Padma Bridge just a span away | The Business Standard
Skip to main content
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Get the Paper
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Wednesday
July 23, 2025

Sign In
Subscribe
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Get the Paper
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
WEDNESDAY, JULY 23, 2025
Padma Bridge just a span away

Bangladesh

Jahidul Islam
04 December, 2020, 11:10 pm
Last modified: 05 December, 2020, 02:26 pm

Related News

  • Evidence of irregularities, graft found in Padma Bridge consultant appointments: ACC chief
  • Padma Bridge marks 3yrs of operation, over Tk2,500 crore toll collected
  • Around Tk60cr toll collected on Padma, Jamuna bridges during holidays
  • 2 dead, 10 injured as bus crashes into truck on Padma Bridge in Munshiganj
  • Padma Bridge sets new records for daily toll collection, vehicle crossings

Padma Bridge just a span away

With the installation of the 41st span, the entire frame of the 6.15-kilometre bridge will be noticeable in the next week

Jahidul Islam
04 December, 2020, 11:10 pm
Last modified: 05 December, 2020, 02:26 pm
The Padma Bridge is Bangladesh’s largest infrastructure project till date, Photo: Mumit M
The Padma Bridge is Bangladesh’s largest infrastructure project till date, Photo: Mumit M

The mega dream project – Padma Multipurpose Bridge – is just 150 metres away from the accentuation of its entire structure.

With the installation of the 41st span of 150-metre length, the entire frame of the 6.15-kilometre bridge will be noticeable in the next week.

The 40th span was installed on Friday, which lengthened 6 kilometres of the mega structure.      

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

Padma Bridge Executive Engineer Dewan Abdur Quader said the span was placed near pillar no. 11 and 12 on Thursday and installed successfully on Friday at 10:58am.

He added that the 41st span will be set up before the upcoming Victory Day and the whole framework of the dream bridge will be visible.

The last span is ready at Mawa construction yard, he continued.

Minister for Road Transport and Bridges Obaidul Quader on Friday said, "There is only one span left to install. I hope it will be done within 10 December. "

According to project officials, a number of four spans were installed each in October and November.

The 40th span was installed 7 days after the installation of the 39th span.

Even though the work of span installation is in the final stage, the work of the entire project will not be completed by June next year, said Project Director Md Shafiqul Islam.

He also noted that the work of the bridge might stretch well into the year of 2022 due to delay caused by the pandemic.

Project stakeholders said apart from span placement, other associated works are also underway.

So far, the overall progress of the bridge project is 81%. Of this, 90% of the main bridge work has already been completed.

Work on Service Area-2 and Jazira connecting road has already been done and 75% of the river management work has also been completed.

The two-storey bridge of metal and concrete structure will allow cars to run on the upper floor and trains on the lower floor.

There will be 2,917 roadway slabs for roads and 2,959 railway slabs for trains.

Of these, 1,239 road slabs and 1,860 rail slabs have been installed as per information till 30 November.

The construction work on the Padma Bridge started in December 2014 with the government's own funding after a tussle with donors.

The bridge became visible on 30 September 2016 with the installation of the first span on pillars no. 36 and 37.

China Major Bridge Engineering Company (MBEC) – a Chinese contractor – is working on the construction of the main bridge while SinoHydro Corporation – another Chinese company – is working on river management.

When the work will end

In 2007, the Executive Committee of the National Economic Council (Ecnec) approved the Padma Bridge construction project at a cost of Tk10,162 crore.

The bridge was supposed to be commissioned by 2013 at the time of design. In 2011, the expenditure was increased to Tk20,507 crore.

The cost of the project was raised to Tk28,793 crore in 2016 through a second amendment and to Tk30,193 crore in 2018. Thus, the project expenditure has tripled.

According to sources, the Planning Commission has extended the project till June next year on the condition of not sending any amendment proposal.

However, the work will not be completed by that time, said Project Director Shafiqul Islam.

Shafiqul told The Business Standard that work on the bridge has been delayed due to the coronavirus.

Although all span installations were supposed to be completed within last June, it was not possible due to the pandemic, and so, it will be impossible to finish everything within the next June, said the project director.

Asked about the commissioning date of the bridge, Shafiqul added that the bridge authorities have not announced any date, however, they have been informed that the work of the bridge will not be completed next year.

Controversy from the beginning

In order to ensure better connectivity for people in 19 districts in the southwestern region of the country, the government took up the $2.9 billion mega bridge project to which the World Bank pledged $1,200 million, ADB $615 million, Jica$415 million and IDB $140 million credit.

However, the World Bank decided to refrain from financing the project due to allegations of corruption. Other donors also followed suit.

But, rejecting the allegations of corruption, Bangladesh decided to build the bridge with its own funds.

At one point, allegations of corruption were proved unfounded in a Canadian court. An investigation by the Anti-Corruption Commission in Bangladesh also found no proof of the allegations.

After the start of work, various complexities including design errors, structural complexities of the river bed and a lack of navigability of the river caused the delay in the bridge work.

As the pandemic hit, foreign consultants and skilled workers left the project area, thus creating a bar to the desired progress of the dream project.

Top News

Padma Bridge / span installation

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • TBS Illustration
    Dhaka proposes third-round tariff talks on Sunday, awaits US response
  • The Government Seal of Bangladesh
    Govt mulls allowing trade unions with 20 workers, industry leaders warn of disorder
  • Photo: CA Press Wing
    Stronger stance needed on maintaining law and order: Political parties to CA

MOST VIEWED

  • Screengrab/Video collected from Facebook
    CCTV footage shows how Air Force jet nosedived after technical malfunction
  • Photo: Collected
    Bangladeshi man jailed for life in UK for murdering wife in front of their baby
  • Why Bangladesh's capital market is poised for a bull run
    Why Bangladesh's capital market is poised for a bull run
  • ISPR clarifies crashed plane was battle aircraft, not training jet
    ISPR clarifies crashed plane was battle aircraft, not training jet
  • Photo: Syed Zakir Hossain/TBS
    Secretariat protest: 75 injured in police-protester clash over edu adviser's resignation for delaying HSC rescheduling
  • Exim Bank's former chairman Nazrul Islam Majumder being taken to court on 22 July 2025. Photo: Collected
    Will repay all money if granted bail, won’t run away, ex-Exim Bank chair Nazrul tells court

Related News

  • Evidence of irregularities, graft found in Padma Bridge consultant appointments: ACC chief
  • Padma Bridge marks 3yrs of operation, over Tk2,500 crore toll collected
  • Around Tk60cr toll collected on Padma, Jamuna bridges during holidays
  • 2 dead, 10 injured as bus crashes into truck on Padma Bridge in Munshiganj
  • Padma Bridge sets new records for daily toll collection, vehicle crossings

Features

Photo: Mehedi Hasan/TBS

Aggrieved nation left with questions as citizens rally to help at burn institute

20h | Panorama
Photo: TBS

Mourning turns into outrage as Milestone students seek truth and justice

14h | Panorama
Illustration: TBS

Uttara, Jatrabari, Savar and more: The killing fields that ran red with July martyrs’ blood

1d | Panorama
Despite all the adversities, girls from the hill districts are consistently pushing the boundaries to earn repute and make the nation proud. Photos: TBS

Ghagra: Where dreams rise from dust for Bangladesh women's football

2d | Panorama

More Videos from TBS

Six unidentified bodies are yet to be identified

Six unidentified bodies are yet to be identified

35m | TBS Today
32 killed in warplane crash in Milestone, live from Burn Institute

32 killed in warplane crash in Milestone, live from Burn Institute

2h | TBS Today
What information did the director of the NBPSI give about the admitted patients?

What information did the director of the NBPSI give about the admitted patients?

12h | TBS Today
India is sending specialist doctors, nurses and equipment to treat burn victims

India is sending specialist doctors, nurses and equipment to treat burn victims

3h | TBS Today
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net