Ashuganj rice silo: Construction lags after 6 years | The Business Standard
Skip to main content
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Get the Paper
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Friday
July 18, 2025

Sign In
Subscribe
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Get the Paper
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
FRIDAY, JULY 18, 2025
Ashuganj rice silo: Construction lags after 6 years

Infrastructure

Azizul Shonchay
06 July, 2024, 12:05 pm
Last modified: 06 July, 2024, 12:06 pm

Related News

  • Govt to import 4 lakh tonnes of rice to avert food risk in flood season
  • Monsoon misses Kurigram; drought threatens Aman cultivation
  • Rice prices up Tk4-8 per kg despite record harvest
  • Bangladesh introduces high-yielding Boro, salt-tolerant, blast-resistant rice varieties
  • ADB, partners unveil plan to overhaul rice sector in Asia-Pacific, including Bangladesh

Ashuganj rice silo: Construction lags after 6 years

Azizul Shonchay
06 July, 2024, 12:05 pm
Last modified: 06 July, 2024, 12:06 pm
Ashuganj steel rice silo project in Brahmanbaria features 30 individual bins, each capable of holding 3,500 tonnes of rice. According to official sources, the project is currently slightly over 77% complete. Photo: TBS
Ashuganj steel rice silo project in Brahmanbaria features 30 individual bins, each capable of holding 3,500 tonnes of rice. According to official sources, the project is currently slightly over 77% complete. Photo: TBS

Highlights:

  • Storage capacity: 105,000 tonnes
  • Can preserve rice quality for up to 2 years
  • Construction delays extend the 2-year project to 6 years
  • Completion expected by December
  • Costs remain unchanged even with deadline extension

The construction of the Ashuganj steel rice silo in Brahmanbaria, a project undertaken as part of the Modern Food Storage Facilities Project, remains incomplete six years after its commencement.

Inaugurated in 2018, the project on the bank of the Meghna River was initially slated for completion by 2020. This project aims to address the challenge of limited rice storage capacity in the district.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

However, the deadline has been extended on several occasions, with the most recent extension set for December this year.

While construction work is ongoing, progress remains slow. According to Modern Food Storage Facilities Project Director Rezaul Karim, the project is currently only slightly over 77% complete. This slow pace has raised concerns about meeting the extended deadline.

"We are hopeful of completing the work by December. Due to the pandemic and other unforeseen challenges, construction activities were halted for a year and a half. This necessitated the multiple deadline extensions," Rezaul Karim said.

He also added that the project costs will not increase despite the extension. 

A recent visit to the construction site revealed that the installation of all 30 bins has been finalised.

Work is currently underway on the remaining structures, including the jetty connecting the river to the silo, the top silo's steel bridge and columns, the bulk truck receiving infrastructure, and the truck scale lab with its weighing equipment.

Despite these ongoing efforts, the pace of work appeared slow.

Md Nishat Hossain, a senior engineer with Toma Construction and Company Limited, the project contractor, explained the reasons behind the slow progress.

"The majority of the silo components are sourced internationally. Unfortunately, during the pandemic, importing equipment became impossible. Additionally, the pandemic forced a work stoppage for a significant period," he said.

Nishat further added, "The subsequent rise in construction material prices presented further challenges, hindering work progress. However, we have addressed all these obstacles and are now working at full capacity. We remain confident in meeting the government's revised deadline."

Brahmanbaria faces a yearly challenge in storing rice due to limited capacity.

"We have a surplus of rice after distribution every season. Due to space constraints in the warehouses, they are sent to neighbouring districts. Once the new silo is operational, this challenge will be effectively addressed," said District Controller of Food Alamgir Kabir.

The Directorate General of Food annually procures around 50,000 tonnes of rice during harvest seasons, exceeding the district's existing food warehouse capacity of 21,500 tonnes. To address this storage constraint, the surplus rice is currently transported to food warehouses in Chattogram.

To alleviate this issue, the Directorate General of Food initiated the construction of a new steel rice silo in Ashuganj under the government's Modern Food Storage Facilities Project.

The project commenced in April 2018 with Toma Construction and Company Limited as the contractor. The silo, designed with a storage capacity of 105,000 tonnes, was estimated to cost Tk 540,45,49,264 and had a projected completion timeframe of two years.

The silo features 30 individual bins, each capable of holding 3,500 tonnes of rice.

An automatic temperature control system will maintain optimal humidity and temperature conditions, allowing for extended rice storage of up to two years without compromising its nutritional value.

This technology is considered to be the most advanced for long-term food grain storage in South Asia, according to industry experts.

A belt conveying and chain conveying system with a capacity of 500 tonnes per hour has also been installed to facilitate efficient packaging and bagging of the stored rice.

However, the project encountered a significant setback due to the Covid-19 pandemic's impact on global supply chains in early 2020. The shipment of crucial equipment was delayed, necessitating four deadline extensions since then.

Bangladesh / Top News

Ashuganj rice silo / Ashuganj / Rice silo / rice

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Around 99% of the cotton used in Bangladesh’s export and domestic garment production is imported. Photo: Collected
    NBR withdraws advance tax on imports of cotton, man-made fibres
  • The fire originated at 10:40pm on the 21th floor of the building. Photo: Collected
    Fire at Sena Kalyan Bhaban in Motijheel under control
  • Chief Adviser Professor Muhammad Yunus presided over a meeting of the National Consensus Commission at the State Guest House Jamuna yesterday (17 July). Photo: UNB
    CA Yunus stresses transparency in finalising July Charter

MOST VIEWED

  • Bangladesh Bank buys $313m more in second dollar auction in three days
    Bangladesh Bank buys $313m more in second dollar auction in three days
  • Representational image. File Photo: Syed Zakir Hossain/TBS
    Malaysia grants Bangladeshi workers multiple-entry visas
  • The Chattogram Custom House building in Chattogram. File Photo: Collected
    Software slowdown disrupts customs operations nationwide
  • NCP leaders are seen getting on an armoured personnel carrier (APC) of the army to leave Gopalganj following attacks on their convoy after the party's rally in the district today (16 july). Photo: Focus Bangla
    NCP leaders leave Gopalganj in army's APC following attack on convoy, clashes between AL, police
  • Renata’s manufacturing standards win european recognition
    Renata’s manufacturing standards win european recognition
  • The supporters of local Awami League and Chhatra League locked in a clash with police following attacks on NCP convoy this afternoon (16 July). Photo: Collected
    Gopalganj under curfew; 4 killed as banned AL, police clash after attack on NCP leaders

Related News

  • Govt to import 4 lakh tonnes of rice to avert food risk in flood season
  • Monsoon misses Kurigram; drought threatens Aman cultivation
  • Rice prices up Tk4-8 per kg despite record harvest
  • Bangladesh introduces high-yielding Boro, salt-tolerant, blast-resistant rice varieties
  • ADB, partners unveil plan to overhaul rice sector in Asia-Pacific, including Bangladesh

Features

Illustration: TBS

20 years of war, 7.5m tonnes of bombs, 1.3m dead: How the US razed Vietnam to the ground

1h | The Big Picture
On 17 July 2024, Dhaka University campus became a warzone with police firing tear shells and rubber bullets to control the student movement. File Photo: Rajib Dhar/TBS

17 July 2024: Students oust Chhatra League from campuses, Hasina promises 'justice' after deadly crackdown

9h | Panorama
Abu Sayeed spread his hands as police fired rubber bullets, leading to his tragic death. Photos: Collected

How Abu Sayed’s wings of freedom ignited the fire of July uprising

2d | Panorama
Illustration: TBS

Open source legal advice: How Facebook groups are empowering victims of land disputes

3d | Panorama

More Videos from TBS

Why the conflicting claims over Gopalganj autopsies?

Why the conflicting claims over Gopalganj autopsies?

2h | TBS Stories
Gopalganj violence in international media

Gopalganj violence in international media

3h | TBS World
The Philippines has become a laboratory for China's disinformation propaganda

The Philippines has become a laboratory for China's disinformation propaganda

3h | TBS World
Gopalganj clash: Army urges not to be misled by rumors

Gopalganj clash: Army urges not to be misled by rumors

5h | TBS Today
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net