Tangail-Rangpur highway: Progress 73%, completion unlikely this year | The Business Standard
Skip to main content
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Saturday
May 31, 2025

Sign In
Subscribe
  • Epaper
  • Economy
    • Aviation
    • Banking
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
SATURDAY, MAY 31, 2025
Tangail-Rangpur highway: Progress 73%, completion unlikely this year

Infrastructure

Khorshed Alam
03 March, 2024, 12:30 pm
Last modified: 03 March, 2024, 12:35 pm

Related News

  • Rough weather slows down Chattogram Port operations
  • Govt opens 220 shelter centres to tackle rain-spawn disasters in Bandarban 
  • 2 missing after being swept away by strong currents in Khagrachari rivers
  • Under-construction embankment collapse kills child in Bhola
  • Speaking about country’s problems in foreign trips won’t solve them: Khasru takes jibe at Yunus

Tangail-Rangpur highway: Progress 73%, completion unlikely this year

Khorshed Alam
03 March, 2024, 12:30 pm
Last modified: 03 March, 2024, 12:35 pm
With major lanes closed off, transports navigate narrow lanes as upgrade work of the 190-kilometre Tangail-Rangpur road into a four-lane highway is underway. Launched in 2016, the project was initially slated for completion by 2021 but officials say it is unlikely to be completed by the extended deadline of December 2024. The photo was taken recently. Photo: Khorshed Alam
With major lanes closed off, transports navigate narrow lanes as upgrade work of the 190-kilometre Tangail-Rangpur road into a four-lane highway is underway. Launched in 2016, the project was initially slated for completion by 2021 but officials say it is unlikely to be completed by the extended deadline of December 2024. The photo was taken recently. Photo: Khorshed Alam

Highlights: 

  • Around 73% of the overall project work has been completed
  • Dec 2024 deadline set to be missed
  • The project is being implemented under 11 packages
  • 3 packages (Bangabandhu Bridge east, west and Gobindaganj) are stalled
  • Officials said land acquisition complexities are behind the delay

Upgrading the 190-kilometre Tangail-Rangpur road into a four-lane highway has progressed around 73%, yet complexity in land acquisition stands in the way of completing the project by the deadline of December this year. 

This highway is a lifeline for the people of northern Bangladesh, carrying thousands of vehicles daily. However, the ongoing construction work, combined with the already heavy traffic, is causing frequent gridlocks at several points. This situation is likely to worsen during the upcoming Eid holidays, leading to longer-than-usual traffic jams for northbound travellers.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

Launched in 2016, the South Asia Subregional Economic Cooperation (Sasec) road connectivity project was initially slated for completion by 2021 but the deadline was extended until December 2024. The project design had to be altered as land could not be acquired as per plan due to several existing structures, said officials. 

Photo: Khorshed Alam/TBS
Photo: Khorshed Alam/TBS

Hamidul Haque, additional project director of the project, said the highway is being developed under 11 packages and some of the packages would not be able to meet their completion deadlines, especially the Bangabandhu Bridge East and West packages and Gobindaganj package.

The Bangabandhu Bridge packages are of utmost significance as they serve as key entry points for vehicles from the North-West region via Tangail's Elenga, he said.

Also, it would take up to December 2025 to complete the work on a three-km road package in Gaibanda's Gobindaganj, which was stalled due to land acquisition issues, the official said.

The project work was initially divided into nine packages but later two packages for constructing two cloverleaf interchanges at both ends of Sirajganj were added. 

Photo: Khorshed Alam/TBS
Photo: Khorshed Alam/TBS

Hamidul Haque, however, assured that all work on the highway is expected to be fully completed by December 2025.

Several other officials engaged in the project, speaking anonymously, said there are two packages located east and west of the Bangabandhu Bridge, covering 13 and 30 kilometres respectively. Progress in these areas has been notably sluggish, with the combined completion rate of these two projects below 50%. The required land has been acquired recently for the Gobindaganj package but it is currently a marketplace. Demolishing these structures and commencing work is expected to take considerable time.

According to Bangabandhu Bridge authorities, during regular periods, approximately 16-17,000 vehicles pass through the bridge daily. However, during Eid, the average number escalates to 42,000 vehicles. These vehicles travel to various districts within the Khulna, Rangpur, and Rajshahi divisions via the bridge. Hence, expediting the construction progress of the Tangail and Sirajganj sections of the project is deemed crucial.

Photo: Khorshed Alam/TBS
Photo: Khorshed Alam/TBS

The road construction spanning from Sherpur in Bogra to Banani in Shahjahanpur falls under package number eight, managed by CPCL Tantia JV Company. At the project's outset, the contracting company faced a 19-month hiatus due to complications in land acquisition for this section.

Mamun Kaiser, the package manager, said, "While most structures in the area have been cleared following various notices, the acquisition of 4.34 acres of land remains pending. Despite repeated notifications to the district administration, uncertainty looms over its acquisition, which significantly impacts our project timeline."

"In the absence of timely land acquisition, completing the package as scheduled poses a challenge. However, we aim to proceed with available spaces. Around 80% of our package has been completed thus far," he added.

Photo: Khorshed Alam/TBS
Photo: Khorshed Alam/TBS

Project details

The 190km road is one of the eight new highways of Bangladesh - 600km in total - which will be added to the proposed South Asia Subregional Economic Cooperation Road Connectivity, said project Spokesperson and Executive Engineer Joy Prakash Chowdhury.

The highway in Northern Bangladesh is expected to help grow industries in the region as well as increase direct trade with India and Nepal.

The construction of the road started in 2016 with an estimated cost of Tk11,899 crore. Later the cost was revised up to Tk16,662 crores. Two flyovers, 26 bridges, a railway and 11 steel-foot overbridges will also be built under the project.

The Roads and Highways Department is constructing the road with the financial assistance of the Asian Development Bank (ADB) under the Sasec project. 

Bangladesh / Top News

Tangail-Rangpur Highway / road communication / Road Connection / Bangladesh / Road Transport and Highway Division (RTHD)

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Chief Adviser Muhammad Yunus meets Japanese Prime Minister Ishiba Shigeru in Japan on 30 May 2025. Photo: CA Office
    Bangladesh, Japan to sign Economic Partnership Agreement by year-end
  • File photo of BNP BNP Standing Committee Member Amir Khasru Mahmud Chowdhury
    Speaking about country’s problems in foreign trips won’t solve them: Khasru takes jibe at Yunus
  • Representational image. Photo: Collected
    'Heavy to very heavy' rainfall expected across country as land depression weakens further

MOST VIEWED

  • Photo: Courtesy
    New notes featuring historic, archaeological structures of Bangladesh to be circulated from 1 June
  • Two Memoranda of Understanding were signed at the seminar titled “Bangladesh Seminar on Human Resources,” in Tokyo on 29 May 2025. Photo: CA Press Wing
    Japan to recruit 100,000 Bangladeshi workers over next 5 years
  • BAT Bangladesh has to vacate Mohakhali HQ as SC rejects lease appeal
    BAT Bangladesh has to vacate Mohakhali HQ as SC rejects lease appeal
  • Representational Photo: Collected
    Country's all jewellery shops to remain indefinitely closed in protest of VP Reponul's arrest: Bajus
  • Khondoker Rashed Maqsood. File Photo: Collected
    Investors urge removal of BSEC chairman in meeting with CA’s special assistant, submit list of demands
  • Illustration: TBS
    Bangladesh repays $3.5b foreign debt in 10 months of FY25

Related News

  • Rough weather slows down Chattogram Port operations
  • Govt opens 220 shelter centres to tackle rain-spawn disasters in Bandarban 
  • 2 missing after being swept away by strong currents in Khagrachari rivers
  • Under-construction embankment collapse kills child in Bhola
  • Speaking about country’s problems in foreign trips won’t solve them: Khasru takes jibe at Yunus

Features

Babar Ali, Ikramul Hasan Shakil, and Wasfia Nazreen are leading a bold resurgence in Bangladeshi mountaineering, scaling eight-thousanders like Everest, Annapurna I, and K2. Photos: Collected

Back to 8000 metres: How Bangladesh’s mountaineers emerged from a decade-long pause

7h | Panorama
Photos: Courtesy

Behind the looks: Bangladeshi designers shaping celebrity fashion

9h | Mode
Photo collage of the sailors and their catch. Photos: Shahid Sarkar

Between sky and sea: The thrilling life afloat on a fishing ship

13h | Features
For hundreds of small fishermen living near this delicate area, sustainable fishing is a necessity for their survival. Photo: Syed Zakir Hossain

World Ocean Day: Bangladesh’s ‘Silent Island’ provides a fisheries model for the future

1d | The Big Picture

More Videos from TBS

Six Lakh Sacrificial Animals Ready in Sirajganj for Eid-ul-Adha

Six Lakh Sacrificial Animals Ready in Sirajganj for Eid-ul-Adha

4h | TBS Stories
Six MoUs signed during Chief Advisor's visit to Japan

Six MoUs signed during Chief Advisor's visit to Japan

7h | TBS Today
Record migrant deaths in 2024

Record migrant deaths in 2024

1d | Podcast
Govt likely to trim subsidies in new budget

Govt likely to trim subsidies in new budget

11h | TBS Insight
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net