Payra power plant may take more time to go into operation | The Business Standard
Skip to main content
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Get the Paper
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Wednesday
July 16, 2025

Sign In
Subscribe
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Get the Paper
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
WEDNESDAY, JULY 16, 2025
Payra power plant may take more time to go into operation

Energy

UNB
03 November, 2019, 11:10 am
Last modified: 03 November, 2019, 12:00 pm

Related News

  • 2nd unit of Payra power plant to shut down over coal shortage
  • Payra-Dhaka power connectivity trial run begins Thursday
  • Payra Power Plant's coal import bills, loan payment stuck over dollar crisis
  • Second unit of Payra 1,320MW power plant resumes production
  • Power flow established at Rampal power plant sub station from Payra plant

Payra power plant may take more time to go into operation

95 percent of works have been completed although a very crucial part of the Shandha Nadi River crossing of the line remains unfinished.

UNB
03 November, 2019, 11:10 am
Last modified: 03 November, 2019, 12:00 pm
Payra power plant may take more time to go into operation

As transmission facilities are not ready yet, the newly-constructed first unit of Payra coal-fired power plant is unlikely to go into commercial operation in December next as planned.

According to official sources, the uncertainty looms over the commercial operation of the vital project as the required transmission lines could not be completed yet.

"We had hoped that necessary transmission lines will be ready by November 15 next. But the current situation doesn't suggest that it'll be possible to get the transmission facilities ready to start the operation by December," Shah Abdul Maula, project director and chief engineer of the Bangladesh-China Power Company Limited (BCPCL), told UNB.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

He said the substation in Gopalganj, which will connect the transmission lines from Payra plant, are still under construction.

The BCPCL, a special joint venture company of Bangladesh's state-owned North-West Power Generation Company Ltd (NWPGCL) and China's state-owned China National Machinery Import & Export Corporation (CMC), has been constructing the 1320MW thermal power plant at a cost of about $2 billion as part of understanding between Dhaka and Beijing.

Abdul Maula said the construction of the 660MW first unit of the plant has been completed and now different segments are now under test-run.

"Once the transmission facilities are ready, they'll have to synchronise the whole system," he said adding that all these considerations suggest that the whole process will take more time, "even beyond December".

Officials said this has been the very first power plant to be run through imported coal, and the first consignment of coal reached the country in September 20 last by a large ship from Indonesia.

BCPCL hopes the second unit of the plant will be able to start operation by June next as transmission facilities are completed.

Meanwhile, officials at Power Grid Company of Bangladesh (PGCB), which is responsible for implementing the transmission projects, admitted that they are lagging behind the schedule in some cases for various reasons.

They said a major project was undertaken by the PGCB to build a number of transmission lines and substations to facilitate power evacuation from Payra plant.

These include construction of 160km 400kV double circuit transmission line from Payra plant to Gopalganj, and 164.6 km Aminbazar–Mawa–Gopalganj-Mongla 400 kV double circuit line, installation of 400/132 kV, 3×325 MVA AIS Substation, construction of 9.4 km river-crossing line beside Padma Bridge and installation of substation (400 kV portion) at Aminbazar with 3×520 MVA transformers.

PGCB officials said all these projects are being implemented targeting the power evacuation from both the Payra and Rampal power plants and these projects will cost about Tk 4650 crore of which Tk 3294 crore will be spent on Payra plant transmission facilities while about Tk 1356 crore on Rampal plant's transmission facilities.

"But the main challenge is to construct a 9.4-km river-crossing line beside Padma Bridge which has already got delayed in financing and tender process," said a top official at the PGCB wishing not to be named.

He said there is a schedule to implement these projects by March 2021. "But, further time may require for completing the projects."

Contacted, PGCB executive director (planning and dev) Yeakub Elahi Chowdhury admitted the delay in implementation of the Padma River-crossing line project.

About the Payra plant to Gopalganj line, he said 95 percent of works have been completed although a very crucial part of the Shandha Nadi River crossing of the line remains unfinished.

He said the PGCB targeted to complete the job by November 15. "But all depend on the weather as bad weather disrupts the construction process."

Engr AM Khurshedul Alam, CEO of NWPGCL and acting Managing Director of Bangladesh China Power Company (Pvt) Limited, said if the transmission facilities are ready by December 31, the Payra plant will supply 660 MW electricity to the southern region which mainly covers district under Khulna and Barisal divisions.

"This will be a great help for the government to replace the high cost of liquid-fuel generated electricity with low-cost electricity of coal-fired power plant," he told UNB.

Bangladesh / Top News

Payra 1320 MW Thermal Power Plant

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Photo: TBS
    Gopalganj attack: Nahid demands arrest of culprits within 24 hours
  • The supporters of local Awami League and Chhatra League locked in a clash with police following attacks on NCP convoy this afternoon (16 July). Photo: Collected
    Gopalganj under curfew tonight; 4 killed as banned AL, police clash after attack on NCP leaders
  • Mahedi and Tanzid lead Bangladesh to historic T20I series win over Sri Lanka.
    Mahedi and Tanzid lead Bangladesh to historic T20I series win over Sri Lanka.

MOST VIEWED

  • 131 foreigners were denied entry into Malaysia by their border control. Photo: The Star
    96 Bangladeshis denied entry at Kuala Lumpur airport
  • Double-decker school buses are lined up in a field in Chattogram city. The district administration has proposed modernising the buses to ensure security and convenience for school students. Photo: TBS
    Country's first smart school bus in Ctg faces shutdown amid funding crisis
  • Representational image. Photo: Collected
    Dollar gains Tk1.8 as BB buys at higher rates, lifting market floor
  • A file photo of people boarding the government-run Betna Express at a railway station. The train operates on the Benapole-Khulna-Mongla route via Jashore. Photo: TBS
    Despite profitability, Betna Express rail service handed over to pvt sector
  • Bangladesh Bank buys $313m more in second dollar auction in three days
    Bangladesh Bank buys $313m more in second dollar auction in three days
  • Infograph: TBS
    Ring Shine Textiles scam: BSEC imposes travel bans on 13

Related News

  • 2nd unit of Payra power plant to shut down over coal shortage
  • Payra-Dhaka power connectivity trial run begins Thursday
  • Payra Power Plant's coal import bills, loan payment stuck over dollar crisis
  • Second unit of Payra 1,320MW power plant resumes production
  • Power flow established at Rampal power plant sub station from Payra plant

Features

Abu Sayeed spread his hands as police fired rubber bullets, leading to his tragic death. Photos: Collected

How Abu Sayed’s wings of freedom ignited the fire of July uprising

1d | Panorama
Illustration: TBS

Open source legal advice: How Facebook groups are empowering victims of land disputes

1d | Panorama
DU students at TSC around 12:45am on 15 July 2024, protesting Sheikh Hasina’s insulting remark. Photo: TBS

‘Razakar’: The butterfly effect of a word

2d | Panorama
Photo: Collected

Grooming gadgets: Where sleek tools meet effortless styles

3d | Brands

More Videos from TBS

China's economy not hit by Trump's tariff war

China's economy not hit by Trump's tariff war

58m | Others
News of The Day, 16 JULY 2025

News of The Day, 16 JULY 2025

2h | TBS News of the day
Death toll rises in Gopalganj clashes surrounding NCP rally

Death toll rises in Gopalganj clashes surrounding NCP rally

3h | TBS News Updates
Meta’s mega move: massive investment in AI infrastructure

Meta’s mega move: massive investment in AI infrastructure

3h | TBS World
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net