | The Business Standard
Skip to main content
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Tuesday
July 15, 2025

Sign In
Subscribe
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
TUESDAY, JULY 15, 2025
Jamuna rail bridge: East part progressing but west lags behind

Transport

Saifuddin Saif
25 September, 2023, 10:05 am
Last modified: 25 September, 2023, 11:42 am

Related News

  • Dollar gains Tk1.8 as BB buys at higher rates, lifting market floor
  • Ctg customs to auction 475 containers to ease port congestion
  • Youths need to be equipped with entrepreneurial, technical skills in AI-era: CA Yunus
  • BFIU seeks bank account details of Islami Bank chairman, family
  • July Memorial Museum set to open on 5 August 

Jamuna rail bridge: East part progressing but west lags behind

The construction was divided into two packages and awarded to two Japanese contractors, and the contracting firm responsible for the western part has now requested a four-month extension

Saifuddin Saif
25 September, 2023, 10:05 am
Last modified: 25 September, 2023, 11:42 am

The Bangabandhu Sheikh Mujib Railway Bridge on the Jamuna River, which is scheduled to open for service in August 2024 to strengthen connectivity with the northern part of the country, is lagging behind the target.

According to an inspection report by the Planning Commission, the civil work implementation on the eastern part has progressed well, while work on the other part is behind schedule.

The construction was divided into two packages and awarded to two Japanese contractors, and the contracting firm responsible for the western part has now requested a four-month extension.

"The civil work in the western part is expected to be delayed by four months. To prevent further delays, the contractor has been instructed to increase the supply of skilled manpower and the necessary equipment," Project Director Al Fattah Md Masudur Rahman told The Business Standard.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

"The contracting company responsible for the civil work in the western part delayed arriving at the site. Furthermore, the machinery they brought with them was not up to standard quality, and they also lacked skilled manpower. Consequently, work on this part has been delayed," he added.

The Planning Commission's inspection report also showed that the construction of only four piers and three span superstructures, out of a total of 23 in the western part, has so far been completed.

On the other hand, all 27 piers in the eastern part have been completed. The work of 26 spans has also been completed, it added.

Parallel to the existing Bangabandhu Bridge, a new railway bridge spanning approximately 4.8 kilometres, equipped with dual gauge and double tracks, is under construction 300 metres upstream.

Funded by the Japanese government, the initial outlay for the project, which commenced in 2016, was Tk9,734 crore. Later, the cost was increased by 72% to Tk16,781 crore.

According to the revised target, rail service on the bridge is scheduled to commence in the middle of next year. As of August, the physical progress had reached 69%.

According to railway sources, the design and drawing of the signalling and telecommunication work have been completed. The physical progress of this segment is 6.82%.

Usually, when a project is delayed due to issues with the implementing agency, the contractor can seek compensation by requesting an increase in the contract price. However, when the delay is caused by the contractor, the implementing agency may not be able to impose a penalty.

The project director explained that, according to the contract, fines can be imposed on a daily basis when the implementation is delayed due to the contracting firm. However, the contractor presents their rationale in this case, and if fines are imposed, they have the opportunity to sue.

"But the government wants to avoid the issue of fines so that the implementation is not delayed due to litigation," added Al Fattah Md Masudur Rahman.

The speed and weight of train movement on the existing bridge have been limited as it is basically a road bridge. Currently, trains can operate at a maximum speed of 20km on this bridge.

In response to this limitation, the government initiated the construction of a railway bridge parallel to the Bangabandhu Bridge. 

Once completed, trains will be able to run at a speed of 120km, and they will also be capable of accommodating both freight and passenger trains of any weight.

Bangladesh / Top News

Bangabandhu Sheikh Mujib Railway Bridge / Jamuna River / Railway / Bangladesh

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Commerce Adviser Sk Bashir Uddin met USTR Ambassador Jamieson Greer at the USTR office in Washington, DC on 10 July 2025. Photo: CA Press Wing
    US tariff: 3rd round talks to be held on issues under non-disclosure agreement 
  • Representational image. Photo: Collected
    Dollar gains Tk1.8 as BB buys at higher rates, lifting market floor
  • US President Donald Trump speaks to the press as he arrives at the White House in Washington, DC, US, July 13, 2025. REUTERS/Annabelle Gordon
    In reversal, Trump arms Ukraine and threatens sanctions on countries that buy Russian oil

MOST VIEWED

  • Graphics: TBS
    Bangladesh Bank buys $171m at higher rate in first-ever auction
  • From Gulf to Southeast Asia, why Bangladeshis are facing visa denials
    From Gulf to Southeast Asia, why Bangladeshis are facing visa denials
  • Infographic: TBS
    Dollar price plummets by Tk2.9 in a week as demand wanes
  • Energy Adviser Fouzul Kabir Khan speaking about tariff negotiations with United States on 13 July 2025. Photo: TBS
    US wants a framework agreement with Bangladesh that includes their security concerns: Fouzul
  • CNG drivers blockaded a road in Banani demanding route allocation on 13 July 2025. Photo: TBS
    CNG drivers block road in Banani for hours, causing Mohakhali-Uttara gridlock 
  • Representational image. Photo: Mohammad Minhaj Uddin/TBS
    Navy-run Dry Dock takeover boosts Ctg Port container handling, daily avg up 7%

Related News

  • Dollar gains Tk1.8 as BB buys at higher rates, lifting market floor
  • Ctg customs to auction 475 containers to ease port congestion
  • Youths need to be equipped with entrepreneurial, technical skills in AI-era: CA Yunus
  • BFIU seeks bank account details of Islami Bank chairman, family
  • July Memorial Museum set to open on 5 August 

Features

Illustration: TBS

Open source legal advice: How Facebook groups are empowering victims of land disputes

6h | Panorama
DU students at TSC around 12:45am on 15 July 2024, protesting Sheikh Hasina’s insulting remark. Photo: TBS

‘Razakar’: The butterfly effect of a word

14h | Panorama
Photo: Collected

Grooming gadgets: Where sleek tools meet effortless styles

1d | Brands
The 2020 Harrier's Porsche Cayenne coupe-like rear roofline, integrated LED lighting with the Modellista special bodykit all around, and a swanky front grille scream OEM Plus for the sophisticated enthusiast looking for a bigger family car that isn’t boring. PHOTO: Ahbaar Mohammad

2020 Toyota Harrier Hybrid: The Japanese Macan

2d | Wheels

More Videos from TBS

Will Patriot missile defense save Ukraine?

Will Patriot missile defense save Ukraine?

7h | Others
Market intermediaries want changes in policies

Market intermediaries want changes in policies

8h | TBS Today
Robbery 'in front' of the police, what happened next...

Robbery 'in front' of the police, what happened next...

8h | TBS Stories
Conspirators want Bangladesh not to hold elections: Fakhrul

Conspirators want Bangladesh not to hold elections: Fakhrul

9h | TBS Today
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net