72.12 pc work of metro rail’s 1st phase completed | The Business Standard
Skip to main content
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Sunday
June 01, 2025

Sign In
Subscribe
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
SUNDAY, JUNE 01, 2025
72.12 pc work of metro rail’s 1st phase completed

Infrastructure

BSS
02 June, 2020, 08:15 pm
Last modified: 02 June, 2020, 08:18 pm

Related News

  • Metro rail services resume after nearly 2hrs halt due to electrical issue
  • Disruption due to drone, overcrowding cause suffering to Metro passengers
  • Metro rail resumes service today after Eid-day break
  • Can 'strike-happy' employees run the Metro rail?
  • Metro rail staff threaten strike from Friday over job policy delay

72.12 pc work of metro rail’s 1st phase completed

The progress of the second phase of construction from Agargaon to Motijheel is 39.73 percent

BSS
02 June, 2020, 08:15 pm
Last modified: 02 June, 2020, 08:18 pm
Photo: Salahuddin Ahmed
Photo: Salahuddin Ahmed

The construction work of the country's first ever metro rail is progressing fast as the authorities have completed overall 72.12 percent work so far of the project from Uttara to Agargaon as per the revised plan.

"The overall physical progress of the first phase construction from Uttara to Agargaon is 72.12 percent," Managing Director of Dhaka Mass Transit Company Limited (DMTCL) MAN Siddique told BSS here today.

He said the progress of the second phase of construction from Agargaon to Motijheel is 39.73 percent.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

"More than 10.26 out of a total 20.1 km of Dhaka metro rail line is now visible, as the government plans to inaugurate the country's first-ever metro on the Golden Jubilee of Bangladesh's independence in December 2021," Siddique said.

According to the DMTCL's progress report, 93 per cent of metro rail's main deck between Agargaon and Uttara has been completed. The integrated progress including Electrical and Mechanical System and Rolling Stock (Rail Coach) and Depot Equipment is 29.80 percent.

The Prime Minister has consented to extend the MRT Line-6 from Motijheel to Kamalapur. Consequently, social survey of extended 1.16 kilometre is ongoing.

"We have given order to Japanese metro train company for manufacturing second, third and fourth set of passenger trains, as the first passenger train was ready for shipment," the managing director said.

He said the DMTCL, an autonomous body under the transport and bridges ministry, is executing the project.

Siddique said construction work is going following the prescribed health guidelines during the COVID-19 pandemic.

The authorities said the trains for the metro rail will have the capacity to transport 60,000 passengers per hour from Uttara, a northern suburb of the capital, to Motijheel.

The authorities said there will be sound proofing walls along the tracts.

To bring a realistic solution to Dhaka city's traffic congestion, the Awami League government led by Prime Minister Sheikh Hasina initiated the mega project.

The project is divided into eight construction packages which will cost Taka 219.85 billion. Of them, Japan's aid agency JICA will provide 165 billion.

The metro rail will have 16 stations – at Uttara North, Central Uttara, Uttara South, Pallabi, Mirpur-11, Mirpur-10, Kazipara, Shewrapara, Agargaon, Bijoy Sharani, Farmgate, Karwan Bazar, Shahbag, Dhaka University, the secretariat and Motijheel.

The metro rail will take 35 minutes to reach Motijheel from Uttara. The station will be high as a three-storey building and will be accessed by escalators and lifts.

Ticket counter and other facilities will be available on the second floor.

The authorities said 12 trains will run on the routes.

The DMTCL managing director said foreigners and also local experts will also be taken under 14 days quarantine aimed at preventing coronavirus spread. The COVID-19 epidemic has not heavily affected the metro rail project.

Road Transport and Bridges Minister Obaidul Quader earlier said the total metro-rail project is being done in eight packages, adding, "Construction work of Mass-Rapid Transport (MRT) Line-6, the country's first elevated metro rail system in Dhaka city, is going on in full swing targeting to complete it by the end 2021."

According to project details, under fifth packages, 3.2-kilometre viaduct and three metro stations are being built from Agargaon to Karwarbazar while 4.9-kilometer metro-rail from Karwanbazar to Motijheel having four stations is being constructed under the sixth package.

Bangladesh / Top News

Metro Rail / 1st phase

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Illustration: TBS
    Tax-free income ceiling to be raised, slabs restructured
  • Infographic: TBS
    Govt targets Dec opening of Dhaka airport's 3rd terminal but Japanese consortium wants 2 more months
  • Chief Adviser Muhammad Yunus returns to Dhaka on 1 June 2025, wrapping up his four-day official tour to Japan. Photo: Courtesy
    CA Yunus returns home wrapping up Japan tour

MOST VIEWED

  • BAT Bangladesh has to vacate Mohakhali HQ as SC rejects lease appeal
    BAT Bangladesh has to vacate Mohakhali HQ as SC rejects lease appeal
  • Bangladesh Chief Adviser Muhammad Yunus speaks to Nikkei Asia in Tokyo on 29 May. Photo: Nikkei Asia
    Bangladesh ready to buy more US cotton, oil to reduce trade gap: Yunus
  • UCB approves 2024 financials, allocates entire profit to NPL provisions
    UCB approves 2024 financials, allocates entire profit to NPL provisions
  • Tax exemptions for key industries to go, sweeping tax hikes planned
    Tax exemptions for key industries to go, sweeping tax hikes planned
  • Matarbari 1,200MW coal-fired plant in Moheshkhali, Cox's Bazar. File Photo: Nupa Alam/TBS
    Supplier slapped with 5 conditions to unload rejected Matarbari coal shipment
  • US Embassy Dhaka. Picture: Courtesy
    Birth tourism not permitted on US visitor visa: US Embassy Dhaka

Related News

  • Metro rail services resume after nearly 2hrs halt due to electrical issue
  • Disruption due to drone, overcrowding cause suffering to Metro passengers
  • Metro rail resumes service today after Eid-day break
  • Can 'strike-happy' employees run the Metro rail?
  • Metro rail staff threaten strike from Friday over job policy delay

Features

Babar Ali, Ikramul Hasan Shakil, and Wasfia Nazreen are leading a bold resurgence in Bangladeshi mountaineering, scaling eight-thousanders like Everest, Annapurna I, and K2. Photos: Collected

Back to 8000 metres: How Bangladesh’s mountaineers emerged from a decade-long pause

1d | Panorama
Photos: Courtesy

Behind the looks: Bangladeshi designers shaping celebrity fashion

1d | Mode
Photo collage of the sailors and their catch. Photos: Shahid Sarkar

Between sky and sea: The thrilling life afloat on a fishing ship

1d | Features
For hundreds of small fishermen living near this delicate area, sustainable fishing is a necessity for their survival. Photo: Syed Zakir Hossain

World Ocean Day: Bangladesh’s ‘Silent Island’ provides a fisheries model for the future

2d | The Big Picture

More Videos from TBS

Fuel prices cut; effective from June 1

Fuel prices cut; effective from June 1

5h | TBS News Updates
News of The Day, 31 MAY 2025

News of The Day, 31 MAY 2025

8h | TBS News of the day
Which way will the job crisis take the Chinese young generation?

Which way will the job crisis take the Chinese young generation?

9h | Others
How Banglalink is implementing Veon DO 1440

How Banglalink is implementing Veon DO 1440

7h | TBS Stories
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net