Metro rail sees 34% aid unused for Covid curbs | The Business Standard
Skip to main content
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Sunday
July 13, 2025

Sign In
Subscribe
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
SUNDAY, JULY 13, 2025
Metro rail sees 34% aid unused for Covid curbs

Infrastructure

Jahidul Islam
27 July, 2021, 12:00 pm
Last modified: 27 July, 2021, 12:20 pm

Related News

  • Metro rail to introduce easy ticketing system
  • DMTCL urges Metro passengers to wear masks amid rising Covid-19 cases
  • Metro rail resumes operation after Eid break; carrying meat not allowed
  • Metro rail takes Eid break today
  • Metro rail services resume after nearly 2hrs halt due to electrical issue

Metro rail sees 34% aid unused for Covid curbs

The project implementing company spent almost 100% of domestic allocation in the fiscal year

Jahidul Islam
27 July, 2021, 12:00 pm
Last modified: 27 July, 2021, 12:20 pm
TBS Infograph
TBS Infograph

The construction of the country's first-ever metro rail saw utilisation of only 66% of its foreign fund in FY21, mainly because procurements of necessary equipment got disrupted in the pandemic time. 

Some Tk4,076 crore in foreign aid was earmarked for five projects under the Dhaka Mass Transit Company Limited (DMTCL), but Tk2,748 crore could be utilised. On the other hand, the project implementing company spent almost 100% of domestic allocation in the fiscal year. 

The DMTCL spent around Tk6,300 crore of the total ADP allocation of over Tk7,245 crore – including domestic and foreign funds – in FY21, according to an ADP implementation review report. 

The report prepared by the Economic Relations Division (ERD) said the disbursement of foreign funds takes more time than that of domestic funds as the implementation of a project with foreign assistance requires approval of agencies concerned in hiring consultants and selecting contractors. 

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

Moreover, a lack of skills in project implementation, inefficiency in bargaining with foreign companies and various other reasons make it difficult to get foreign aid, as per the report.

Managing Director of DMTCL MAN Siddique said, "The use of foreign funds depends a lot on the pandemic situation of donor countries as well as suppliers of goods and services."

Giving an example, he said five metro trains were supposed to arrive from Japan by last June. "We could not carry out direct inspections owing to travel restrictions imposed by the Japanese government amid Covid-19. That is why we had the inspection done by appointing a Japanese consulting firm." 

Under such an arrangement, it was possible to bring in only two locomotives. The arrival of the remaining three will be delayed as many more restrictions have now been imposed because of the ongoing Olympic Games alongside the travel ban still in force, the DMTCL managing director said.

Pradip Ranjan Chakraborty, secretary to the Implementation Monitoring and Evaluation Division Secretary, told The Business Standard, "It is true that it takes some extra time to get foreign aid. However, it is not fair that a large portion of it for an important project [metro rail] was not disbursed."

The IMED secretary said in the case of spending government funds on projects, only following public procurement rules was enough. But to spend foreign aid, it is also necessary to abide by different policies of different donor agencies or countries. That is why the utilisation of foreign funds remains comparatively low.

Officials concerned at the ADP review meeting of the Road Transport and Highways Division expressed dissatisfaction over the fact that a large portion of foreign aid in DMTCL's projects was not spent.

The review report said more than Tk1,328 crore remained unutilised from the foreign aid allocation for five projects, including three construction projects and two survey projects under the DMTCL. 

Several officials who took part in the meeting said Road Transport and Highways Division Secretary Md Nazrul Islam expressed dissatisfaction with the DMTCL for not being able to use all of its foreign aid. 

At the meeting, the secretary said the ADP implementation of other departments of the division was close to 100%, but the overall progress had been slow due to the failure of DMTCL.

The MRT Line-6 project involving Tk22,000 crore started in 2012 and its tenure will end in June 2024. At the end of last June, the project's financial progress stood at around 71%. Had 100% of the allocated foreign aid been used, 77% of the project work would have been completed. 

The project for setting MRT Line-1 from the airport to Kamalapur railway station and from Natun Bazar to Purbachal was approved in 2019. The project involving Tk52,561 crore has so far made 1.5% progress.

The financial progress of the MRT Line-5 (northern) from Hemayetpur in Savar to Bhatara, via Mirpur-10 and Banani, has been about 3%. 

According to the DMTCL sources, the government wants to set up about 129km of underground and elevated routes of six metro rail lines in Dhaka by 2030. 

Of these, construction of a 71.24km line has started under three projects involving Tk115,785 crore. The Japan International Cooperation Agency will provide about 75% of the costs of these projects as loans.

The project to set up a metro rail line from Uttara to Motijheel started in 2012 and overall progress in the project has been 67.63%. The progress of the Uttara-Agargaon route is 87.8%. The work from Agargaon to Motijheel section has made 59.48% progress.

Under the MRT Line-1 project, detailed design work is underway at the end of the basic design for the construction of metro rail from the airport to Kamalapur and from Natunbazar to Purbachal. Acquisition of about 93 acres of land for the project is also in progress.

A feasibility study and basic design of Dhaka Mass Rapid Transit Development Project Line-5 (north) project have been completed, said officials. 
 

Bangladesh / Economy / Top News

Metro Rail / First Metro Rail / Metro Rail Project

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Photo: TBS
    Political activists go awry while government takes a deep slumber
  • Home Affairs Adviser Lieutenant General (retd) Jahangir Alam Chowdhury at the 11th meeting of the Advisory Council Committee on Law and Order on Sunday, 13 July 2025. Photo: TBS
    Combing operation from now on to catch identified criminals, improve law & order: Home adviser
  • Representational image/Collected
    Mitford murder: 2 more accused arrested

MOST VIEWED

  • RAB Director General AKM Shahidur Rahman speaks at the press briefing on a fake bomb threat on Biman Bangladesh flight on Saturday, 12 July 2025. Photo: TBS
    Mother faked bomb threat on Biman flight to stop married son from flying with girlfriend: RAB
  • Bangladeshi garment workers make clothing in the sewing section of a factory in Gazipur, Bangladesh, April 9, 2025. Photo: REUTERS/Mohammad Ponir Hossain/File Photo
    Some Walmart garment orders from Bangladesh on hold due to US tariff threat
  • Infographic: TBS
    Dollar price plummets by Tk2.9 in a week as demand wanes
  • Bangladesh and US hold tariff talks on 11 July 2025. Photo: CA Press Wing
    Dhaka, Washington yet to agree on 20% of US tariff conditions: BGMEA
  • Infograph: TBS
    Matarbari power plant eyes G2G coal deal with Indonesia after quality setbacks
  • Dr Mohammad Zakir Hossain, managing director of Delta Pharma Ltd and secretary general of the Bangladesh Association of Pharmaceutical Industries (BAPI). Sketch: TBS
    Pharma industry grew with policy support, needs it again to survive: BAPI secretary general

Related News

  • Metro rail to introduce easy ticketing system
  • DMTCL urges Metro passengers to wear masks amid rising Covid-19 cases
  • Metro rail resumes operation after Eid break; carrying meat not allowed
  • Metro rail takes Eid break today
  • Metro rail services resume after nearly 2hrs halt due to electrical issue

Features

Photo: Collected

Grooming gadgets: Where sleek tools meet effortless styles

26m | Brands
The 2020 Harrier's Porsche Cayenne coupe-like rear roofline, integrated LED lighting with the Modellista special bodykit all around, and a swanky front grille scream OEM Plus for the sophisticated enthusiast looking for a bigger family car that isn’t boring. PHOTO: Ahbaar Mohammad

2020 Toyota Harrier Hybrid: The Japanese Macan

1d | Wheels
The showroom was launched through a lavish event held there, and in attendance were DHS Motors’ Managing Director Nafees Khundker, CEO Imran Zaman Khan, and GMs Arman Rashid and Farhan Samad. PHOTO: Akif Hamid

GAC inaugurate flagship showroom in Dhaka

1d | Wheels
After India's visa restriction, China's Kunming is drawing Bangladeshi patients

After India's visa restriction, China's Kunming is drawing Bangladeshi patients

1d | Panorama

More Videos from TBS

Apu Biswas secures bail following court surrender

Apu Biswas secures bail following court surrender

1h | TBS Today
Legal fight if 'Shapla' symbol is not given: NCP

Legal fight if 'Shapla' symbol is not given: NCP

2h | TBS Today
Prisoner sentenced to prison for not showing news of president in Tunisia

Prisoner sentenced to prison for not showing news of president in Tunisia

4h | TBS World
The price of the dollar is falling; how much can it fall?

The price of the dollar is falling; how much can it fall?

5h | TBS Stories
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net