Russia agrees to extend loan disbursement for Rooppur until 2026 | The Business Standard
Skip to main content
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Monday
June 30, 2025

Sign In
Subscribe
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
MONDAY, JUNE 30, 2025
Russia agrees to extend loan disbursement for Rooppur until 2026

Energy

Shaikh Abdullah & Saifuddin Saif
27 February, 2025, 12:30 am
Last modified: 27 February, 2025, 02:38 pm

Related News

  • NCP blames BNP, allies for stalemate in reform progress
  • DSE extends winning streak for 5th day
  • Export container transport resumes from ICDs to Ctg Port as customs officers end protest
  • Leadership crisis deepens at DSE
  • Gun magazine found in Adviser Asif’s bag at airport; unintentionally packed, he clarifies

Russia agrees to extend loan disbursement for Rooppur until 2026

During a meeting with Chief Adviser Muhammad Yunus yesterday, Rosatom Director General Alexey Likhachev agreed to revise the Intergovernmental Credit Agreement (IGCA), extending the credit utilisation period until the end of 2026.

Shaikh Abdullah & Saifuddin Saif
27 February, 2025, 12:30 am
Last modified: 27 February, 2025, 02:38 pm
Infographics: TBS
Infographics: TBS

Russian nuclear corporation Rosatom has agreed to extend the credit utilisation period by two years for the Rooppur Nuclear Power Plant (RNPP), a key project for strengthening Bangladesh's energy security.

During a meeting with Chief Adviser Muhammad Yunus yesterday (26 February), Rosatom Director General Alexey Likhachev agreed to revise the Intergovernmental Credit Agreement (IGCA), extending the credit utilisation period until the end of 2026.

In this regard, the two sides agreed to sign Protocol No. 2 to the agreement shortly, while complying with all the necessary formalities, said the CA's Press Wing in a press release.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

According to Economic Relations Division (ERD) sources, the total cost of the Rooppur project is estimated at $12.65 billion, with 90%, or $11.38 billion, funded by a loan from the Russian government and 10% covered by Bangladesh's own financing. Under the agreement, the loan was due for disbursement by December 2024.

Bangladesh has so far received around $7.70 billion from Russia. The government could not receive the entire amount due to a slowdown in work during the Covid pandemic and later due to the impact of the Russia-Ukraine war.

Consequently, Bangladesh in June 2024 requested the Russian authorities to extend the loan disbursement period until December 2026. However, the response was delayed due to US sanctions, which had left Russian bills stuck in Bangladesh. In 2022, following Russia's involvement in Ukraine, the US imposed sanctions on Russia's bank for transactions related to the Rooppur plant, preventing Bangladesh from making payments.

Once the agreement is revised, the government will receive the remaining $3.68 billion from Russia by December 2026.

Both the chief adviser and the Rosatom director general also emphasised the importance of continued cooperation in areas such as staff training, safety protocols, and knowledge transfer to ensure the long-term success of the project, added the CA's Press Wing's statement.

CA wants to expand cooperation

Chief Adviser Yunus told Likhachev, who arrived in Bangladesh on a one-day visit to discuss the issue, that Bangladesh looks forward to expanding cooperation in nuclear energy, focusing on shared interests and advancements in peaceful nuclear technology. The Rosatom director general last toured Bangladesh in April 2024.

The meeting, held at the chief adviser's official residence Jamuna, primarily addressed the ongoing collaboration between Bangladesh and Russia in developing the former's first nuclear power plant.

During the discussions, Prof Yunus appreciated Rosatom's continued support in the construction of the plant and emphasised the timely completion of the project with a view to meeting Bangladesh's growing energy needs.

"We are looking forward to your support, which is very important for us," the chief adviser told the Rosatom director general.

Work progressing as planned

Likhachev shared updates on the Rooppur plant, emphasising that the construction work is progressing as planned, with multiple milestones already achieved. "Any choice the people of Bangladesh make is sacred for us," he said.

He informed Yunus that the dry run of the project is ongoing while the test run will commence soon.

A dry run of the power plant will involve rehearsal of a process or operation without the actual materials or resources that would be used in a real-world scenario.

A test run is a more advanced stage of testing that involves operating the systems with the actual materials or resources.

He also assured that Rosatom remains committed to facilitating the successful completion of the project, with a strong focus on safety, quality, and compliance with international standards.

Among others, Principal Secretary Siraj Uddin Mia, Senior Science and Technology Secretary Md Mokabbir Hossain, and ERD Secretary Md Shahriar Kader Siddiky were present during the meeting.

From the Russian side, Russian Ambassador to Bangladesh Alexander Khozin, Deputy Chairman of the Federal Environmental, Industrial, and Nuclear Supervision Service Alexey Feropontov, Rosatom's First Deputy Director General Andrey Petrov, and Vice President of ASE JSC and Project Director of Rooppur NPP Alexey Deriy accompanied the Rosatom director general at the meeting.

Russia's positive response

ERD Secretary Shahriar told The Business Standard, "Russia has positively responded to the proposal to extend the loan disbursement period, and we are taking steps to ensure all relevant agencies are fully operational to complete the project on time."

The Russian delegation held a preparatory meeting with the ERD on 25 February, ahead of the meeting with the chief adviser. Officials from the ERD, science and technology ministry, and the Rooppur Nuclear Power Plant were present, and discussions focused on extending both the loan disbursement and repayment periods.

According to the agreement, the first instalment of repayment is due on 15 March 2027. However, since the entire amount was not released on time, Dhaka has proposed starting repayments on 15 March 2029. The matter is expected to be finalised during the protocol signing.

Bangladesh currently owes the Russian government $750 million, including $450 million for the feasibility study of the plant, with the remainder being interest on the current loan and outstanding interest.

Unit-1 94% complete, Unit-2 76%

Senior Secretary to science and technology ministry Md Mokabbir Hossain told TBS that Unit-1 of the plant is 94% complete, and Unit-2 is 76% complete. With the loan disbursement period extended, the remaining work can now proceed quickly.

According to the Implementation Monitoring and Evaluation Division, 67.8% of the physical work of the Rooppur plant construction project was completed as of October last year, with financial progress similarly on track.

The project was scheduled for completion in December 2025. The first shipment of nuclear fuel from Russia arrived in Dhaka on 28 September 2023, and was officially handed over in a ceremony on 5 October 2023, attended virtually by Russian President Vladimir Putin and then prime minister Sheikh Hasina.

At the event, Putin said Bangladesh's Rooppur power plant would be fully operational by 2026.

With the receipt of uranium from Russia, Rooppur is now an internationally recognised nuclear facility. However, there are concerns about the plant's full operation in 2026 due to delays in the construction of a special transmission line required to supply electricity to the national grid.

Plant will add 2,400MW to national grid

Once completed, the plant will add 2,400MW to the national grid. The grid line installation was originally scheduled for completion in 2023 but was delayed, and the new target of October 2024 also went unmet.

The Power Grid Bangladesh, responsible for the installation, has now said the work will be completed by March, although project insiders believe full installation will not be finished by then.

Ambassador M Humayun Kabir, president of the Bangladesh Enterprise Institute, told TBS that Russia's decision to extend the loan disbursement period is a positive development, acknowledging Bangladesh's situation.

He described it as a challenge for Bangladesh and praised the decision as a thoughtful response. Kabir also said there are no significant activities with Russia aside from this project, and trade between the two countries is limited. Additionally, Russia is under US sanctions, and any potential for business expansion would depend on the lifting of those sanctions.

Rooppur plant Project Director Md Zahedul Hassan told TBS that the construction has been delayed due to several factors, including the pandemic, the Russia-Ukraine war, and grid line installation.

Currently, 75% of the project is complete, and it is expected to be fully operational by 2026 if all goes well.

He added that by 2025, one unit will generate electricity for the national grid. The installation of main equipment is complete, and the pipeline for electricity generation through heat was tested two days ago, with start-up and adjustment work currently underway.

Bangladesh / Top News

Rooppur Nuclear Power Plant project / Russia / Bangladesh

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • File photo of Chattogram Port/TBS
    Ctg port to dispatch 7,000 containers today after two-day NBR 'complete shutdown'
  • Bank holiday: Transactions, stock markets to remain suspended tomorrow
    Bank holiday: Transactions, stock markets to remain suspended tomorrow
  • A Chevron gas station sign is seen in Del Mar, California, April 25, 2013. Chevron will report earnings on April 26. REUTERS/Mike Blake
    Chevron to resume Jalalabad gas project after Petrobangla clears $237m dues

MOST VIEWED

  • Representational image. File Photo: Rajib Dhar/TBS
    Gold prices drop by Tk4,292 within a week
  • Return to work or face stern action, govt warns protesters as NBR jobs declared 'essential services'
    Return to work or face stern action, govt warns protesters as NBR jobs declared 'essential services'
  • Representational image/Collected
    5 arrested over Cumilla's Muradnagar rape, circulation of video 
  • Officials of the NBR, under the banner of the NBR Unity Council, continued their protest on Sunday since 9am. Photo: Syed Zakir Hossain/TBS
    NBR staff call off protest as govt goes tough
  • Remittance inflow hits record $30b in FY25
    Remittance inflow hits record $30b in FY25
  • Record $30b remittance lifts reserves to $26b
    Record $30b remittance lifts reserves to $26b

Related News

  • NCP blames BNP, allies for stalemate in reform progress
  • DSE extends winning streak for 5th day
  • Export container transport resumes from ICDs to Ctg Port as customs officers end protest
  • Leadership crisis deepens at DSE
  • Gun magazine found in Adviser Asif’s bag at airport; unintentionally packed, he clarifies

Features

Photo: Collected

Innovative storage accessories you’ll love

22h | Brands
Two competitors in this segment — one a flashy newcomer, the other a hybrid veteran — are going head-to-head: the GAC GS3 Emzoom and the Toyota CH-R. PHOTOS: Nafirul Haq (GAC Emzoom) and Akif Hamid (Toyota CH-R)

GAC Emzoom vs Toyota CH-R: The battle of tech vs trust

23h | Wheels
Women farmers, deeply reliant on access to natural resources for both farming and domestic survival, are among the most affected, caught between ecological collapse and inadequate structural support. Photo: Shaharin Amin Shupty

Hope in the hills: How women farmers in Bandarban are weathering the climate crisis

15h | Panorama
How a young man's commitment to nature in Tetulia won him a national award

How a young man's commitment to nature in Tetulia won him a national award

1d | Panorama

More Videos from TBS

Two firefighters killed in Idaho shooting

Two firefighters killed in Idaho shooting

1h | TBS World
'An advisor is abusing power in Muradnagar for his own interests'

'An advisor is abusing power in Muradnagar for his own interests'

14h | TBS Stories
NBR officials announce withdrawal of protest at joint press conference

NBR officials announce withdrawal of protest at joint press conference

14h | TBS Today
Trump is not making any concessions to India: The Economist

Trump is not making any concessions to India: The Economist

5h | Others
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net