Govt's 5,238MW grid-tied solar push faces tepid response from investors | The Business Standard
Skip to main content
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Thursday
May 22, 2025

Sign In
Subscribe
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
THURSDAY, MAY 22, 2025
Govt's 5,238MW grid-tied solar push faces tepid response from investors

Energy

Shazzad Hossen
11 May, 2025, 09:30 am
Last modified: 11 May, 2025, 01:54 pm

Related News

  • Govt plans renewable energy, eco-tourism on unused tea estate land
  • Renewable energy pitch will not yield fruit until institutional change
  • EIB to provide €350 million loan for Bangladesh's renewable energy projects
  • Govt plans ‘some load-shedding’ to ease subsidy pressure
  • Some amount of load-shedding in summer unavoidable: Adviser Fouzul

Govt's 5,238MW grid-tied solar push faces tepid response from investors

Industry insiders blame abrupt policy shifts as reason for dismal investor turnout

Shazzad Hossen
11 May, 2025, 09:30 am
Last modified: 11 May, 2025, 01:54 pm
Solar power project in Chattogram. Photo: TBS
Solar power project in Chattogram. Photo: TBS

The government's ambitious push to install 5,238 megawatts of grid-tied solar power at 55 sites across Bangladesh has hit a stumbling block. Despite repeated deadline extensions for tender bids, the initiative has drawn a lukewarm response, signalling eroding confidence in the country's renewable energy policy.

The Bangladesh Power Development Board (BPDB) floated four international tender packages between 5 December 2024 and 19 March 2025 for the construction of the solar plants from Lalmonirhat in the north to Teknaf in the south. 

These tenders, aimed at boosting solar capacity, cover design, installation, supply, testing, commissioning, and land and financing arrangements by private developers.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

Yet, by 5 May, the BPDB had sold only 183 tender documents across the four packages. Investor disinterest has prompted repeated delays, with the bid submission deadlines extended between one and five times for each package.

According to BPDB data, 11 plants have seen zero tender document sales, while another 13 received only a single response – raising questions about confidence in the country's renewable energy policies.

Officials at the BPDB said the outlook remains uncertain. "Despite our efforts to give bidders enough time to evaluate projects, many are staying away," said one official, requesting anonymity. "The trust deficit surrounding our energy policy is proving hard to overcome."

"We are trying to attract credible companies in this new round of bidding after cancelling previous Letters of Intent," said Muhammad Fouzul Kabir Khan, adviser to the power, energy and mineral resources ministry. 

"However, we remain cautiously optimistic," he added.

Package breakdown

The first package, comprising 12 plants with a combined 353MW capacity, was initially due for submission on 3 February. It has since been rescheduled five times, with the current deadline set for 19 May. 

So far, 95 bid documents have been sold. Of these, the 45MW plant at Bhaluka substation attracted the most interest with 19 bids, while several others – such as Hathazari, Bajitpur, Chandraghona, and Nobabganj – each drew only three.

The second package, for ten 50MW plants (500MW total), received just 39 bids despite four extensions. Sales began on 8 January, with the first deadline on 10 March. Panchagarh substation saw the highest engagement with nine bid documents sold, while Muktagacha drew only one.

In the third package, launched on 27 January, the BPDB proposed 19 solar plants totalling 1,780MW. After three deferrals, the submission deadline is now 22 May. 

Of 42 bid documents sold, the Moulvibazar substation (100MW) received the highest interest with six documents, while seven 100MW plants attracted just one bid each. Proposed plants at Pekua (70MW) and Gopalganj (100MW) saw no bids at all.

The fourth package, the largest in capacity, involves 14 plants with a total output of 2,605MW. Originally slated for submission on 28 May and now pushed to 18 June, this package has seen just seven bid documents sold. Nine plants – totalling 1,615MW – have yet to attract a single buyer.

Policy volatility undermines confidence

Industry insiders point to a series of abrupt policy shifts as the reason behind the dismal investor turnout.

In November 2023, the government revoked 31 solar power plant deals signed under the Quick Enhancement of Electricity and Energy Supply (Special Provision) Act – contracts awarded without competitive bidding.

These cancelled projects, totalling 3,287MW and backed by an estimated $6 billion in foreign investment, left investors blindsided. Fifteen companies have since filed 11 writ petitions with the High Court, seeking redress. Many had already secured land, set up offices, and were preparing to import machinery.

"The cancellations have had a chilling effect on investor sentiment," said Shafiqul Alam, lead analyst at the Institute for Energy Economics and Financial Analysis (IEEFA). "Many of these investors had been preparing for years."

BPDB officials concede that interest remains tepid, and further deadline extensions may be necessary. "For packages 3 and 4, we initially allowed only a month for bid submissions," said one official. "This time we're giving over two months. Still, response remains far below expectations."

Outreach efforts fall flat

The BPDB has reached out to multilateral lenders like the World Bank, Asian Development Bank, and local financier Infrastructure Development Company (IDCOL) to promote the tenders. 

It has also engaged with diplomatic representatives from more than a dozen countries, including the US, UK, Japan, Germany, and China. But the results remain underwhelming.

Hasan Mehedi, chief executive of the Coastal Livelihood and Environmental Action Network (CLEAN), also attributed the lack of traction to inconsistent policy signals. 

"The government's arbitrary cancellation of contracts has damaged investor trust," he said. "If the interim government wants to restore credibility, it must assure policy continuity."

When asked what kinds of responses BPDB is getting from investors, Md Rashedul Haq Prodhan, secretary of BPDB, said, "We can't say anything definitively until we find how many bidders finally dropped their bids."

Top News

Solar Power / Renewable Energy / Electricity

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Amid rumours, ISPR publishes complete list of those sheltered in cantonments after Hasina’s ouster
    Amid rumours, ISPR publishes complete list of those sheltered in cantonments after Hasina’s ouster
  • Bangladesh Bank Governor Ahsan H Mansur. TBS Sketch
    Inflation expected to drop to 5% by end of 2025: BB governor
  • Govt eats the crow – backtracks on implementing NBR split, for now
    Govt eats the crow – backtracks on implementing NBR split, for now

MOST VIEWED

  • How Renata's Tk1,000cr investment plan became a Tk1,400cr problem
    How Renata's Tk1,000cr investment plan became a Tk1,400cr problem
  • Govt officials to get up to 20% dearness allowance
    Govt officials to get up to 20% dearness allowance
  • File Photo: Mumit M/TBS
    Bangladesh to introduce new banknotes before Eid-ul-Adha
  • National Security Adviser Khalilur Rahman speaks at a press briefing at the Foreign Service Academy on 21 May 2025. Photo: PID
    No talks on Myanmar corridor, only discussed channelling aid with UN: Khalilur Rahman
  • Protestors block the intersection in front of InterContinental Dhaka on 22 May 2025. Photo: Syed Zakir Hossain/TBS
    Traffic at a standstill amid multiple protests on city streets
  • NBR officials hold press conference on 21 May 2025. Photo: TBS
    NBR officials announce non-cooperation from today, call for nationwide strike from Saturday

Related News

  • Govt plans renewable energy, eco-tourism on unused tea estate land
  • Renewable energy pitch will not yield fruit until institutional change
  • EIB to provide €350 million loan for Bangladesh's renewable energy projects
  • Govt plans ‘some load-shedding’ to ease subsidy pressure
  • Some amount of load-shedding in summer unavoidable: Adviser Fouzul

Features

Shantana posing with the students of Lalmonirhat Taekwondo Association (LTA), which she founded with the vision of empowering rural girls through martial arts. Photo: Courtesy

They told her not to dream. Shantana decided to become a fighter instead

1d | Panorama
Football presenter Gary Lineker walks outside his home, after resigning from the BBC after 25 years of presenting Match of the Day, in London, Britain. Photo: Reuters

Gary Lineker’s fallout once again exposes Western media’s selective moral compass on Palestine

1d | Features
Fired by US aid cuts, driven by courage: A female driver steering through uncertainty

Fired by US aid cuts, driven by courage: A female driver steering through uncertainty

2d | Features
Photo: TBS

How Shahbagh became the focal point of protests — and public suffering

3d | Panorama

More Videos from TBS

How did Musk become Trump's political weapon?

How did Musk become Trump's political weapon?

49m | Others
BNP wants elections and resignation of questionable advisors within this year

BNP wants elections and resignation of questionable advisors within this year

3h | TBS Today
Qatar's luxury Boeing in Trump's hands: a diplomatic understanding wrapped in a gift or a contract?

Qatar's luxury Boeing in Trump's hands: a diplomatic understanding wrapped in a gift or a contract?

1h | Others
‘Intolerable burden’: Businesses sound alarm on extortion, crime spikes

‘Intolerable burden’: Businesses sound alarm on extortion, crime spikes

4h | TBS Insight
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab