Payra power ready for December launch, new challenges await | The Business Standard
Skip to main content
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Get the Paper
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Sunday
July 20, 2025

Sign In
Subscribe
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Get the Paper
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
SUNDAY, JULY 20, 2025
Payra power ready for December launch, new challenges await

Bangladesh

Eyamin Sajid
24 August, 2019, 01:10 pm
Last modified: 25 August, 2019, 11:54 am

Related News

  • 2nd unit of Payra power plant to shut down over coal shortage
  • Payra-Dhaka power connectivity trial run begins Thursday
  • Payra Power Plant's coal import bills, loan payment stuck over dollar crisis
  • Second unit of Payra 1,320MW power plant resumes production
  • Power flow established at Rampal power plant sub station from Payra plant

Payra power ready for December launch, new challenges await

Within June next year, the plant will go for full operation.

Eyamin Sajid
24 August, 2019, 01:10 pm
Last modified: 25 August, 2019, 11:54 am

The country’s first mega coal-fired power plant in Payra is set to begin partial operation from December and help speed up industrialisation but with a set of new challenges.

Power Board sources said that the Chinese-built 1320 megawatt plant is already 81 percent complete and is far ahead of the constructions of Indian Rampal and the Japanese Matarbari mega coal power projects.

Initially, the plant is expected to generate 600 megawatts using coal imported from Indonesia. Within June next year, the plant will go for full operation.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

While this is an exciting news for a country that reeled in energy crisis for more than two decades, the Payra 1320 megawatt power plant demands that the nation handles a set of challenges that it had never dealt with before.

To run this plant alone in its full capacity, the country would have to import around 4 million tonnes of coal from Indonesia a year. The handling of such a huge volume of coal is a technical and environmental challenge.

This would impose an energy import bill of US 400 million dollars, on top of $3.5 billion dollars the nation is spending for import of Liquefied Natural Gas (LNG) per year.

While spending so much money for primary energy to feed the power plant, the government faces the challenges of finding adequate customers to buy the power. A new 1320 mw plant can feed general customers of at least six or seven districts. 

Till date, the biggest power plant to come into operation is the AES Meghnaghat 450mw power project. But when that project came into operation two decades ago, the country had frequent power outage problems—a scenario that no longer exists today. 

The deal for the Payra 1320 megawatt thermal coal power project was signed in late 2014 and was supposed to come into operation from December 2018. While being one year behind the schedule, it is doing much better than the Rampal plant that was signed in 2013 with the initial goal to complete it within three years. This plant is now expected to come into operation in 2021 alongside the 1200 mw Japan-funded Matarbari plant. The Matarbari deal was also signed before the Payra project. 

The cost of power from Payra plant would be close to Tk 7 per kilowatt hour—which is on par with other recent coal power projects, but more than double the price of the Meghnaghat power project.

Power Division data show that the country is currently working on 19 coal-based power plants which comprise the capacity of a total of 18,392 megawatts. 

However, there is no visible progress in these projects except the Matarbari, Payra and Rampal power projects. 

To supply coal to Payra plant, the government has signed a contract with PT Bayan Resources Tbk, an Indonesia-based coal mining company. Large ships carrying the coal will anchor at the deep sea near the Payra port, allowing smaller ships to unload the coal and deliver it to the plant. 

This tedious and costly arrangement will continue till the construction of Payra deep seaport is complete over the next few years. 

The success story

While most large power projects typically face several years’ delay in completion, how did the Payra project finish almost in time?

The project implementing agency credits this success to a transparent land acquisition process and a resettlement programme, multi-tasking plan and above all, a good leadership. Disputes over land acquisition and resettlement can often eat up project implementation time. 

“Teamwork was the main factor behind this success. Besides, the workplan also played a vital role as we have been working in a parallel system rather than sequential system,” said Shah Abdul Maula, project director of the Payra plant.  

Power experts however partially credit quick land development work for the project to other agencies. As the government is developing Payra as a deep seaport, the land filling work was already in progress when the power project’s implementation began. The Payra power project authorities did not have to face this hurdle, something the Matarbari and Rampal projects had to face.

Financial closure and environmental clearances for this project also came faster than the two other projects.

“The Payra power plant has been implemented by China, with Chinese fund. We know that Chinese projects progress faster than those financed by other countries. This was the main factor behind the early arrival of Payra power project,” said Power Cell’s Director General Mohammad Hossain. 

But BD Rahmatullah, former director of Power Cell, questions the quality of work and the equipment import process. 

He said, “An early handover of a project is not the main benchmark when the project is being implemented by Chinese firms not having good international reputations. 

“The quality of equipment and work should be monitored because it will be the prime issue after commissioning the project,” he added.  

Every procurement for Payra power project was done through a direct tender process that lacks accountability and transparency. 

Infograph / Top News / Energy

Payra 1320 MW Thermal Power Plant / Payra plant

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Photo: Collected
    BNP alleges arrests, harassment of innocent civilians in Gopalganj's Kotalipara
  • Army patrol amid curfew in Gopalganj on 17 July 2025. Photo: Olid Ebna Shah/TBS
    Curfew, Section 144 withdrawn in Gopalganj
  • Bangladesh seal commanding T20 win over Pakistan in Mirpur
    Bangladesh seal commanding T20 win over Pakistan in Mirpur

MOST VIEWED

  • Photo: Collected
    Most expensive car crash in Bangladesh as Rolls-Royce hits road divider on 300 Feet
  • Screengrab from video
    Jamaat Ameer Shafiqur collapses on stage mid-speech at Suhrawardy rally
  • Renata’s Mirpur facility earns Bangladesh’s first EU GMP
    Renata’s Mirpur facility earns Bangladesh’s first EU GMP
  • Bangladesh's Chief of Army Staff General Waker-uz-Zaman gestures during an interview with Reuters at his office in the Bangladesh Army Headquarters, in Dhaka, Bangladesh, 23 September 2024. Photo: Reuters
    Army chief stresses discipline, humanitarian values for national progress
  • Jamaat holds its first-ever Suhrawardy Udyan rally at Suhrawardy Udyan on 19 July 2025. Photo: Jamaat-e-Islami/Facebook
    Elections under PR system most appropriate now, Jamaat’s Taher tells Suhrawardy rally
  • Infograph: TBS
    Liquidation of troubled NBFIs may cost govt Tk12,000cr in taxpayer money

Related News

  • 2nd unit of Payra power plant to shut down over coal shortage
  • Payra-Dhaka power connectivity trial run begins Thursday
  • Payra Power Plant's coal import bills, loan payment stuck over dollar crisis
  • Second unit of Payra 1,320MW power plant resumes production
  • Power flow established at Rampal power plant sub station from Payra plant

Features

Despite all the adversities, girls from the hill districts are consistently pushing the boundaries to earn repute and make the nation proud. Photos: TBS

Despite poor accommodation, Ghagra’s women footballers bring home laurels

3h | Panorama
Photos: Collected

Water-resistant footwear: A splash of style in every step

5h | Brands
Tottho Apas have been protesting in front of the National Press Club in Dhaka for months, with no headway in sight. Photo: Mehedi Hasan

From empowerment to exclusion: The crisis facing Bangladesh’s Tottho Apas

22h | Panorama
The main points of clashes were in Jatrabari, Uttara, Badda, and Mirpur. Violence was also reported in Mohammadpur. Photo: TBS

20 July 2024: At least 37 killed amid curfew; Key coordinator Nahid Islam detained

22h | Panorama

More Videos from TBS

Hasina government's close associates are giving up ownership of property in the UK

Hasina government's close associates are giving up ownership of property in the UK

2h | Others
Sculptor Hamiduzzaman Khan's death marks the end of a colorful life

Sculptor Hamiduzzaman Khan's death marks the end of a colorful life

2h | Others
News of The Day, 20 JULY 2025

News of The Day, 20 JULY 2025

2h | TBS News of the day
Are good relations being developed between political parties?

Are good relations being developed between political parties?

2h | TBS Stories
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net