Delays, disputes: Four road projects worth $6.8b axed from PPP with Japan | The Business Standard
Skip to main content
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Saturday
June 07, 2025

Sign In
Subscribe
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
SATURDAY, JUNE 07, 2025
Delays, disputes: Four road projects worth $6.8b axed from PPP with Japan

Economy

Jahidul Islam
30 March, 2024, 09:35 am
Last modified: 30 March, 2024, 12:05 pm

Related News

  • Tk5,040cr allocation for PPP projects encouraging: Bida executive chairman
  • Recruiting skilled workers: Japan's restaurant group to open training centre in Dhaka
  • CA Yunus urges accelerated development of infrastructures in Moheshkhali, Matarbari
  • $1.07b loan deals likely during chief adviser's upcoming Japan visit
  • Prioritise environment while approving development projects: Rizwana

Delays, disputes: Four road projects worth $6.8b axed from PPP with Japan

Officials say the projects will be implemented under the Annual Development Programme or alternative means

Jahidul Islam
30 March, 2024, 09:35 am
Last modified: 30 March, 2024, 12:05 pm

Four major road connectivity projects involving over $6.8 billion have been dropped from the list of public-private partnerships (PPP) with Japan due to delays in starting, poor profitability, and disputes regarding implementation procedures.

The Dhaka Metro Line-2 project, involving $3.48 billion, was already taken off the PPP list, and three other projects were withdrawn during the 6th joint PPP platform meeting between Bangladesh and Japan held in Dhaka on 18 March, according to Road Transport and Highways Division officials.

The other three projects are – the widening of Chattogram-Cox's Bazar highway involving $1.69 billion, the construction of an outer ring road around Dhaka involving $1.2 billion and the upgradation of Nabinagar-Manikganj-Paturia road into an expressway involving $548 million.

Experts said dropping such projects reflects faulty decision-making, weaknesses in PPP management in the country, and inefficiencies in project execution.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

This was a missed opportunity, they said, noting that these projects, earmarked five to seven years ago, could have yielded substantial benefits by now if construction had progressed as planned.

Moreover, they caution that transitioning the implementation modality will likely result in increased costs and delays, putting additional strain on the government's fiscal space and budget management.

Govt hopes to implement projects under ADP

ABM Amin Ullah Nuri, secretary of the Road Transport and Highways Division, however, assured that the implementation of these projects will soon start under the Annual Development Programme (ADP) or through alternative means.

Regarding the Chattogram-Cox's Bazar highway project, he told TBS that once the Matarbari deep sea port is operational, the Chattogram to Cox's Bazar highway will become crucial for the country's economy, leading to a substantial rise in road traffic.

"Considering this, the road needs to be widened quickly. There have been talks of development of the project under PPP modality for over the last seven years, but there was no progress," Amin Ullah said.

He also said that the Japanese investors offered to take the operation and maintenance of the road under PPP modality but it was not accepted by the government.

"We have sufficient road operation and maintenance capabilities. There is no scope for spending foreign currency on all these works in PPP," he explained.

The secretary said the project now has been taken off the PPP list due to the urgent need to increase the width of the road to cope with the demand.

"Initiatives will be taken to start the work with funding from any source under the Annual Development Programme," he added.

In 2018, the Cabinet Committee on Economic Affairs (CCEA) greenlit the proposal for the project. It was initially discussed during the first joint PPP platform meeting between Bangladesh and Japan in 2017, with Marubeni Corporation of Japan slated to invest $1.6 billion in the project.

The project profile developed by the Public Private Partnership Authority (PPPA) said the 136km road is imperative from the viewpoint of tourism as it connects the most popular tourist sites with the rest of the country.

Upgrading of Nabinagar-Manikgang-Paturia Road into Expressway

The upgrading of Nabinagar-Manikganj-Paturia Road into an expressway project involves $548 million. It was selected for PPP modality in the 4th joint PPP platform meeting with Japan in 2020.

The potential investor JFE Engineering Corporation of Japan withdrew from implementing the project before the approval of CCEA, saying the project would not be profitable, said Md Abul Bashar, director general of the PPPA.

RTHD Secretary Nuri said once the ongoing development of several link roads is completed, the Nabinagar-Manikganj-Paturia road will experience significant traffic potential.

He also said implementing the project under the ADP would guarantee a positive return and could be profitable for any other PPP investor.

Dhaka Outer Ring Road PPP Project

PPPA Director General Bashar said another project called "Construction of Outer Ring Road," proposed in 2017 with an estimated investment of $1.2 billion by Japan's Marubeni Corporation, has been dropped from the PPP list due to disagreements over the project's phases.

The Road Division intends to implement all three phases of the outer ring road under PPP, but the investor is interested in only one or two phases under PPP, he added.

What experts say

Professor Mustafizur Rahman, distinguished fellow at the Center for Policy Dialogue, said the failure to start work on projects identified as important seven years ago is a huge loss of opportunity.

He said every infrastructure would have been operational if the work were started on time and the people of the country would have benefited from it.

The economist said using PPP eases the government's fiscal burden, allowing more spending on education, health, social security, and human resource development while managing infrastructure financing through private investments.

He warned that if these projects were implemented under the ADP, it would increase costs and time. "Initiatives to implement these projects with foreign loans would push to pay more as interest cost, as the scope of managing concessional loans is reduced."

Shamsul Hoque, director of Buet's Accident Research Institute, said foreign investors are losing interest in PPP projects in Bangladesh due to prolonged implementation processes and various complications.

"Investors perceive a lack of project completion certainty in Bangladesh, leading to reluctance in partnership and aversion to taking loans with interest," he said.

Highlighting examples like the Dhaka Elevated Expressway and Dhaka Bypass, he mentioned issues such as unclear land availability and utility transfer problems faced by PPP investors.

To prevent such crises, he suggested completing all preparatory work, including land acquisition and utility relocation, before initiating PPP projects.

Infograph / Top News

ppp / PPP project / Japan - Bangladesh / Bangladesh-Japan / Development projects / Road projects

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • CA’s televised address to the nation on the eve of the Eid-ul-Adha on 6 June. Photo: Focus Bangla
    National election to be held any day in first half of April 2026: CA
  • File photo of BNP Standing Committee Member Amir Khasru Mahmud Chowdhury. Photo: Collected
    CA's election timeline 'bypasses' 90% political parties' demand for Dec 2025 polls: Khasru
  • Badiul Alam Majumdar. Photo: Collected
    One month enough for election campaigning after Eid-ul-Fitr next year: Badiul Alam

MOST VIEWED

  • BRAC Bank to issue Tk1,000cr social bond
    BRAC Bank to issue Tk1,000cr social bond
  • Long lines of vehicles were seen at the Mawa toll plaza, although movement remained smooth on 5 June 2025. Photos: TBS
    Padma Bridge sets new records for daily toll collection, vehicle crossings
  • The government vehicle into which a sacrificial cow was transported by a UNO. Photo: TBS
    Photo of Natore UNO putting cattle in govt vehicle takes social media by storm
  • Fire service personnel carry out rescue operations after Dhaka-bound Parjatak Express train hit a CNG auto-rickshaw last night (5 June). Several other vehicles also got trapped under the train. Photo: Mohammad Minhaj Uddin
    3 killed, several injured after Dhaka-bound Parjatak Express train hits CNG auto-rickshaw on Kalurghat bridge
  • China to help Bangladesh counter political disinformation in foreign media
    China to help Bangladesh counter political disinformation in foreign media
  • CA’s televised address to the nation on the eve of the Eid-ul-Adha on 6 June. Photo: Focus Bangla
    National election to be held any day in first half of April 2026: CA

Related News

  • Tk5,040cr allocation for PPP projects encouraging: Bida executive chairman
  • Recruiting skilled workers: Japan's restaurant group to open training centre in Dhaka
  • CA Yunus urges accelerated development of infrastructures in Moheshkhali, Matarbari
  • $1.07b loan deals likely during chief adviser's upcoming Japan visit
  • Prioritise environment while approving development projects: Rizwana

Features

Illustration: TBS

Unbearable weight of the white coat: The mental health crisis in our medical colleges

2d | Panorama
(From left) Sadia Haque, Sylvana Quader Sinha and Tasfia Tasbin. Sketch: TBS

Meet the women driving Bangladesh’s startup revolution

2d | Panorama
Illustration: TBS

The GOAT of all goats!

4d | Magazine
Photo: Nayem Ali

Eid-ul-Adha cattle markets

4d | Magazine

More Videos from TBS

Why is there a rift between Donald Trump and Elon Musk?

Why is there a rift between Donald Trump and Elon Musk?

13h | TBS World
Trump bans citizens of 12 countries, including Iran, from entering the United States

Trump bans citizens of 12 countries, including Iran, from entering the United States

14h | TBS World
Blacksmiths Hoping for Profit During Eid

Blacksmiths Hoping for Profit During Eid

19h | TBS Stories
Home Affairs Advisor explains security arrangements for empty Dhaka

Home Affairs Advisor explains security arrangements for empty Dhaka

19h | TBS Today
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net