Akhaura-Agartala railway project contractor to be changed if negligence found: Minister | The Business Standard
Skip to main content
  • Latest
  • Epaper
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Thursday
June 19, 2025

Sign In
Subscribe
  • Latest
  • Epaper
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
THURSDAY, JUNE 19, 2025
Akhaura-Agartala railway project contractor to be changed if negligence found: Minister

Bangladesh

Saifuddin Saif
07 April, 2022, 01:35 pm
Last modified: 08 April, 2022, 04:35 am

Related News

  • Pvt sector's foreign loan rises by $454m on stable exchange rate, reserve in three months
  • BAEC clarifies position on testing fees, certification timeframe
  • Constitutional Council, president election dominate talks, no consensus reached
  • Stocks rise amid Middle East tensions
  • Poultry sector faces crisis from DOC production instability: Experts

Akhaura-Agartala railway project contractor to be changed if negligence found: Minister

Even after extending the deadline for three times, only half of the construction has been completed so far

Saifuddin Saif
07 April, 2022, 01:35 pm
Last modified: 08 April, 2022, 04:35 am
Photo: TBS
Photo: TBS

Railways Minister Nurul Islam Sujan has warned that if negligence of duty is found, the Indian contractor of the Akhaura-Agartala dual-gauge railway link project would be changed.

Visiting the project site in Akhaura on Thursday, Sujan said, "Hopefully the contractor will understand our concerns. If I see that the works have stopped due to any negligence on his [the contractor's] part, I will be forced to get someone new."

According to a Bangladesh Railway report, the Indian contractor has been appointed to implement the project as per the terms of the Indian Line of Credit. Indian manpower is also working on this project. The construction materials for the project have to be imported from India. 

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

The railway report said the Indian contractor could not bring construction materials from India as manufacturing companies of sleeper and other materials were closed for a long time due to the pandemic. Besides, the Indian manpower employed in the project also faced problems coming to Bangladesh. Due to these reasons, the implementation of the project was delayed and the implementation deadline needs to be extended.

During the visit, the railways minister expressed dissatisfaction over the slow pace of implementation of the project, being implemented with Indian funding, and instructed the Indian contractor to complete the construction fully by next December.

Indian High Commissioner Vikram Kumar Doraiswami was also present at that time.

Talking to the media, the railway minister said, "The contractor we hired has informed us that the installation of railway tracks will be completed by June. The rest of the work may take a little longer. He (the contractor) blamed the Covid pandemic for all the delay. We have to accept the excuse considering the present circumstances." 

The minister said, "The project's deadline expires this June. But we will be happy if things are completed by December."

With an aim to establish rail communication with Seven Sister states, including Tripura, in India, implementation of the Akhaura-Agartala dual gauge railway project began in June 2016 with Indian loan funding. The project was scheduled to be completed in two and a half years. But the construction work could not be completed even after extending the deadline three more times.

Already three years behind schedule, the Akhaura-Agartala railway project is going to miss its current deadline of next June too. Even after extending the deadline three times, only half of the construction has been completed so far.

From the beginning, the implementation of the project has been slow. Later, due to Covid pandemic, construction work at the field level was stopped from March 2020. 

According to the railway report, implementation of the project was halted as construction materials and Indian manpower working on the project could not reach the project area due to the pandemic.

The last deadline for completion of the project was until next June, but so far only 52% work has been completed. In this situation, the Railway has proposed to extend the deadline for another year, till June 2023. In a letter dated 13 March, the Railway informed the Planning Commission, the Implementation Monitoring and Evaluation Division and the Economic Relations Department (ERD) about the extension of the deadline. 

The total length of Akhaura-Agartala railway is 10.5 kilometers with 4 kilometers in India and 6.5 kilometers in Bangladesh. This railway line will run from Gangasagar railway station in Akhaura upazila of Brahmanbaria to Nishchintopur border in Agartala. People of the two countries will be able to travel very easily and at low cost if this much desired railway is constructed.

The contract for the Bangladesh part of the Akhaura-Agartala railway project was signed on 21 May 2016 with Texmaco Rail and Engineering Limited, a New Delhi-based contractor. The contractor started construction of the railway on 29 July, 2016.

India is providing a Tk420.76 crore loan for the Tk477.81 crore project.

Sujan, while addressing the press, said, "This is a very important project for Bangladesh and India. I and Doraiswami are both disappointed to see the slow progress of the project."

The Indian high commissioner to Bangladesh also echoed Sujan.

He said that the prime ministers of the two countries have given utmost importance to the implementation of the project. 

"I hope the works will be completed within the extended deadline. We are also under pressure to finish the project quickly."

The minister was accompanied by senior officials of the Bangladesh Railway.

Top News / South Asia

Bangladesh / India / Bangladesh-India rail link / Akhaura-Agartala rail link

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Pvt sector's foreign loan rises by $454m on stable exchange rate, reserve in three months
    Pvt sector's foreign loan rises by $454m on stable exchange rate, reserve in three months
  • An anti-missile system operates as missiles are launched from Iran, as seen from Tel Aviv, Israel, 18 June 2025. Photo: Reuters
    Khamenei rejects Trump's demand for surrender, Trump says 'good luck'
  • Evacuation of Bangladeshis: Where do they go next from conflict-ridden Iran?
    Evacuation of Bangladeshis: Where do they go next from conflict-ridden Iran?

MOST VIEWED

  • Infograph: TBS
    Govt to ease loan rules to help foreign firms expand in Bangladesh
  • Google Pay. Photo: Collected
    Google Pay coming to Bangladesh next week
  • Logo of Beximco Group. Photo: Collected
    Beximco defaults on €33m in Germany, Deshbandhu owes Czech bank €4m
  • Global map showing nuclear weapon inventories by country as of January 2025, including deployed, stored, and retired warheads. Source: SIPRI
    How Israel's secret nuclear arsenal comes under spotlight amid attacks on Iran
  • The Kallyanpur Canal is burdened with more than 600,000 kilograms of waste every month. Photo: Courtesy
    Kallyanpur canal project shows how to combat plastic pollution in Dhaka
  • The India-Bangladesh integrated checkpost in Fulbari. Photo: Passang Yolmo via Telegraph India
    Import of boulders from Bhutan to Bangladesh stopped by Indian transporters in Fulbari

Related News

  • Pvt sector's foreign loan rises by $454m on stable exchange rate, reserve in three months
  • BAEC clarifies position on testing fees, certification timeframe
  • Constitutional Council, president election dominate talks, no consensus reached
  • Stocks rise amid Middle East tensions
  • Poultry sector faces crisis from DOC production instability: Experts

Features

Evacuation of Bangladeshis: Where do they go next from conflict-ridden Iran?

Evacuation of Bangladeshis: Where do they go next from conflict-ridden Iran?

5h | Panorama
The Kallyanpur Canal is burdened with more than 600,000 kilograms of waste every month. Photo: Courtesy

Kallyanpur canal project shows how to combat plastic pollution in Dhaka

1d | Panorama
The GLS600 overall has a curvaceous nature, with seamless blends across every panel. PHOTO: Arfin Kazi

Mercedes Maybach GLS600: Definitive Luxury

2d | Wheels
Renowned authors Imdadul Haque Milon, Mohit Kamal, and poet–children’s writer Rashed Rouf seen at Current Book Centre, alongside the store's proprietor, Shahin. Photo: Collected

From ‘Screen and Culture’ to ‘Current Book House’: Chattogram’s oldest surviving bookstore

3d | Panorama

More Videos from TBS

What's going on in Netanyahu's head behind the regime change story?

What's going on in Netanyahu's head behind the regime change story?

5h | TBS World
The type of bomb the US could use if Trump attacks Iran

The type of bomb the US could use if Trump attacks Iran

5h | TBS World
Why is Fordow Nuclear Facility at the Center of Trump’s Deliberations?

Why is Fordow Nuclear Facility at the Center of Trump’s Deliberations?

8h | TBS World
AI will replace jobs at tech giant: Amazon CEO

AI will replace jobs at tech giant: Amazon CEO

8h | Others
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net