A month's delay increases project cost by 0.95%: BIDS | The Business Standard
Skip to main content
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Monday
May 12, 2025

Sign In
Subscribe
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
MONDAY, MAY 12, 2025
A month's delay increases project cost by 0.95%: BIDS

Infrastructure

TBS Report
18 May, 2023, 06:10 pm
Last modified: 18 May, 2023, 09:49 pm

Related News

  • World Bank to provide $280m loan to improve Ctg water supply, sanitation
  • Regional connectivity projects face unprecedented delays after political changeover
  • Bay Terminal: Tk14,908cr support project set for final govt approval
  • Matarbari deep-sea port construction deal with Japanese firms likely this month
  • Govt approves 29 new projects to combat climate change

A month's delay increases project cost by 0.95%: BIDS

It would be difficult to mitigate time and cost overruns without any reform in existing practice of land acquisition 

TBS Report
18 May, 2023, 06:10 pm
Last modified: 18 May, 2023, 09:49 pm
Photo: Unsplash
Photo: Unsplash

Highlights:

  • Development projects tend to go through multiple phases of revision 
  • Overruns delay benefits and can make them irrelevant
  • RHD implemented only 13.61% projects within the stipulated in 10 years
  • Delays cause welfare loss and hurt complementary private investment 

A month delay in the duration of development projects leads to an average of 0.95 percentage point increase in their implementation costs, according to findings of a research conducted by the Bangladesh Institute of Development Studies (BIDS).

For perspective, a project estimated at Tk10,000 crore can cost Tk95 crore more when its tenure faces escalation for a month due to various reasons, particularly delay in land acquisition.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

Without any reformation in existing practice of land acquisition, it would be difficult to mitigate time and cost overruns, the BIDS said. 

The information was revealed at a session on the second day of the BIDS Research Almanac 2023 on Thursday. Jayed Bin Satter, research associate of the BIDS presented the highlights of a research titled "Time and Cost Overrun in Development Projects: Evidence from Audit Reports of Roads Projects". 

Other key reasons for time escalation include delayed work order placements, price escalations, lack of skilled manpower, negotiation with stakeholders, and consultant recruitment by donor agencies.

Development projects in Bangladesh have a tendency to go through multiple phases of revision resulting in time escalation and cost escalation, the research finds. 

Time and cost overruns delay expected benefits from the project making them irrelevant, and in financial terms, delays cause welfare loss and hurt complementary private investment. 

"In the case of projects financed through borrowing, longer implementation periods have high rates of interest and add to more repayment schedule," according to research findings. 

For instance, the Roads and Highways Department (RHD) managed to implement only 13.61% of its development projects within the stipulated time and cost in the last ten years, Jayed Bin Satter said at the event. 

Furthermore, the tenure of about 80% of projects implemented by the RHD from FY13 to FY22 has seen an increase. At the same time, the cost of about 56% of the projects has been increased. 

He said the government placed the highest priority on the transportation and communication sector in the last decade and the allocation for the sector increased to 28.7% of the total Annual Development Programme (ADP) in the current fiscal year from 23.3% in FY14.

Dr Mohammad Emdad Ullah Mian, member of the Physical Infrastructure Division of the Planning Commission said that land acquisition is not the single reason for the delay in project implementation.

Although much importance is given by the concerned organisation at the time of project preparation and approval, it is neglected during the implementation phase, he added.

He also acknowledged that financing constraints are a significant cause of delays.

Top News

BIDS / project

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Infograph: TBS
    Food, fertilisers, raw materials: NBR plans advance tax on 200 duty-free imports
  • Photo: TBS
    Tea exports jump by 58% in 2024
  • A view of the state-owned Intercontinental Hotel in Dhaka, illuminated in the evening. The photo was taken on Sunday. Photo: Rajib Dhar/TBS
    InterContinental seeks Tk900cr govt-backed loan to recover from losses

MOST VIEWED

  • Chief Adviser Muhammad Yunus holds a high-level meeting on the country's capital market at the State Guest House Jamuna in Dhaka on 11 May 2025. Photo: PID
    Chief adviser orders listing of SOEs, govt-linked MNCs to revitalise stock market
  • World Bank sees favouritism in digital bank licensing in Bangladesh
    World Bank sees favouritism in digital bank licensing in Bangladesh
  • Bangladesh Bank. File Photo: Collected
    Govt can now temporarily take over any bank, NBFI
  • US President Donald Trump and Israeli Prime Minister Benjamin Netanyahu meet at the White House in Washington, US, February 4, 2025. Photo: REUTERS/Elizabeth Frantz
    Trump cuts ties with Netanyahu over manipulation concerns: Israeli media
  • Solar power project in Chattogram. Photo: TBS
    Govt's 5,238MW grid-tied solar push faces tepid response from investors
  • File Photo: US Vice President JD Vance delivers remarks at the American Dynamism Summit in Washington, DC, US, March 18, 2025. REUTERS/Kent Nishimura/File Photo
    Vance called Modi to encourage ceasefire talks after receiving 'alarming intelligence:' CNN

Related News

  • World Bank to provide $280m loan to improve Ctg water supply, sanitation
  • Regional connectivity projects face unprecedented delays after political changeover
  • Bay Terminal: Tk14,908cr support project set for final govt approval
  • Matarbari deep-sea port construction deal with Japanese firms likely this month
  • Govt approves 29 new projects to combat climate change

Features

Photo: Courtesy

No drill, no fuss: Srijani’s Smart Fit Lampshades for any space

21h | Brands
Photo: Collected

Bathroom glow-up: 5 easy ways to upgrade your washroom aesthetic

21h | Brands
The design language of the fourth generation Velfire is more mature than the rather angular, maximalist approach of the last generation. PHOTO: Arfin Kazi

2025 Toyota Vellfire: The Japanese land yacht

1d | Wheels
Kadambari Exclusive by Razbi’s summer shari collection features fabrics like Handloomed Cotton, Andi Cotton, Adi Cotton, Muslin and Pure Silk.

Cooling threads, cultural roots: Sharis for a softer summer

2d | Mode

More Videos from TBS

How Trump's love of maps has shaken up geopolitics

How Trump's love of maps has shaken up geopolitics

12h | Others
What can be done to restore investor confidence in the capital market?

What can be done to restore investor confidence in the capital market?

13h | Podcast
How important is dignity diplomacy in the US-China trade war?

How important is dignity diplomacy in the US-China trade war?

14h | Others
News of The Day, 11 MAY 2025

News of The Day, 11 MAY 2025

15h | TBS News of the day
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net