BRT tragedy as repeated warnings fell on deaf ears | The Business Standard
Skip to main content
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Friday
July 04, 2025

Sign In
Subscribe
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
FRIDAY, JULY 04, 2025
BRT tragedy as repeated warnings fell on deaf ears

Bangladesh

TBS Report
16 August, 2022, 10:40 pm
Last modified: 17 August, 2022, 01:27 pm

Related News

  • Chinese firm responsible for BRT girder accident not to get any work in future: Quader
  • Safety measures still meager as BRT work resumes quietly
  • Probe body recommends action against Chinese contractor in girder accident
  • 10 people remanded over Uttara girder crash
  • BRT accident: Anomalies everywhere 

BRT tragedy as repeated warnings fell on deaf ears

Despite repeated instructions, the contractors are not providing the workers with safety harnesses, face shields, gloves and goggles

TBS Report
16 August, 2022, 10:40 pm
Last modified: 17 August, 2022, 01:27 pm
Photo: TBS
Photo: TBS

The two Chinese contractors of the Dhaka airport-Gazipur Bus Rapid Transit (BRT) were warned multiple times by the consultant and the government implementation and monitoring agency over the construction safety flaws, but to no avail.

The latest report in July by the project consultant SMEC Int Pty Ltd & Associates mentioned that the project site lacks safety barriers.

Despite repeated instructions, the contractors are not providing the workers with safety harnesses, face shields, gloves and goggles.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

The report also expressed concerns over construction materials left right in the middle of the busy road by the contractors – China Gezhouba Group Co Ltd (CGGC) and Jiangsu Provincial Transportation and Group Co Ltd (JTEG).

In 2020, the Implementation Monitoring and Evaluation Division (IMED) inspected the project and warned of major fatal accidents due to inadequate safety measures.

But the contractors did not listen to those cautionary advice, as a series of mishaps took place almost on a regular basis.

On 14 March last year, six people were injured as a girder of the BRT fell on them. The next day, a pier cap came off in Abdullahpur.

On 9 July of the current year, one person was killed and two others were injured as a BRT girder collapsed at Chandna in Gazipur.    

Latest, the Dhaka BRT tragedy happened on Monday as five people of a family including two children died after a girder of the BRT project fell on a private car in the city's Uttara area.

The BRT project was undertaken in 2012 with a deadline of 2016.

The Gezhouba Group is constructing the 16 km road on the BRT route, flyovers, 19 BRT stations and roadside drains. The firm secured the work by offering a rate that is 6.52% less than estimated cost of Tk915 crore.

On the other hand, the Jiangsu Provincial Transportation and Group is building a four-kilometre elevated road.

According to officials, the project failed to lodge desired progress even after five years of the deadline mainly due to the slow and careless construction by the Chinese contractors.

But the Ministry of Road Transport and Bridges did not take any action against the contractors, rather generously allowed them to extend the deadline time and again, driving up the cost to Tk4,268 crore from initial Tk2,228 crore.

The 2020 IMED report also pointed the finger at poor feasibility study, flaws in design, changing the design amid the implementation and adding and removing components.      

If the work was completed on time with proper planning, it would have been possible to travel from Gazipur to Dhaka airport in just 20 minutes. About 25,000 passengers could be transported on this road per hour.
 
Riddled with problems from scratch

The implementation of BRT Line-3 from Dhaka airport to Sadarghat route has been recommended in the Strategic Transport Plan developed in 2005 with the assistance of the World Bank to streamline the capital's transport system. To spread this facility outside Dhaka, later, an initiative was taken to extend the project to Gazipur.

Under the urban transport project supported by the ADB, building a BRT line on the Gazipur-Dhaka airport road was first suggested in the feasibility study.

In the light of this recommendation, a project titled "Greater Dhaka Sustainable Urban Transport Project (BRT)" was taken up in 2012 with the financial support of the ADB to build a 20.5 km dedicated bus corridor at a cost of around Tk2040 crore.

Later, the project cost doubled due to various complications. The government backtracked on the decision to build the BRT from the airport to Sadarghat to avoid the reappearance of the crisis.
 
Flip-flopping on designs time and again

Due to weakness in the feasibility study and the project design, the authorities are forced to change the design of the BRT project from time to time.

In the original project, a 2.81km flyover was to be constructed, but in the amendment, it has been increased to 5.07 km.

Four flyovers will be converted into six lanes instead of four lanes. Among them, defects were found in the design of the flyover at Ghazipur intersection.

There was a plan to construct a 3.5km flyover, but later it was increased to 4.5km. Construction of a footpath along this important road was added in the amendment. Construction of separate service lanes for slow-moving vehicles on both sides of the road was also added later.
 
Five years went past before field work came into view

The project director and a consultant were appointed in the year following the approval. Detail design, tender process for various works took a long time to complete.

After all the processes, the first deal with the contractor was signed in early 2016. And, the last package deal was done in 2016. As such, five years have passed since the beginning of the work at the field level. In the meantime, the project deadline expired.
 
What the experts say

Shamsul Haque, civil engineering professor of the Bangladesh University of Engineering and Technology (BUET) and a public transportation expert, said, "There were major imperfections and flaws in the design of the project. Completion of a project becomes difficult when the scope of work changes mid-project."

He pointed out that there is no alternative to footpaths in a busy area.

"Besides, modern drainage systems must be kept. Arrangements should also be made for how the road transport will operate along the BRT," he said.

He feels the future of the project has become uncertain as not all these aspects were taken into consideration in the beginning and were later added and amended.

"Such a precedent of conducting construction work by putting people's lives at risk cannot be found in any other countries of the world. Contractors put people's lives at risk just to save a few bucks. This is purely because of the inefficiency of the implementing agencies," he said.

Shafiqul Islam, managing director of the BRT project, says that the contractor has a shortage of money and people. As a result, the security arrangement was inadequate.

He also said that the BRT authorities cannot avoid the responsibility of the accident.

Analysts believe Monday's accident could have been avoided if action had been taken against those whose inefficiency or negligence caused accidents in the same project earlier.

Professor Adil Muhammad Khan, executive director of Institute for Planning and Development said, "Although late, it has caught the authorities' attention."

On Tuesday, Dhaka north Mayor Atiqul Islam said the safety will have to be ensured first, then the work will resume.
 
A construction site already prone to traffic mishap

Project consultant SMEC Int Pty Ltd & Associates said in the report that a total of 45,493 different types of vehicles move daily on the route and as a result, it is prone to traffic congestion and road accidents.

The consultant stressed on updating and implementing the Traffic Management Plan (TMP) prepared by the consultant during the detailed design phase prior to the construction starts.

The report urged the constructors to communicate to the public through local officials regarding the scope and schedule of the construction, as well as construction activities causing disruptions or access restrictions.

In coordination with local traffic authorities, it recommended the implementation of appropriate traffic diversion schemes to avoid inconvenience to road users, ensure smooth traffic flow, and avoid or minimise accidents, traffic hold ups, and congestion due to project operations.

The consultant report also suggested installing bold diversion signs that would be clearly visible even at night, and provide flag persons to warn of dangerous conditions to ensure safety for vehicles and pedestrians moving around construction areas.

The consultant firm said in its report that very little of their recommendations were adopted.

Top News

BRT tragedy

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Ships and shipping containers are pictured at the port of Long Beach in Long Beach, California, US, 30 January 2019. Photo: REUTERS
    Bangladesh expects US tariff relief after Trump's cuts to Vietnam
  • Local spinners produce export-standard carded and combed yarn. Photo: Mumit M
    Will higher taxes drive up RMG's yarn import reliance?
  • Screengrab from a CCTV video shows a chaotic moment as several individuals chase a woman down a staircase inside a hotel in Dhaka's Mohalhali on 1 July 2025
    Jubo Dal leader expelled over alleged attack on women in Mohakhali hotel

MOST VIEWED

  • Chief adviser’s Special Envoy for International Affairs and Adviser Lutfey Siddiqi
    Fake documents submission behind visa complications for Bangladeshis: Lutfey Siddiqi
  • History in women's football: Bangladesh qualify for Asian Cup for the first time
    History in women's football: Bangladesh qualify for Asian Cup for the first time
  • Electric power transmission pylon miniatures and Adani Green Energy logo are seen in this illustration taken, on 9 December 2022. Photo: Reuters
    Bangladesh clears all dues to Adani Power
  • What it will take to merge crisis-hit Islamic banks
    What it will take to merge crisis-hit Islamic banks
  • A file photo of the NBR Bhaban in Agargaon, Dhaka
    NBR officers gripped by fear as govt gets tough  
  • NBR Office in Dhaka. File Photo: Collected
    Govt sends 4 senior NBR officials on forced retirement

Related News

  • Chinese firm responsible for BRT girder accident not to get any work in future: Quader
  • Safety measures still meager as BRT work resumes quietly
  • Probe body recommends action against Chinese contractor in girder accident
  • 10 people remanded over Uttara girder crash
  • BRT accident: Anomalies everywhere 

Features

Illustration: TBS

Why rare earth elements matter more than you think

7h | The Big Picture
Illustration: TBS

The buildup to July Uprising: From a simple anti-quota movement to a wildfire against autocracy

1d | Panorama
Illustration: TBS

Ulan Daspara: Remnants of a fishing village in Dhaka

3d | Panorama
Photo: Collected

Innovative storage accessories you’ll love

4d | Brands

More Videos from TBS

Patiya Police Station OC Withdrawn Amid Protests: What Experts Are Saying

Patiya Police Station OC Withdrawn Amid Protests: What Experts Are Saying

5h | Podcast
"We are not numbers... we are people... we are hungry."

"We are not numbers... we are people... we are hungry."

6h | TBS Stories
Violence against women and children at epidemic level: Advisor

Violence against women and children at epidemic level: Advisor

7h | TBS Stories
Appropriate action will be taken against army personnel involved in disappearances: AHQ

Appropriate action will be taken against army personnel involved in disappearances: AHQ

8h | TBS Today
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net