Planning Commission suggests cost cut in revised Padma Bridge project | The Business Standard
Skip to main content
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Sunday
June 08, 2025

Sign In
Subscribe
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
SUNDAY, JUNE 08, 2025
Planning Commission suggests cost cut in revised Padma Bridge project

Bangladesh

Jahidul Islam
18 April, 2023, 10:10 am
Last modified: 18 April, 2023, 10:19 am

Related News

  • Padma Bridge sets new records for daily toll collection, vehicle crossings
  • Homebound rush begins: Padma Bridge and Dhaka-Chattogram highway keep Eid travel smooth
  • Inflation eased in April due to monetary, fiscal measures: Planning Commission report
  • Planning Commission nods to trimmed-down Tk2.3 lakh crore ADP for FY26
  • Padma Bridge protection embankment at risk of collapse from soil erosion

Planning Commission suggests cost cut in revised Padma Bridge project

Jahidul Islam
18 April, 2023, 10:10 am
Last modified: 18 April, 2023, 10:19 am
Padma Bridge. Photo: TBS
Padma Bridge. Photo: TBS

The Planning Commission has questioned the rationale behind the cost hike in the proposed third revision of the Padma Multipurpose Bridge Project, noting that costs in some sectors need to be reduced for final approval.

The revised proposal is expected to be placed in the Executive Committee of the National Economic Council (Ecnec) meeting on Tuesday, according to sources at the commission.

Although the Padma Bridge was opened to traffic in June last year, work on some elements of the project is still underway. Besides, due payments for the work done need to be cleared. Hence, the project has been revised for the 3rd time.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

The Bridges Division sent the revised proposal to the Planning Commission in January, seeking an additional Tk2,682.13 crore and an extension of tenure by another year. 

According to the revised proposal, the reasons for the additional fund include the devaluation of the taka against the US dollar, design change in pile foundation, increase in VAT (value-added tax) and income tax due to change in legislation, increased cost due to the design of 400kV transmission tower foundation platforms, and design change in Mawa River training work, additional works related to operation and maintenance and other civil works and bridge opening ceremony, etc.

At the Project Evaluation Committee (PEC) meeting held in March, the Planning Commission sought an explanation from the Bridges Division for the cost increase in some sectors, including allowances of officials and consultants, purchasing computers and accessories, and work on main bridges and river management.

The minutes of the meeting, signed by the member (secretary) of the Physical Infrastructure Division of the Planning Commission, Mohammad Emdad Ullah Mian, have been sent to various departments, including the Bridges Division.

According to the proposal, the project authority has already spent 1.5 to 8.5 times the sanctioned allocation in various sectors of the project and sought fresh allocation, which is 16 times higher than the approved amount. The commission said such an increase in expenditure goes against planning discipline.

In the evaluation committee meeting, a decision was made to approve the proposal on condition that the project implementing agency will review and readjust some of the additional expenditures and complete all project works by June next year, as mentioned in the proposal.

What project officials say

According to project officials, the increase in VAT and income tax rates and devaluation of currency led to additional expenditure in several sectors.

As per the third revised proposal, the project cost will now increase to Tk32,875.54 crore, which in the second revision was estimated to be at Tk30,193.38 crore.

In the meeting, Project Director Safiqul Islam said, the increase in VAT and income tax rates for the construction work raised the cost by Tk687 crore (Tk405 crore for the main bridge and Tk282 crore for river management). Besides, the cost has also increased due to the increase in VAT and income tax of consultants.

He also said the dollar exchange rate was Tk78.30 at the time of the contract, which now stands at Tk107. As a result, about Tk200 crore more will be required.

In addition, an additional 43 months of work on the main bridge and 55 months of work on river management have increased the expenditure by Tk727 crore, the project director said.

Moreover, additional expenditure has been sought for electricity connection, entertainment and other ancillary works — to which the Planning Commission objected.

When asked about lowering costs, Manjur Hossain, Secretary of the Bridges Division, told The Business Standard (TBS), "It will be possible to reduce expenditure in some sectors. However, as the contract with the contractor is about to expire in June this year, the project proposal needs to be approved quickly to clear the remaining bills for the work on the main bridge."

According to officials of the Bangladesh Bridge Authority (BBA), most of the works, for which funds were sought in the third revision, have been completed. The new financing is now needed to pay the bills.

Project details

According to Planning Commission sources, the Padma Bridge project was approved in August 2007 at a cost of Tk10,162 crore with loans from various organisations, including the World Bank.

Although the work was supposed to be completed by June 2015, the cost was increased to Tk20,507 crore, and the tenure was extended by six months in the first revision of the project.

The second revision was approved in February 2015, increasing the cost to Tk28,793 crore with 100% internal financing due to the cancellation of loans from the World Bank and other lenders. In this revision, the project deadline was set in December 2018.

Later, in the special revision, the cost of the project was further increased to Tk30,193.39 crore with a deadline of June 2023. *

 

Top News

Planning Commission / Padma Bridge

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • File Photo: British MP Tulip Siddiq attends a news conference with Richard Ratcliffe, the husband of jailed British-Iranian aid worker Nazanin Zaghari-Ratcliffe, in London, Britain October 11, 2019. Photo: REUTERS/Peter Nicholls/File Photo
    Tulip requests meeting with CA Yunus over corruption allegations: Guardian
  • Dhaka South City Corporation collecting waste from different areas under its jurisdiction following Eid-ul-Adha celebrations. Photo: TBS
    City corporations claim full waste removal, yet Eid waste visible on Dhaka streets
  • According to the Department of Livestock, around 9 lakh animals were sacrificed in Chattogram this year. Photo: Collected
    Seasonal traders count losses as sacrificial animal rawhides left unsold in Chattogram, donated to orphanages

MOST VIEWED

  • Army Chief General Waker-Uz-Zaman and his wife exchange Eid greetings with Chief Adviser Muhammad Yunus at the State Guest House Jamuna in Dhaka today (7 June). Photo: CA Press Wing
    Army chief exchanges Eid greetings with CA Yunus
  • Photo collage shows political posters in Bagerhat. Photos: Jannatul Naym Pieal
    From Sheikh Dynasty to sibling rivalry: Bagerhat signals a turning tide in local politics
  • BNP Standing Committee criticises chief adviser's speech, calls for national election by December
    BNP Standing Committee criticises chief adviser's speech, calls for national election by December
  • Rawhide collected from various parts of the city. Photo taken on 7 June in Old Dhaka. Rajib Dhar/ TBS
    Rawhide prices see slight increase, but below fair value
  • CA’s televised address to the nation on the eve of the Eid-ul-Adha on 6 June. Photo: Focus Bangla
    National election to be held any day in first half of April 2026: CA
  • BNP leaders lay a wreath at the grave of BNP founder Ziaur Rahman at Sher-e-Bangla Nagar in Dhaka on 7 June 2025. Photo: BSS
    April not suitable for national polls: Fakhrul

Related News

  • Padma Bridge sets new records for daily toll collection, vehicle crossings
  • Homebound rush begins: Padma Bridge and Dhaka-Chattogram highway keep Eid travel smooth
  • Inflation eased in April due to monetary, fiscal measures: Planning Commission report
  • Planning Commission nods to trimmed-down Tk2.3 lakh crore ADP for FY26
  • Padma Bridge protection embankment at risk of collapse from soil erosion

Features

Photo collage shows political posters in Bagerhat. Photos: Jannatul Naym Pieal

From Sheikh Dynasty to sibling rivalry: Bagerhat signals a turning tide in local politics

1d | Bangladesh
Illustration: TBS

Unbearable weight of the white coat: The mental health crisis in our medical colleges

3d | Panorama
(From left) Sadia Haque, Sylvana Quader Sinha and Tasfia Tasbin. Sketch: TBS

Meet the women driving Bangladesh’s startup revolution

4d | Panorama
Illustration: TBS

The GOAT of all goats!

5d | Magazine

More Videos from TBS

Why do political parties have different opinions about the elections in April?

Why do political parties have different opinions about the elections in April?

3h | TBS Stories
Power shift in Chinese politics, Is Li Qiang emerging in Xi Jinping's shadow?

Power shift in Chinese politics, Is Li Qiang emerging in Xi Jinping's shadow?

19h | TBS World
Commercial cultivation of red and black grapes on the soil of Bangladesh

Commercial cultivation of red and black grapes on the soil of Bangladesh

6h | TBS Stories
Eid joy fills the capital, with residents busy performing animal sacrifices

Eid joy fills the capital, with residents busy performing animal sacrifices

1d | TBS Today
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net