Fund cut as Dhaka's fast-track transit projects on slow spending lane | The Business Standard
Skip to main content
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Thursday
May 29, 2025

Sign In
Subscribe
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
THURSDAY, MAY 29, 2025
Fund cut as Dhaka's fast-track transit projects on slow spending lane

Infrastructure

Jahidul Islam & Saifuddin Saif
29 January, 2023, 01:00 pm
Last modified: 29 January, 2023, 03:35 pm

Related News

  • BRTC to launch AC bus service in BRT corridor tomorrow
  • BRT service partially opens on 16 December
  • 7 flyovers of BRT project open today
  • Slow progress triggers over 54% fund cuts for 4 metro projects
  • Metro rail to fully open in October: Quader

Fund cut as Dhaka's fast-track transit projects on slow spending lane

Road transport high-ups note the spending appetite for the projects dwindles on the back of poor implementation

Jahidul Islam & Saifuddin Saif
29 January, 2023, 01:00 pm
Last modified: 29 January, 2023, 03:35 pm

Five projects, including the airport-Kamalapur underground metro train, aiming at an integrated and swift rail rapid transit for Dhaka have proposed around 50% allocation cut this year, show documents, as the works clocked less than 20% progress in the first half of FY23. 

The five projects had around Tk8,269 crore allocation for FY23, including government and foreign funding. The fund trimming proposals amounted to Tk4,105 crore – around Tk1,583 crore from the government and Tk2,521 crore from the foreign parts.

The implementing agency Dhaka Mass Transit Company Limited (DMTCL) attributed the slow progress and subsequent budget trimming to land acquisition hiccups, tangled up utility lines and tender issues. 

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

However, the Budget Management Committee of the Road Transport and Highways Division labelled the fund cut proposal for the government's fast-track projects "disappointing" and pinned the blame on DMTCL's "inefficiency", according to meeting minutes.         

Against the backdrop, the physical work of Mass Rapid Transit (MRT) Line-1 – connecting Dhaka airport to Kamalapur with an elevated link from Natun Bazar to Purbachal by an underground metro rail – is going to be inaugurated on 2 February. 

Prime Minister Sheikh Hasina will inaugurate the country's first underground rail construction with MRT-1's depot work at Purbachal. The Executive Committee of the National Economic Council (Ecnec) commissioned the MRT-1 in October 2019 at an estimated Tk52,561 crore.   

But prior to commencing the MRT-1 physical work even after three years, the DMTCL has proposed to cut around Tk1,792 crore, which is about 79% of the total allocation of Tk2276 crore for FY23.

In the current fiscal year, the state-owned company wants to bring down the MRT-1 budget to Tk483 crore thanks to the slow pace of work.

The Budget Management Committee meeting expressed concern over the slower implementation of the priority projects and refunding of a substantial amount from the original allocation in the annual development programme.

Referring to the government's project line-up rearranging due to fund crunch, participants at the meeting said adequate allocations have been kept aside for metro rail projects with the highest priority even amid the crisis. 

The proposals for fund cuts were mostly attributed to "inefficient" implementation, which was regarded as "disappointing".

The meeting urged the DMTCL authorities to speed up the spending in the next fiscal year to catch up with the allocations.  

Md Abul Kashem Bhuiyan, project director of MRT-1, said, "We had a plan of awarding three contract packages to construct the main line from airport to Rampura in the current fiscal year. We surrendered the allocation as we failed to do so."

He shifted the blame to the pandemic that delayed the preparatory works such as basic design, detailed design and land acquisition. He also accused the Japan International Cooperation Agency (Jica), the foreign financier, of delays in making some key decisions.

"The Jica was supposed to provide some observations on land acquisition within one month. But the lender took five months to do so," he told The Business Standard.

In October 2019, the Ecnec also approved MRT Line-5 (Northern Route) at Tk41,238 crore to develop rapid metro transit connecting Hemayetpur and Bhatara via Gabtoli, Mirpur-1, 10 and 14, Banani, Gulshan-2 and Natun Bazar. 

The project has Tk800 crore allocated in FY23, but the project authorities seek to reduce it by 49.24% to Tk406 crore in the revised development budget. 

Aftab Hossain Khan, director for MRT-5 project, told The Business Standard they proposed surrendering the money as there is no big payment in the upcoming months.

He said the project, which now is at the design stage, has already acquired lands and would require more money flow next fiscal year for land development.  

"We hope the depot construction will begin in July or August in FY24. We then will be able to catch up with the allocation," he said.

The MRT Line-6 project between Uttara to Motijheel was inaugurated partially in December last year. Though project officials claim the work is progressing fast to extend the services up to Motijheel within 2023, MRT-6 is going to surrender about Tk1,914 crore from its Tk4,963 crore allocation in FY23.

Despite repeated attempts, The Business Standard could not reach MRT-6 Project Director Md Aftabuddin Talukder for comments.

Economy / Infograph / Top News

Transit projects / Mass Rapid Transit (MRT) / Bus Rapid Transit (BRT)

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • How termination of USDA-funded trade facilitation project will affect Bangladesh
    How termination of USDA-funded trade facilitation project will affect Bangladesh
  • File photo of Bangladesh Secretariat. Photo: Collected
    Visitors banned from entering Secretariat on Mondays and Thursdays
  • File photo of BNP Secretary General Mirza Fakhrul Islam Alamgir. Photo: Collected
    Asked for roadmap, govt didn’t give in 10 months, now 'December it is': Mirza Fakhrul

MOST VIEWED

  • Google Pay. Photo: Collected
    Google Pay likely coming to Bangladesh soon
  • Graphics: TBS
    Suspicious banking activities surge by 56% since July: Cenbank
  • Representational image of cable car/Freepik
    Cable car to be installed from Himchari to Reju Khal in Marine Drive Road
  • Illustration: TBS
    Bangladesh sees highest-ever per capita income of $2,820 in FY25, BBS provisional data shows
  • IFIC Bank receives Tk6,000 cr in new deposits in six months
    IFIC Bank receives Tk6,000 cr in new deposits in six months
  • Abdul Awal Mintoo, chairman of National Bank Limited. Sketch: TBS
    'Regulatory support must for National Bank to restore depositors' confidence'

Related News

  • BRTC to launch AC bus service in BRT corridor tomorrow
  • BRT service partially opens on 16 December
  • 7 flyovers of BRT project open today
  • Slow progress triggers over 54% fund cuts for 4 metro projects
  • Metro rail to fully open in October: Quader

Features

In recent years, the Gor-e-Shaheed Eidgah has emerged as a strong contender for the crown of the biggest Eid congregation in the country, having hosted 600,000 worshippers in 2017. Photo: TBS

Gor-e-Shaheed Boro Maath: The heart of Dinajpur

2d | Panorama
The Hili Land Port, officially opened in 1997 but with trade roots stretching back to before Partition, has grown into a cornerstone of bilateral commerce.

Dhaka-Delhi tensions ripple across Hili’s markets and livelihoods

3d | Panorama
Photo: Collected

Desk goals: Affordable ways to elevate your study setup

3d | Brands
Built on a diamond-type frame, the Hornet 2.0 is agile but grounded. PHOTO: Asif Chowdhury

Honda Hornet 2.0: Same spirit, upgraded sting

3d | Wheels

More Videos from TBS

The fight between two brothers; Adidas vs Puma

The fight between two brothers; Adidas vs Puma

2h | Others
Trump is again keen to make Canada the 51st state

Trump is again keen to make Canada the 51st state

3h | Others
Trump's tariff strategy and Europe's investment politics, violence or negotiation?

Trump's tariff strategy and Europe's investment politics, violence or negotiation?

4h | Others
Rumours surrounding the Club World Cup: Which club will Ronaldo join?

Rumours surrounding the Club World Cup: Which club will Ronaldo join?

4h | Others
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net