How fuel loading will be carried out at Rooppur Nuclear Power Plant
The entire fuel loading process is expected to take around 45 days.
Bangladesh is set to enter a new phase in its energy journey as uranium fuel loading begins at the Rooppur Nuclear Power Plant, marking a crucial step towards nuclear power generation.
According to a report by bdnews24, the fuel loading process for Unit 1 of the plant in Ishwardi, Pabna, is scheduled to begin at 2:30pm today (28 April). With this, the country formally moves into the operational stage of generating electricity using nuclear energy.
Project officials said all necessary preparations have already been completed.
Project in charge Ruhul Quddus said that with assistance from Russian experts and under the supervision of trained Bangladeshi engineers, installation of 163 fuel assemblies into the reactor core will begin later in the day.
The Bangladesh Atomic Energy Regulatory Authority granted the formal licence for fuel loading on 16 April, following multiple layers of safety inspections and successful pre-operational tests conducted in line with standards set by the International Atomic Energy Agency.
Former project director of the country's first nuclear power plant and ex-chairman of the Bangladesh Atomic Energy Commission, Shaukat Akbar, described the stage as a "historic milestone". He told bdnews24 that the project is now transitioning from construction to final preparation for electricity generation.
"Fuel loading marks the completion of the construction phase and the beginning of readiness for power generation," he noted, adding that the plant will play a key role in meeting rising energy demand with carbon-free and environmentally friendly electricity.
What is fuel loading and how it works
Fuel loading is one of the most sensitive and technically complex stages of a nuclear power plant's commissioning. It involves placing uranium fuel into the reactor core to enable controlled nuclear reactions.
Instead of fossil fuels such as coal, gas, or oil, nuclear plants use small uranium pellets – each weighing about 4.5 to 5 grams. These pellets are encased in zirconium alloy tubes to form fuel rods, which are then bundled into fuel assemblies.
At Unit 1, a total of 163 such fuel assemblies will be installed inside the reactor core using a specialised automated refuelling machine.
The entire system, including transport equipment and machinery, has already been tested using dummy assemblies to ensure operational readiness.
The process is being carried out under strict safety protocols, with trained Bangladeshi operators working alongside experts from Rosatom. During loading, the reactor vessel will remain filled with water to help shield radiation.
Each assembly has a predetermined position within the core, as the configuration directly affects reactor performance and safety. After installation, control rods, which regulate the nuclear reaction, will be tested to ensure proper functioning.
The entire fuel loading process is expected to take around 45 days. Once completed, the reactor will be brought to a minimum controlled power level in a phase known as "first criticality", where a controlled chain reaction begins.
Explaining the technical aspects, Shaukat Akbar told bdnews24 that each fuel assembly is about 4.6 metres long and weighs roughly 750kg, containing approximately 534kg of fuel.
"Each uranium pellet used in the reactor weighs just 4.5 to 5 grams, yet its energy output is remarkable. A single pellet can produce energy equivalent to about one tonne of coal," he said.
He added that these pellets can meet a household's electricity needs for several months without emitting toxic fumes or carbon.
Officials said that after fuel loading and subsequent tests, the plant is expected to begin supplying around 300MW of electricity to the national grid on a trial basis by late July or August this year.
The generation capacity will then be gradually increased, with Unit 1 projected to reach its full capacity of 1,200MW by the end of the year or early 2027.
Technology, capacity and long-term impact
With the Rooppur Nuclear Power Plant (NPP), Bangladesh has entered the global nuclear community, making it the world's 33rd nuclear power-generating nation.
The plant is based on advanced Generation III+ VVER-1200 technology and incorporates multiple layers of safety. These include active and passive safety systems, five layers of safety barriers, and a core catcher designed to prevent radiation leakage in extreme scenarios. The facility has been built in compliance with International Atomic Energy Agency (IAEA) safety standards.
Rooppur NPP has a total generation capacity of 2,400 megawatts and is expected to produce around 17.40 billion kilowatt-hours of electricity annually. Its operational lifespan is projected to exceed 60 years, with the potential for extension by a further 20 to 30 years through proper maintenance and modernisation.
The project involves a total investment of approximately $12.65 billion and is expected to significantly reduce Bangladesh's reliance on imported fossil fuels while stabilising long-term energy costs.
In the long term, around 3,000 skilled personnel will be required for operation and maintenance. Under a general contract between the Bangladesh Atomic Energy Commission (BAEC) and JSC Atomstroyexport, the necessary workforce has already undergone training in Russia.
The project adheres to international standards for the peaceful use of nuclear energy and is expected to play a central role in supporting sustainable development.
"Today, Bangladesh has joined the group of nations that use peaceful nuclear energy as a reliable source of sustainable development. Undoubtedly, the Rooppur Nuclear Power Plant will become a key element of the country's energy system. For Rosatom, this project marks another important step in the development of the global nuclear industry and in strengthening friendly relations with our international partners. We are pleased to work together with our Bangladeshi friends in building a modern and reliable nuclear power plant and see strong prospects for further cooperation," said Alexey Likhachev, director general of Rosatom.