Chattogram waterlogging mitigation projects mired in complexities | The Business Standard
Skip to main content
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Wednesday
May 21, 2025

Sign In
Subscribe
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
WEDNESDAY, MAY 21, 2025
Chattogram waterlogging mitigation projects mired in complexities

Infrastructure

Jobaer Chowdhury
06 March, 2022, 01:15 pm
Last modified: 06 March, 2022, 01:37 pm

Related News

  • Garment accessories, paper-cellophane traders demand cancellation of Ctg port's four-fold store rent hike
  • Prolonged rainfall causes severe waterlogging in Kurigram
  • Fake juice factory busted in Chattogram, one arrested
  • Who should run Bangladesh's busiest container terminal?
  • Ctg's Zia Memorial Museum to be transformed into modern one: Farooki

Chattogram waterlogging mitigation projects mired in complexities

Jobaer Chowdhury
06 March, 2022, 01:15 pm
Last modified: 06 March, 2022, 01:37 pm
An underconstruction sluice gate at the mouth of Rajakhali lake of the River Karnaphuli in Chattogram. Under a project to solve the waterlogging problem of the city, infrustuctural work of 40 sluice gate is complete but installation of pumps and gates are not likely to be completed before the monsoon this year. Photo: Mohammad Minhaz Uddin.
An underconstruction sluice gate at the mouth of Rajakhali lake of the River Karnaphuli in Chattogram. Under a project to solve the waterlogging problem of the city, infrustuctural work of 40 sluice gate is complete but installation of pumps and gates are not likely to be completed before the monsoon this year. Photo: Mohammad Minhaz Uddin.

Four large projects taken up by the government involving an estimated cost of Tk10,603 crore to solve the decade-old waterlogging problem in Chattogram city are not likely to benefit the people of this city any time soon due to various issues such as the complexities in land acquisition and design, lack of coordination and slow pace of work.

For example, to get rid of this long-standing waterlogging, work is underway to install regulators at the mouths of 40 canals in the city. These canals have been blocked for the physical work of installing the regulators but not more than five regulators will be operational before the monsoon season this year.

Besides, 36 canals of the city are being dug and renovated to keep the flow of rain and tidal water in order. Work on 18 of the canals has not been completed due to land acquisition complications.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

In August 2017, the Executive Committee of the National Economic Council (Ecnec) approved the Tk5,616 crore project for re-excavation, expansion, renovation and development of canals to alleviate waterlogging in the city.

Land acquisition has remained a major obstacle since the project started in April 2018. At the time of approval, the compensation for land acquisition was one and a half times but it has been refixed three times amending the law. Therefore, out of the 6,516 kathas of land allotted for the project, only 300 kathas have been acquired.

Besides, out of 85.68 km of road along the canal, 13.05 km has been completed. And, work has started on 15 out of 42 silt traps to prevent hilly sand.

Project Director Lieutenant Colonel Md Shah Ali of the 34th Engineering Construction Brigade of the Army, the director of the project, told The Business Standard (TBS), "Under the project, setting up of regulators in Maryam Bibi, Kalabagicha, Tekpara, Firingibazar and Maheshkhal will be completed before the monsoon season."

"Regulators have been brought from the UK and gates from the Netherlands. Besides, the soil will be removed from all the canals before the monsoon," he added.

Under another Tk2,310crore project for the construction of roads from Kalurghat bridge to Chaktai canal along the banks of Karnaphuli, the instalment of 12 regulators are stuck in a financial crisis. In the current financial year, only Tk213 crore has been allocated against the demand of Tk500 crore.

Under the project, 8.55 km of roads and embankments are also to be constructed. The work is to be completed in June this year by extending the implementation period in three phases.

Rajiv Das, project director and Chittagong Port Authorities (CPA) executive engineer, told TBS, "We have received Tk100 crore in the first year of Covid-19, which is very little for such a big project."

An underconstruction sluice gate at the mouth of Rajakhali lake of the River Karnaphuli in Chattogram. Under a project to solve the waterlogging problem of the city, infrustuctural work of 40 sluice gate is complete but installation of pumps and gates are not likely to be completed before the monsoon this year. Photo: Mohammad Minhaz Uddin.
An underconstruction sluice gate at the mouth of Rajakhali lake of the River Karnaphuli in Chattogram. Under a project to solve the waterlogging problem of the city, infrustuctural work of 40 sluice gate is complete but installation of pumps and gates are not likely to be completed before the monsoon this year. Photo: Mohammad Minhaz Uddin.

Another project for flood protection wall construction on the banks of the River Karnaphuli, to be implemented by the Bangladesh Army at Tk1,620crore, is also stuck due to the objection of CPA, financial crisis and complexities in the regulator's designs. 

Under the project, a 19-km long flood protection wall was to be constructed on the banks of the river in addition to installing regulators at the mouths of 23 canals. Of these, physical work has been completed in only two regulators and four are in progress even though the project deadline will end in June. Not even Tk100 crore has been disbursed for the project so far.

An extension of one year has been requested, however, the people concerned think that it would not be possible to get such a huge amount of money in one year. No one from the authorities wanted to comment on it.

CPA Chief Hydrographer Commander M Arifur Rahman told TBS, "The port area was excluded in the feasibility study of the wall construction because if walls are constructed in the area from the Padma, Meghna, Jamuna oil on the bank to ghat-15 where will the ships dock!"

Water Development Board Executive Engineer Toyan Kumar Tripura said, "Due to the port's objection, a 12.35-km wall will not be constructed from ghat-15 to Shah Amanat Bridge. However, the construction of a 6.5 km flood protection wall from Kalurghat to Madunaghat is underway. The project is being revised. As much land acquisition does not have to be done the project cost and time will come down a lot."

On 24 June 2014, Ecnec approved a canal excavation project from Baroipara to the Karnaphuli at Tk1,256crore to be implemented by the Chittagong City Corporation. After seven years, the project was inaugurated on 27 November last year. Although the duration of the project has been extended till 2024, the physical work has not started due to the non-acquisition of land.

Tk914 crore has been spent on land acquisition. The district administration has so far allotted 10 acres out of 25 acres.

Project Director of Chattogram City Corporation Executive Engineer Md Farhadul Alam said it would take another six months to get the land. Then the canal excavation work will start.

Bangladesh / Top News

waterlogging / Waterlogging in ctg / Chattogram / Chattogram city

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Govt to cut property registration tax by 40%, align deed value with market rates
    Govt to cut property registration tax by 40%, align deed value with market rates
  • British Prime Minister Keir Starmer speaks during a reception, following the UK-EU summit, in London, Britain, May 19, 2025. REUTERS/Hannah McKay/Pool/File Photo
    UK suspends trade talks with Israel, summons ambassador, issues sanctions over new Gaza offensive
  • A file photo of the NBR Bhaban in Agargaon, Dhaka
    NBR dissolution: Protesters say meeting with advisers not fruitful, announces sit-in programme tomorrow

MOST VIEWED

  • Lotto inaugurates new factory to nearly triple production capacity
    Lotto inaugurates new factory to nearly triple production capacity
  • Ikramul Hasan Shakil at the Base Camp of Mount Everest. Photo: Collected from Shakil's official Facebook page
    From sea to summit: Shakil walks from Cox's Bazar to conquer Everest
  • Illustration: Collected
    Unemployment rate hits historic high, rises to 4.63% as 27.4 lakh now jobless
  • Representational image
    Govt plans to scrap reduced tax benefits for textile sector
  • Saleh Uddin Ahmed. Sketch: TBS
    Large depositors in troubled banks to be offered shares, bonds: Salehuddin
  • The Chattogram Custom House building in Chattogram. File Photo: Collected
    Ctg custom house pen-down strike continues for 5th day

Related News

  • Garment accessories, paper-cellophane traders demand cancellation of Ctg port's four-fold store rent hike
  • Prolonged rainfall causes severe waterlogging in Kurigram
  • Fake juice factory busted in Chattogram, one arrested
  • Who should run Bangladesh's busiest container terminal?
  • Ctg's Zia Memorial Museum to be transformed into modern one: Farooki

Features

Football presenter Gary Lineker walks outside his home, after resigning from the BBC after 25 years of presenting Match of the Day, in London, Britain. Photo: Reuters

Gary Lineker’s fallout once again exposes Western media’s selective moral compass on Palestine

4h | Features
Fired by US aid cuts, driven by courage: A female driver steering through uncertainty

Fired by US aid cuts, driven by courage: A female driver steering through uncertainty

11h | Features
Photo: TBS

How Shahbagh became the focal point of protests — and public suffering

1d | Panorama
PHOTO: Collected

Helmet Hunt: Top 5 half-face helmets that meet international safety standards

2d | Wheels

More Videos from TBS

Western world warns Israel over aid blockade and military operation

Western world warns Israel over aid blockade and military operation

4h | TBS World
Atrai dam breaks for the second time within 4 months

Atrai dam breaks for the second time within 4 months

5h | TBS Today
How is China the 'winner' of the India-Pakistan conflict?

How is China the 'winner' of the India-Pakistan conflict?

6h | Others
Why ADP implementation rate lowest in education and health sectors?

Why ADP implementation rate lowest in education and health sectors?

7h | Podcast
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net