Power shortfall nears 2,000MW amid summer hit, gas shortage   | The Business Standard
Skip to main content
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Saturday
July 12, 2025

Sign In
Subscribe
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
SATURDAY, JULY 12, 2025
Power shortfall nears 2,000MW amid summer hit, gas shortage  

Energy

Joynal Abedin Shishir
27 June, 2024, 10:20 pm
Last modified: 27 June, 2024, 10:24 pm

Related News

  • Power of individuals must be limited in governance: Ali Riaz
  • BNP plans to create 10 million jobs in 18 months if voted to power: Amir Khasru
  • India's $80 billion coal-power boom is running short of water
  • Brains without borders: How Bangladesh’s youth are shaping soft power diplomacy
  • Adani finally agrees to sit over power purchase disputes

Power shortfall nears 2,000MW amid summer hit, gas shortage  

Rural areas hit hardest

Joynal Abedin Shishir
27 June, 2024, 10:20 pm
Last modified: 27 June, 2024, 10:24 pm
Representational image/Collected
Representational image/Collected

Following the Eid holidays, as summer continues, the country is grappling with rising electricity demand and inadequate power production, resulting in severe disruptions to daily life with rural areas experiencing the worst impact.

Power Division officials say gas shortages have led to complete or partial shutdown of several gas-based power plants. Simultaneously, maintenance work at major coal-based power plants has reduced electricity production. 

It all led to a significant deficit when the lack of rain and rising temperatures have increased power demand.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

According to data from the Power Grid Company of Bangladesh, at 2am today, nationwide electricity demand was 15,100MW, while production was only 13,026MW, resulting in a 1,981MW shortfall.

The situation was even worse the previous day, with load-shedding recorded at 2,240MW, according to the sole state-owned entity responsible for transmitting electricity from power plants to the national grid.

Experts believe the Grid Company's figures do not fully reflect the real situation, suggesting that actual load-shedding may be higher due to inaccuracies in demand calculations.

According to officials at power distribution companies, all state-owned, nationwide load-shedding has exceeded 2,000-3,000MW over the last couple of days.

Data from the Rural Electrification Board, which supplies electricity to over 80% of rural areas, notes that it maintained load-shedding of about 2,500-3,000MW today.

As a result, rural areas have been experiencing power outages for 18-20 hours a day, severely affecting industrial production and the charging of batteries for power vehicles, causing significant commuting difficulties, said people in various affected areas.

In some areas, power outages occur every hour, worsening public suffering in the prolonged and intense heat, they added.

Reasons for increased load-shedding?

The Power Division reports that the country's largest power plant in Payra has completely shut down one of its units. The plant's total capacity is 1,244MW, but with one unit closed, the other unit is generating only about 600MW. 

Maintenance work is also ongoing at one unit of the second-largest power plant in Rampal, which has a capacity of 1,234MW, reducing its output to about 800MW.

The third-largest power plant, SS Power in Chattogram, with a capacity of 1,224MW, also has one unit closed for maintenance, producing only about 600MW. The second-largest gas-based power plant, Meghnaghat, with a capacity of 584MW, is currently completely shut down due to gas shortages, it added.

Moreover, technical issues have caused Summit's LNG terminal to go out of operation, further reducing gas supply. The floating LNG terminal of Summit Group was sent to Singapore for repairs after being damaged by Cyclone Remal. As a result, gas supply has decreased, impacting electricity production.

According to Petrobangla, the country currently has a daily gas demand of 3,800 million cubic feet, but only 2,600 mmcfd are being supplied, resulting in a 1,000-1,200MW shortfall in gas-based electricity production.

Kamruzzaman Khan, director at Petrobangla, told The Business Standard, "Summit's floating LNG terminal (FSRU) in Maheshkhali, Cox's Bazar, was damaged by Cyclone Remal and taken to Singapore for repairs. It will take another 15-17 days for repairs to be completed and for the terminal to return to the country. We may have to wait until July 15 for its return."

Seeking anonymity, an official at the Bangladesh Power Development Board told TBS, "The simultaneous damage to Summit's LNG terminal, the sudden shutdown of one unit at the Payra power plant, and maintenance at Adani's power plant have made it challenging to manage the overall situation.

"The lack of rain and rising temperatures have increased power demand, leading to load-shedding. However, officials claim that the situation will improve rapidly with cooler temperatures due to rainfall and the reopening of the Payra power plant." 

Top News

load-shedding / power / Gas Shortage

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Bangladesh and US hold tariff talks on 11 July 2025. Photo: CA Press Wing
    Dhaka, Washington yet to agree on 20% of US tariff conditions: BGMEA
  • A file photo of BNP acting chairman Tarique Rahman speaking virtually at a party programme. Photo: Collected
    ‘Why is govt allowing this’: Tarique calls for crackdown on mob violence
  • Rakibul Alam Chowdhury, former vice-president of BGMEA. Photo: Courtesy
    35% US tariff: Bangladesh’s $10b garment trade teeters on edge

MOST VIEWED

  • Representational image
    In addition to 35% tariff, US demands 40% local value addition for 'Made in Bangladesh' goods
  • Screengrab blurred
    Killers bash in head of man with rock, stomp body with perverse pleasure
  • How tender rules and a lone bidder stall a $2.5b power plant
    How tender rules and a lone bidder stall a $2.5b power plant
  • Economist Abul Barkat; Photo: Courtesy
    Economist Abul Barkat arrested in graft case
  • Photo: UNB
    WHO's Saima Wazed Putul 'placed on indefinite leave' amid corruption allegations: Health Policy Watch
  • After India's visa restriction, China's Kunming is drawing Bangladeshi patients
    After India's visa restriction, China's Kunming is drawing Bangladeshi patients

Related News

  • Power of individuals must be limited in governance: Ali Riaz
  • BNP plans to create 10 million jobs in 18 months if voted to power: Amir Khasru
  • India's $80 billion coal-power boom is running short of water
  • Brains without borders: How Bangladesh’s youth are shaping soft power diplomacy
  • Adani finally agrees to sit over power purchase disputes

Features

The 2020 Harrier's Porsche Cayenne coupe-like rear roofline, integrated LED lighting with the Modellista special bodykit all around, and a swanky front grille scream OEM Plus for the sophisticated enthusiast looking for a bigger family car that isn’t boring. PHOTO: Ahbaar Mohammad

2020 Toyota Harrier Hybrid: The Japanese Macan

2h | Wheels
The showroom was launched through a lavish event held there, and in attendance were DHS Motors’ Managing Director Nafees Khundker, CEO Imran Zaman Khan, and GMs Arman Rashid and Farhan Samad. PHOTO: Akif Hamid

GAC inaugurate flagship showroom in Dhaka

2h | Wheels
After India's visa restriction, China's Kunming is drawing Bangladeshi patients

After India's visa restriction, China's Kunming is drawing Bangladeshi patients

1d | Panorama
Photo: Collected/BBC

What Hitler’s tariff policy misfire can teach the modern world

1d | The Big Picture

More Videos from TBS

Flashpoint Cumilla: where the July coup turned violent

Flashpoint Cumilla: where the July coup turned violent

Now | TBS Stories
US-Canada trade talks still uncertain

US-Canada trade talks still uncertain

2h | TBS World
Air India crash: What happened before the plane crashed?

Air India crash: What happened before the plane crashed?

3h | TBS World
Home Affairs Advisor calls on everyone to come forward and stop violence

Home Affairs Advisor calls on everyone to come forward and stop violence

5h | TBS Today
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net