118 projects in 12 years, yet trains are still slow. Why? | The Business Standard
Skip to main content
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Monday
May 26, 2025

Sign In
Subscribe
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
MONDAY, MAY 26, 2025
118 projects in 12 years, yet trains are still slow. Why?

Panorama

Dr Md Shamsul Hoque
22 November, 2020, 12:10 pm
Last modified: 22 November, 2020, 12:38 pm

Related News

  • Railway starts selling advance tickets
  • Dhaka's rail communications with southern region resume after 15 hrs
  • Jahanabad Express derails, southern rail links cut for 12 hours
  • Tk93.51cr project launched for green railway development
  • Innovating railway turntable with local tech: Ruet alumnus wins int’l award 

118 projects in 12 years, yet trains are still slow. Why?

The world is now promoting rail, even if they have to provide a subsidy, as railways are more sustainable and environment-friendly than other means of communication

Dr Md Shamsul Hoque
22 November, 2020, 12:10 pm
Last modified: 22 November, 2020, 12:38 pm
Representational Photo: Collected
Representational Photo: Collected

Over the last 12 years, the railway has taken up 118 development projects, of which 79 projects have been completed, and 39 projects are still ongoing. And yet, train speed has not increased, and till now derailment and head-on clashes continue. 

We have focused so much on infrastructure development projects that we have almost forgotten about the maintenance and operation-related projects. Also, when you take so many projects at a time, and do not have a sufficient workforce, the performance suffers.

The railway is a maintenance-intensive sector. It has to be of international standard, and there is no way we can say that we lack the budget. Round the year, we need to maintain the infrastructure.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

We have taken projects to develop new infrastructure so that our trains can move at more than 100 kmph speed. But unfortunately, we have not taken a single project to develop the corridor access control system.

There are illegal level crossings, shanties, and markets around the railway tracks. No matter how many tracks we lay down, or replace the wooden sleepers with the concrete ones, we will not be able to raise the speed. A prerequisite for faster service is that there has to be section 144 around the railway corridors so that the trains can move without reducing its speed. But as long as we do not solve this issue, our trains will run slow.

Additionally, in Bangladesh, there is no professionalism in the rail sector. We inherited around 2,800 km of rail network and hundreds of stations when the British left the subcontinent. But when the sector did not receive any funding for maintenance, it had to shrink down the operational routes and close down the non-performing stations. Also, the human resources were brought down through golden handshakes.

Human resource is one of the major assets of the railway sector. If we want to operate trains safely, we need experienced loco masters and technicians; because we cannot train a person to become skilled like them overnight. The focus also shifted from the railways as it was a non-performing sector, and the donors were not keen to invest here as well.

For a long time, there was no separate ministry for the Bangladesh Railway. It used to operate under the Roads and Highways department. As a result, it had been deprived of investment and development for a long time.

On the other hand, investment rose on the development of highways. Highways provide a passport to freedom. Not only in Bangladesh, people everywhere in the world would rather reach their intended destination directly from their doorsteps, instead of having to hop from one station to another. Apart from the road and highways, this is not possible when travelling by train, ships or aeroplanes. So, understanding the pulse of citizens, the government and funding agencies invested more in developing the highways.

Any engineering project requires a massive amount of focused time, and many railway officials are working as project directors of several railway projects at a time. As a result, they cannot provide the quality time required, even if they wanted to. 

So, naturally, the project faces time and cost overruns. Also, the projects need revisions sometimes, due to changes in different policies like land acquisition. In my opinion, if we could proceed systematically, it would be possible to see developments happening in the railway sector.  

Bangladesh is a small country, and it is mostly flat terrain. Also, the capital is situated almost in the middle of the country. So if you want to travel to the furthest corner of the country, you will have to travel around 350 km. So the train is not an ideal mode of transportation in this regard as we can develop highways easily. And as our highways are getting better day by day, it will be hard to convince the passengers to adopt a station to station service, while they can easily access the door to door facility.

Yet, we need development in the railway sector because a country cannot survive with roads as the only mode of communication; and it is also not sustainable and environment-friendly. Waterways and railways are a blessing in this regard.

We need to be tactical and identify if we want to invest more on passenger transportation or freight transportation. Freight transportation will not only bring revenue but also reduce pressure on the roads and thereby will help in developing balanced intermodal sustainable transport systems.

The containers that land in our ports are moved to their destinations through covered vans, and often intermodal containers get knocked down in the ports, creating multimodal break-bulk cargo, which is not sustainable at all. 

The process should be that when a container arrives at the port through ships, it will use railway intermodal to reach its destination. And if we can develop our railway tracks directly from port to different EPZs and 100 special economic zones, the containers will certainly be transported through trains, and the government will be able to generate more revenue than it will be able to generate from passenger transportation. 

Moreover, due to faster, reliable and pilfer proof containerised freight transport systems, industries will get better global competitive edges. 

The railway also has a lot of idle land throughout the country. Nowadays it is tough to find suitable land for commercial and industrial development. And everywhere around the world, these lands are leased to different companies so that they can build business and commercial establishments around the rail stations and tracks. 

Thus, if the railway decides to use the immovable property they inherit, they will find investments easily and can generate non-operational revenue, which can be gainfully utilised to meet recurrent O&M costs and gradually become subsidy free.

The entire world knows that government-owned organisations alone cannot provide satisfactory services to passengers, which is why the government makes the roads, and private companies provide transportation services. So we need a public-private framework to ensure proper service. However, unfortunately, it is not possible under the existing structure.

In the 21st century, every country around the world is focusing more on railways, as it is more sustainable and environment friendly. Earlier, people thought only about development, but nowadays, they are thinking more about sustainable development.

As a result, the world is now promoting rail, even if they have to provide a subsidy, as the railways are more sustainable and environment friendly - less land-hungry and low carbon footprint - than other means of communication. This is more pertinent for Bangladesh with its acute scarcity and low per capita land, in tandem with high competing demand for agriculture, industries, housing etc.

The author is a professor of Civil Engineering at Bangladesh University of Engineering and Technology (BUET)

Analysis / Top News

Railway / Department

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Showkat Aziz Russell, Anwar-ul Alam Chowdhury Parvez, Razeeb Haider. Photos: Collected
    Business leaders decry 'economic assassination' amid crippling gas crisis
  • A BNP delegation led by senior leader Khandaker Mosharraf Hossain meets with Chief Adviser Muhammad Yunus during a meeting at Guest State House Jamuna on 24 May 2025. Photo: CA Press Wing
    Stalemate over election: Resolving or deepening?
  • Chief Adviser Muhammad Yunus. File Photo: CA Press Wing
    CA meeting with BNP, Jamaat, NCP and 20 others: What was said

MOST VIEWED

  • Infographic: TBS
    New transport strategy for Dhaka seeks to promote walking, cycling
  • Representational image: Collected
    Minimum tax may rise to Tk5,000 for individuals, Tk1,000 for new filers
  • File photo of Sajib Barai. Photo: TBS
    Barishal medical student ends life after citing 'excessive academic pressure'
  • FIre service officials taking the bodies after a truck hitting a motorcycle in Banani left two people killed on the spot on 25 May 2025. Photo: TBS
    2 killed after truck hits motorcycle in Banani
  • Ports crippled as NBR officials escalate protests, threaten full trade halt
    Ports crippled as NBR officials escalate protests, threaten full trade halt
  • BNP senior leaders and CA at Jamuna on 24 May evening. Photo: CA Press Wing
    Talks with CA: BNP calls for swift completion of reforms for elections in Dec, removal of 'controversial' advisers

Related News

  • Railway starts selling advance tickets
  • Dhaka's rail communications with southern region resume after 15 hrs
  • Jahanabad Express derails, southern rail links cut for 12 hours
  • Tk93.51cr project launched for green railway development
  • Innovating railway turntable with local tech: Ruet alumnus wins int’l award 

Features

The Hili Land Port, officially opened in 1997 but with trade roots stretching back to before Partition, has grown into a cornerstone of bilateral commerce.

Dhaka-Delhi tensions ripple across Hili’s markets and livelihoods

5h | Panorama
Photo: Collected

Desk goals: Affordable ways to elevate your study setup

11h | Brands
Built on a diamond-type frame, the Hornet 2.0 is agile but grounded. PHOTO: Asif Chowdhury

Honda Hornet 2.0: Same spirit, upgraded sting

11h | Wheels
The well has a circular opening, approximately ten feet wide. It is inside the house once known as Shakti Oushadhaloy. Photo: Saleh Shafique

The last well in Narinda: A water source older and purer than Wasa

2d | Panorama

More Videos from TBS

27 wildlife rescued in mini zoo raid

27 wildlife rescued in mini zoo raid

4h | TBS Stories
How the small country in South America has become the subject of research.

How the small country in South America has become the subject of research.

3h | Others
All Israeli armored brigades are now deployed in Gaza

All Israeli armored brigades are now deployed in Gaza

4h | TBS World
India-Pakistan, China-Iran; Why is everyone pulling the Taliban closer?

India-Pakistan, China-Iran; Why is everyone pulling the Taliban closer?

5h | Others
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net