Rooppur power generation to get delayed until July 2024 | The Business Standard
Skip to main content
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Saturday
May 24, 2025

Sign In
Subscribe
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
SATURDAY, MAY 24, 2025
Rooppur power generation to get delayed until July 2024

Energy

Eyamin Sajid
29 December, 2022, 02:30 pm
Last modified: 29 December, 2022, 10:44 pm

Related News

  • 18 engineers of Rooppur Nuclear Power Plant dismissed following week-long unrest
  • PDB to sign power purchase deal with Rooppur nuclear plant 
  • Russia extends Rooppur loan repayment by two years, waives $164m penalty
  • Turbine installed at unit-1 of Rooppur nuke plant
  • Rooppur nuclear plant runs hydraulic pressure tests

Rooppur power generation to get delayed until July 2024

Eyamin Sajid
29 December, 2022, 02:30 pm
Last modified: 29 December, 2022, 10:44 pm
Rooppur Nuclear Power Plant
Rooppur Nuclear Power Plant

Rooppur Nuclear Power Plant is going to miss the December 2023 deadline to go into production as German company Siemens AG has refused to supply the gas-insulated switchgear (GIS) for the project's substation.

Country's biggest ever project in terms of cost and foreign investment, Rooppur Nuclear Power Plant's first unit will not be able to start production before July 2024, but the authorities have decided to receive the GIS service from a Chinese firm, said officials from the project and the Ministry of Power on Thursday while visiting the Rooppur site at Ishwardi, Pabna.

Addressing the media after a meeting with project officials, State Minister for Power, Energy and Mineral Resources Nasrul Hamid, however, said the progress of the first unit of the plant is around 87% and the project of the power grid is also good.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

"But Covid caused a delay. We expect that the entire of next year will be needed and we would be able to evacuate power by mid-2024," he said.

Talking about the progress of the power transmission line, Nasrul Hamid said, "During the pandemic, engineers could not work. On the other hand, river crossing work was also delayed because of the tender process."

Secretary of the Power Division Habibur Rahman, Rooppur nuclear project's Director Dr Md Shawkat Akbar and Power Development Board Chairman Mahbubur Rahman also visited the project site Thursday.

Science Minister Yeafesh Osman had said on 18 October that the work of the project was going on as per scheduled time frame.

"We are hopeful of completing the project within the time," said Yeafesh Osman.

At that time, Project Director Shawkat also told the media that they were in the stage of commissioning work of the first unit, which they were expecting to start operation next October.

He also said the power plant's fuel, Uranium, was expected to reach Bangladesh in September 2023.

But, on Thursday, the project director claimed that the unit will be readied by June 2023.

"If all the supportive issues are settled, it would be ready to produce electricity by 2024," he added.

German company not supplying GIS service

A substation, through which the power plant's electricity would be connected to the national power transmission line, is due to be constructed by the same contractor that is implementing the plant.

However, German industrial manufacturing company Siemens AG recently rejected to supply the necessary items for the GIS service for the substation.

Subsequently, the general contractor decided to procure the equipment from an alternative supplier to comply with the terms of readiness of GIS for installation in November 2023, said Alexey Deiry, vice-president of Atomstroyexport, in a presentation on the update of the project Thursday at a meeting with the officials of power ministry.

Now, the authorities have selected Chinese firm SIEYUAN Electric Ltd to procure the necessary equipment.

Recent media reports claimed that a Russian ship carrying project materials for the Rooppur plant, currently under US sanctions, was denied permission to dock in Bangladesh.

Asked about the issue, the project director said, "This is a matter of the foreign ministry. They will be able to address this issue better."

Also asked if the ongoing Ukraine-Russia war has any impact on the project, he refused to comment on any effect of the Western sanctions on Russia.

Power purchase agreement by June

Rooppur nuclear project,  the maiden nuclear power generation project in Bangladesh,  is expected to be a cheaper and cleaner source of electricity.

The latest generation 3+ Russian VVER 1200 reactor will be used for power generation, which complies with all international safety requirements.

Regarding power tariff, the state minister said, "We are expecting that the per unit electricity rate would fluctuate between Tk4kWh to Tk5kWh.

We have already prepared the draft of the power purchase agreement (PPA) and hope it will be signed by the middle of the next year.

Bangladesh / Top News

Rooppur Nuclear Power Plant / Nuclear Energy

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • PKSF's Tk240cr scheme to guarantee bank loans for micro-financiers
    PKSF's Tk240cr scheme to guarantee bank loans for micro-financiers
  • Nahid Islam, head of National Citizens Party (NCP). File Photo: AFP
    Delhi-backed conspiracies afoot to orchestrate another '1/11' crisis after AL ban: Nahid
  • Savar Cantonment map. Screenshot from Google Maps
    515 cops among 626 sheltered at cantts after July uprising, 435 in Savar

MOST VIEWED

  • Amid rumours, ISPR publishes complete list of 626 individuals sheltered in cantonments after Hasina’s ouster
    Amid rumours, ISPR publishes complete list of 626 individuals sheltered in cantonments after Hasina’s ouster
  • Illustration: TBS
    Prof Yunus considering resignation: Nahid tells BBC Bangla after meeting CA
  • Govt backtracks for now on implementing NBR split
    Govt backtracks for now on implementing NBR split
  • Commuters sit on the floor at Shahbagh metro station amid an increased crowd on 22 May 2025. Photo: Sadiqe Al Ashfaqe/TBS
    Dhaka metro sees spike in passengers amid protest-choked city roads
  • The Advisory Council of the interim government holds a meeting at the state guest house Jamuna in Dhaka on 10 May 2025. Photo: PID
    What CA Yunus discussed with Advisory Council about 'resignation'
  • Five political parties hold meeting at the office of Inslami Andolan on 22 May 2025. Photo: Courtesy
    5 parties, including NCP and Jamaat, agree to support Yunus-led govt to hold polls after reforms

Related News

  • 18 engineers of Rooppur Nuclear Power Plant dismissed following week-long unrest
  • PDB to sign power purchase deal with Rooppur nuclear plant 
  • Russia extends Rooppur loan repayment by two years, waives $164m penalty
  • Turbine installed at unit-1 of Rooppur nuke plant
  • Rooppur nuclear plant runs hydraulic pressure tests

Features

The well has a circular opening, approximately ten feet wide. It is inside the house once known as Shakti Oushadhaloy. Photo: Saleh Shafique

The last well in Narinda: A water source older and purer than Wasa

8h | Panorama
The way you drape your shari often depends on your blouse; with different blouses, the style can be adapted accordingly.

Different ways to drape your shari

10h | Mode
Shantana posing with the students of Lalmonirhat Taekwondo Association (LTA), which she founded with the vision of empowering rural girls through martial arts. Photo: Courtesy

They told her not to dream. Shantana decided to become a fighter instead

2d | Panorama
Football presenter Gary Lineker walks outside his home, after resigning from the BBC after 25 years of presenting Match of the Day, in London, Britain. Photo: Reuters

Gary Lineker’s fallout once again exposes Western media’s selective moral compass on Palestine

3d | Features

More Videos from TBS

Rare Bostami Turtles Face Extinction Due to Lack of Conservation

Rare Bostami Turtles Face Extinction Due to Lack of Conservation

9h | TBS Stories
American Army trains fire service in Cox's Bazar to deal with disasters

American Army trains fire service in Cox's Bazar to deal with disasters

11h | TBS Today
An Actor Turned Storyteller

An Actor Turned Storyteller

8h | TBS Programs
Professor Yunus 'thinking about resigning': Nahid Islam

Professor Yunus 'thinking about resigning': Nahid Islam

1d | TBS Today
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net