Sheikh Sayera Khatun hospital yet to open even after a decade  | The Business Standard
Skip to main content
  • Latest
  • Epaper
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Friday
June 27, 2025

Sign In
Subscribe
  • Latest
  • Epaper
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
FRIDAY, JUNE 27, 2025
Sheikh Sayera Khatun hospital yet to open even after a decade 

Infrastructure

Saifuddin Saif
07 October, 2021, 12:45 pm
Last modified: 07 October, 2021, 12:50 pm

Related News

  • 2 killed, 25 injured in Gopalganj highway crash
  • Tk65 crore wasted on unplanned projects in Ctg City; all four now abandoned
  • Three hospitals ‘held hostage’ as discharged July uprising injured keep occupying beds
  • When hospitals rest and patients languish: Eid woes of the ailing in Bangladesh
  • Emergency services resume at Ophthalmology Institute after week-long suspension

Sheikh Sayera Khatun hospital yet to open even after a decade 

The project cost has almost doubled due to implementation delay

Saifuddin Saif
07 October, 2021, 12:45 pm
Last modified: 07 October, 2021, 12:50 pm
Photo/Collected
Photo/Collected
  • Highlights:
  • Cost increased to Tk705 crore from the initial Tk463.62 crore
  • After the seventh extension, the deadline will expire in June 2022
  • The work has Tk11.50 crore ADP allocation this fiscal year
  • Since 2012, the work so far logs 75% physical progress

The construction of Sheikh Sayera Khatun Medical College Hospital and Nursing Institute after the name of Bangabandhu's mother in Gopalganj is poised for an eighth extension as the authorities could not complete the work in a decade.

The project cost has almost doubled due to the implementation delay. In two phases, the authorities have increased the cost to Tk705 crore, from its initial cost of Tk463.62 crore.

At a meeting on 29 August, the Project Implementation Committee of the Health Services Division expressed the fear that the tenure and cost of the 500-bed hospital and medical college construction will increase again.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

In the last fiscal year, the government gave an adequate allocation for the project, which – beginning in March 2012 on DC Road in Gopalganj – was originally due to be completed in February 2015.

But the Directorate General of Health Services (DGHS), the implementing agency, could not complete the project.

Following the seventh extension, the deadline will expire in June 2022.

Apprehending that the implementation work will not be completed, the government has allocated only Tk11.50 crore for this project in the annual development programme this fiscal year.

To complete the project, Tk174 crore will have to be spent this fiscal year. As a result, people concerned said it is not possible to complete the project with such a small allocation this financial year.

Since its inception, Tk531 crore has been spent on the project and so far no more than 75% of its physical progress has been done.

"From the beginning, there were various problems with this project. There are still complications with the contractor," said Md Helal Uddin, additional secretary at the Health Services Division.

"But, at a meeting on 27 September, the health minister directed the authorities concerned to complete the work this fiscal year and also asked for necessary steps to increase the allocation."

On the other hand, people involved in the project say that the hospital equipment has not been purchased yet due to complexities in the tender process.

About half of the construction of the nursing institute is not yet complete. The recruitment process is not over yet. As a result, even if adequate allocation is available, it will be difficult to complete the project in the current financial year, they added.

After a long delay, the construction of the medical college and the hospital buildings has been 100% and 96% completed, respectively. Besides, work on several buildings such as dorms for doctors and students has also been completed.

Project Director Dr Asit Kumar Mallick said the tender for procurement of hospital equipment and furniture was incorrect and therefore the tender could not be floated.

"We expect the tender process to be completed by January. And if this is the case, it will be possible to launch indoor health services from June next year. The hospital aims to launch outdoors next December. The recruitment of manpower will also be completed in the meantime," he added.

The project director, who took charge last January, said a lot of work had gained momentum during his time.

"But due to the death of the contractor of the nursing college, it is not possible to say when the work will be completed. A lawsuit is pending between the two owners of the original contracting firm. If this complication is not removed, the construction work will not be completed," he added.

In June 2018, the Implementation Monitoring and Evaluation Department (IMED) prepared an intensive monitoring report on the project. The report cited delays in land acquisition and landfilling as reasons for the slow progress of project implementation.

A responsive bidder could not be found due to the price and conditions of experience mentioned in the tender for the construction of the nine-storey hospital building with a ten-storey foundation.

As a result, the conditions were relaxed in the tender notification for the third time. The construction started in February 2017. Again, the contractor did not complete the work within the time stipulated in the contract.

Lack of drainage, non-availability of potable water and delay in installation of power substations were mentioned in the IMED report. 

Top News

Sheikh Sayera Khatun hospital / hospital / Gopalganj / project / project cost

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Photo: Courtesy
    28 Bangladeshis reach Pakistan border from Iran, set to return home: MoFA
  • Turning the tide: Bangladesh shipbreaking sheds hazardous past for green future
    Turning the tide: Bangladesh shipbreaking sheds hazardous past for green future
  • Employees staged a demonstration as part of their ongoing protest demanding the removal of the NBR chairman. Authorities shut the main gate. The photo was taken in front of the NBR headquarters in Agargaon on 26 June 2025. Photos: Syed Zakir Hossain/TBS
    NBR officials open to talks with govt, but protest continues

MOST VIEWED

  • As distributors overcharge, govt plans to sell LPG directly to consumers
    As distributors overcharge, govt plans to sell LPG directly to consumers
  • Representational image. Photo: TBS
    2025 Global Liveability Index: Dhaka slips 3 notches, just ahead of war-torn Tripoli, Damascus
  • For the first time, Shipping Corp to buy two vessels using Tk900cr of its own funds
    For the first time, Shipping Corp to buy two vessels using Tk900cr of its own funds
  • Illustration: Khandaker Abidur Rahman/TBS
    BAT Bangladesh to invest Tk297cr to expand production capacity
  • File Photo: Rajib Dhar/TBS
    Bangladesh no longer just a volume player but a global hub for sustainable RMG products: Commerce secy
  • Screengrab from Thikana talkshow
    Jamaat ameer offers unconditional apology for all past wrongs, including during Liberation War

Related News

  • 2 killed, 25 injured in Gopalganj highway crash
  • Tk65 crore wasted on unplanned projects in Ctg City; all four now abandoned
  • Three hospitals ‘held hostage’ as discharged July uprising injured keep occupying beds
  • When hospitals rest and patients languish: Eid woes of the ailing in Bangladesh
  • Emergency services resume at Ophthalmology Institute after week-long suspension

Features

Zohran Mamdani gestures as he speaks during a watch party for his primary election, which includes his bid to become the Democratic candidate for New York City mayor in the upcoming November 2025 election, in New York City, US, June 25, 2025. REUTERS/David 'Dee' Delgado

What Bangladesh's young politicians can learn from Zohran Mamdani

13h | Panorama
Footsteps Bangladesh, a development-based social enterprise that dared to take on the task of cleaning a canal, which many considered a lost cause. Photos: Courtesy/Footsteps Bangladesh

A dead canal in Dhaka breathes again — and so do Ramchandrapur's residents

13h | Panorama
Sujoy’s organisation has rescued and released over a thousand birds so far from hunters. Photo: Courtesy

How decades of activism brought national recognition to Sherpur’s wildlife saviours

1d | Panorama
More than half of Dhaka’s street children sleep in slums, with others scattered in terminals, parks, stations, or pavements. Photo: Syed Zakir Hossain

No homes, no hope: The lives of Dhaka’s ‘floating population’

2d | Panorama

More Videos from TBS

The instructions given by the Chief Advisor for installing solar panels on the roofs of government buildings

The instructions given by the Chief Advisor for installing solar panels on the roofs of government buildings

8h | TBS Today
Why Zohran thanked 'Bangladeshi aunties'?

Why Zohran thanked 'Bangladeshi aunties'?

8h | TBS World
Ayatollah Ali Khamenei claims 'victory' against US and Israel

Ayatollah Ali Khamenei claims 'victory' against US and Israel

9h | TBS World
News of The Day, 26 JUNE 2025

News of The Day, 26 JUNE 2025

10h | TBS News of the day
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net