A month's delay increases project cost by 0.95%: BIDS | The Business Standard
Skip to main content
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Friday
May 16, 2025

Sign In
Subscribe
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
FRIDAY, MAY 16, 2025
A month's delay increases project cost by 0.95%: BIDS

Infrastructure

TBS Report
18 May, 2023, 06:10 pm
Last modified: 18 May, 2023, 09:49 pm

Related News

  • World Bank to provide $280m loan to improve Ctg water supply, sanitation
  • Regional connectivity projects face unprecedented delays after political changeover
  • Bay Terminal: Tk14,908cr support project set for final govt approval
  • Matarbari deep-sea port construction deal with Japanese firms likely this month
  • Govt approves 29 new projects to combat climate change

A month's delay increases project cost by 0.95%: BIDS

It would be difficult to mitigate time and cost overruns without any reform in existing practice of land acquisition 

TBS Report
18 May, 2023, 06:10 pm
Last modified: 18 May, 2023, 09:49 pm
Photo: Unsplash
Photo: Unsplash

Highlights:

  • Development projects tend to go through multiple phases of revision 
  • Overruns delay benefits and can make them irrelevant
  • RHD implemented only 13.61% projects within the stipulated in 10 years
  • Delays cause welfare loss and hurt complementary private investment 

A month delay in the duration of development projects leads to an average of 0.95 percentage point increase in their implementation costs, according to findings of a research conducted by the Bangladesh Institute of Development Studies (BIDS).

For perspective, a project estimated at Tk10,000 crore can cost Tk95 crore more when its tenure faces escalation for a month due to various reasons, particularly delay in land acquisition.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

Without any reformation in existing practice of land acquisition, it would be difficult to mitigate time and cost overruns, the BIDS said. 

The information was revealed at a session on the second day of the BIDS Research Almanac 2023 on Thursday. Jayed Bin Satter, research associate of the BIDS presented the highlights of a research titled "Time and Cost Overrun in Development Projects: Evidence from Audit Reports of Roads Projects". 

Other key reasons for time escalation include delayed work order placements, price escalations, lack of skilled manpower, negotiation with stakeholders, and consultant recruitment by donor agencies.

Development projects in Bangladesh have a tendency to go through multiple phases of revision resulting in time escalation and cost escalation, the research finds. 

Time and cost overruns delay expected benefits from the project making them irrelevant, and in financial terms, delays cause welfare loss and hurt complementary private investment. 

"In the case of projects financed through borrowing, longer implementation periods have high rates of interest and add to more repayment schedule," according to research findings. 

For instance, the Roads and Highways Department (RHD) managed to implement only 13.61% of its development projects within the stipulated time and cost in the last ten years, Jayed Bin Satter said at the event. 

Furthermore, the tenure of about 80% of projects implemented by the RHD from FY13 to FY22 has seen an increase. At the same time, the cost of about 56% of the projects has been increased. 

He said the government placed the highest priority on the transportation and communication sector in the last decade and the allocation for the sector increased to 28.7% of the total Annual Development Programme (ADP) in the current fiscal year from 23.3% in FY14.

Dr Mohammad Emdad Ullah Mian, member of the Physical Infrastructure Division of the Planning Commission said that land acquisition is not the single reason for the delay in project implementation.

Although much importance is given by the concerned organisation at the time of project preparation and approval, it is neglected during the implementation phase, he added.

He also acknowledged that financing constraints are a significant cause of delays.

Top News

BIDS / project

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Banks struggle in their core business as net interest income falls
    Banks struggle in their core business as net interest income falls
  • Jagannath University students and teachers protest at the Kakrail Mosque intersection in Dhaka on 15 May 2025. Photo: Mehedi Hasan/TBS
    JnU teachers, students to go on mass hunger strike after Friday prayers
  • Selim Jahan. TBS Sketch
    Ending the stalemate and thereafter: The IMF loans in Bangladesh

MOST VIEWED

  • Chief Adviser Muhammad Yunus speaking at Chittagong Port on 14 May 2025. Photo: CA Press Wing
    Ctg port must emerge as best with int'l standard facilities for economic growth: CA
  • Shahriar Alam Shammo. Photo: Collected
    3 arrested over JCD leader Shammo killing
  • Up to 20% dearness allowance for govt employees likely from July
    Up to 20% dearness allowance for govt employees likely from July
  • Chief Adviser Muhammad Yunus on a visit to Chattogram on 14 May 2025. Photo: TBS
    CA Yunus begins Chattogram tour with packed engagements
  • Infograph: TBS
    Govt plans to align official land price with market rates
  • Infographics: TBS
    $3.5b loan unlocked with shift to market-based exchange rate

Related News

  • World Bank to provide $280m loan to improve Ctg water supply, sanitation
  • Regional connectivity projects face unprecedented delays after political changeover
  • Bay Terminal: Tk14,908cr support project set for final govt approval
  • Matarbari deep-sea port construction deal with Japanese firms likely this month
  • Govt approves 29 new projects to combat climate change

Features

Hatitjheel’s water has turned black and emits a foul odour, causing significant public distress. Photo: Syed Zakir Hossain

Blackened waters and foul stench: Why can't Rajuk control Hatirjheel pollution?

4h | Panorama
An old-fashioned telescope, also from an old ship, is displayed at a store at Chattogram’s Madam Bibir Hat area. PHOTO: TBS

NO SCRAP LEFT BEHIND: How Bhatiari’s ship graveyard still furnishes homes across Bangladesh

1d | Panorama
Sketch: TBS

‘National University is now focusing on technical and language education’

2d | Pursuit
Illustration: TBS

How to crack the code to get into multinational companies

2d | Pursuit

More Videos from TBS

Ben Cohen arrested for protesting US support for Israel

Ben Cohen arrested for protesting US support for Israel

1h | TBS News Updates
What is the secret behind the success of Pakistan's Chinese J-10C fighter jet?

What is the secret behind the success of Pakistan's Chinese J-10C fighter jet?

2h | Others
Why are Jagannath University students and teachers on a blockade?

Why are Jagannath University students and teachers on a blockade?

2h | Podcast
Is Real ID USA security or immigration confusion?

Is Real ID USA security or immigration confusion?

2h | Others
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net