95% construction work of MRT Line-1 depot completed | The Business Standard
Skip to main content
  • Latest
  • Epaper
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Thursday
June 19, 2025

Sign In
Subscribe
  • Latest
  • Epaper
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
THURSDAY, JUNE 19, 2025
95% construction work of MRT Line-1 depot completed

Infrastructure

BSS
15 April, 2025, 07:05 pm
Last modified: 15 April, 2025, 07:19 pm

Related News

  • 123 more Bangladeshi migrants repatriated from Libya
  • BCG organises free medical camp and awareness event in khulna
  • Pvt sector's foreign loan rises by $454m on stable exchange rate, reserve in three months
  • BAEC clarifies position on testing fees, certification timeframe
  • Constitutional Council, president election dominate talks, no consensus reached

95% construction work of MRT Line-1 depot completed

Project Director of Dhaka Mass Rapid Transit Development Project (Line-1), Md Abul Kashem Bhuiyan, said under the contract package-1, construction of the depot on 35.90 hectares of land at Pitalganj in Rupganj under Narayanganj district is almost completed

BSS
15 April, 2025, 07:05 pm
Last modified: 15 April, 2025, 07:19 pm
Dhaka metro rail. File Photo: TBS
Dhaka metro rail. File Photo: TBS

At least 95% of construction work of the MRT Line-1 depot has been completed so far, while works are progressing fast, aimed at completing the MRT Line-1 by 2028.

Talking to BSS, Project Director of Dhaka Mass Rapid Transit Development Project (Line-1), Md Abul Kashem Bhuiyan, said under the contract package-1, construction of the depot on 35.90 hectares of land at Pitalganj in Rupganj under Narayanganj district is almost completed. 

"The financial progress rose to 88% while the realistic progress stood at 95%. Contract package-1 (CP-1) for the construction of civil work of depot and CP-2 documents will be sent to the head office for approval," he said.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

The project director said the MRT Line-1 has a total of 19,872 kilometres of underground, consisting airport route with 12 underground stations, while an 11,369-kilometre elevated section from Notun Bazar to Pitalganj Depot of Purbachal route with seven elevated and two underground stations is being implemented through a total of 12 packages. 

The Line-1, having two parts - the Airport Route and the Purbachal Route is being constructed with 12 packages, as the construction work of both the routes began on 2 February 2023, he added.

According to the project details, Dhaka Mass Transit Company Limited (DMTCL) has been implementing the MRT Line-1 with 12 packages.

Of the packages, the authorities sent draft contract documents of CP-2 and CP-5 to the  Japan International Cooperation Agency (JICA) on 13 March 2025 after completing the pre-contract negotiation process for getting no objections.

Besides, processes are on for retendering of CP-3, as no pre-qualified bidder submitted their tender documents during the tender schedule period.

The financial proposal of CP-4 was opened on 27 February 2025, while the evaluation of the financial proposal is underway, it said. 

Pre-contract negotiation with the lowest bidder under the CP-6 is going on after getting JICA's concurrence on the evaluation report of the financial proposal on 13 February.

The DMTCL is evaluating the technical proposal of the tender documents under contract package 7, which was floated on 27 February 2025.

The authority has re-fixed on 17 April for opening of the tender documents of the CP-8, which was floated on 4 November 2024.

Technical evaluation proposal reports of CP-9 and 10 were sent on 2 March 2025 and 19 March 2025 respectively, to JICA for concurrence. 

The tender documents for both packages were invited on 23 December 2024 and 9 December 2024 respectively.

 The DMTCL has invited a tender for the CP-10 on 9 January 2025. 22 April will be the last date for submitting tender documents.

The CP-12 was invited on 19 February 2025, while the tender documents will be opened on 2 June 2025.

The project details said the entire MRT Line-1 project is being implemented in 12 packages at a cost of Tk. 53,977 crore while the JICA is providing Tk. 39,450 crore as project assistance and the Bangladesh government is giving Tk. 14,527 crore.

Experts said 13.66 lakh people can move by this metro rail per day which is about 2.83 times higher than the existing MRT Line-6.

They said the government is moving forward with the mega plan to build a 140-kilometer metro rail network in Dhaka and its adjacent areas by 2030 to reduce traffic congestion.

Once the planned network consisting of six lines comes into reality, 50 lakh people will be able to use the facilities as the lines will cover 129 kilometres area of the city - about 68 km elevated and about 61km underground - having more than 100 stations.

Bangladesh

MRT / Bangladesh / depot

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • A drone photo shows the damage over residential homes at the impact site following missile attack from Iran on Israel, in Tel Aviv, Israel June 16, 2025. Photo: REUTERS/Moshe Mizrahi/File Photo
    Israel says hospital struck by Iranian missiles as Trump weighs US involvement
  • Photo: Screengrab
    Enforced disappearance perpetrators still threatening victims, families: Inquiry commission chief
  • Missiles launched from Iran are intercepted as seen from Ashkelon, Israel, June 18, 2025. REUTERS/Amir Cohen
    Explainer: How did Iran manage to pierce through Israel’s air defence systems?

MOST VIEWED

  • Logo of Beximco Group. Photo: Collected
    Beximco defaults on €33m in Germany, Deshbandhu owes Czech bank €4m
  • The India-Bangladesh integrated checkpost in Fulbari. Photo: Passang Yolmo via Telegraph India
    Import of boulders from Bhutan to Bangladesh stopped by Indian transporters in Fulbari
  • Infograph: TBS
    End of a loophole: Defaulters on foreign loans barred from local bank borrowing
  • Smoke rises following an Israeli attack on the IRIB building, the country's state broadcaster, in Tehran, Iran, June 16, 2025. Majid Asgaripour/WANA (West Asia News Agency) via REUTERS
    Israel-Iran War: Russia says Israel's attacks illegal, UAE warns of 'uncalculated, reckless steps'
  • An anti-missile system operates as missiles are launched from Iran, as seen from Tel Aviv, Israel, 18 June 2025. Photo: Reuters
    Khamenei rejects Trump's demand for surrender, Trump says 'good luck'
  • Soldiers salute Arakan Army chief Major General Twan Mrat Naing during a parade in Myanmar, 6 April 2018. File Photo: Arakan Army deputy chief Brig Gen Nyo Twan Awng/Twitter
    Rohingya militant groups recruit from camps to fight Arakan Army, warns Crisis Group

Related News

  • 123 more Bangladeshi migrants repatriated from Libya
  • BCG organises free medical camp and awareness event in khulna
  • Pvt sector's foreign loan rises by $454m on stable exchange rate, reserve in three months
  • BAEC clarifies position on testing fees, certification timeframe
  • Constitutional Council, president election dominate talks, no consensus reached

Features

Evacuation of Bangladeshis: Where do they go next from conflict-ridden Iran?

Evacuation of Bangladeshis: Where do they go next from conflict-ridden Iran?

17h | Panorama
The Kallyanpur Canal is burdened with more than 600,000 kilograms of waste every month. Photo: Courtesy

Kallyanpur canal project shows how to combat plastic pollution in Dhaka

1d | Panorama
The GLS600 overall has a curvaceous nature, with seamless blends across every panel. PHOTO: Arfin Kazi

Mercedes Maybach GLS600: Definitive Luxury

3d | Wheels
Renowned authors Imdadul Haque Milon, Mohit Kamal, and poet–children’s writer Rashed Rouf seen at Current Book Centre, alongside the store's proprietor, Shahin. Photo: Collected

From ‘Screen and Culture’ to ‘Current Book House’: Chattogram’s oldest surviving bookstore

3d | Panorama

More Videos from TBS

Iran's Missile Range: How Far Can Tehran's Weapons Strike?

Iran's Missile Range: How Far Can Tehran's Weapons Strike?

32m | Others
Will the US be able to overthrow the Iranian government? What does history say?

Will the US be able to overthrow the Iranian government? What does history say?

2h | TBS World
From Local to Global: The World Burns in the Fire of Conflict

From Local to Global: The World Burns in the Fire of Conflict

3h | TBS World
What's going on in Netanyahu's head behind the regime change story?

What's going on in Netanyahu's head behind the regime change story?

17h | TBS World
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net