Revised ADP: Allocations up for some mega projects, down for others | The Business Standard
Skip to main content
  • Latest
  • Epaper
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Saturday
June 28, 2025

Sign In
Subscribe
  • Latest
  • Epaper
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
SATURDAY, JUNE 28, 2025
Revised ADP: Allocations up for some mega projects, down for others

Infrastructure

Saifuddin Saif
19 March, 2020, 10:05 am
Last modified: 19 March, 2020, 11:39 am

Related News

  • Mega projects were tools for looting, not rural development: Adviser Fouzul
  • ADP spending drops Tk24,718cr in Jul-Mar
  • Tk2.16 lakh crore allocated for revised ADP
  • Revised ADP set for 11.83% YoY lower
  • Costs of Hasina govt's 8 mega projects overran by $7b. Task force finds 8 reasons

Revised ADP: Allocations up for some mega projects, down for others

The government will trim the ADP size by Tk9,800 owing to complexities over land acquisition and tender invitation, and lack of efficiency in project implementation

Saifuddin Saif
19 March, 2020, 10:05 am
Last modified: 19 March, 2020, 11:39 am
Photo: Mumit M/TBS
Photo: Mumit M/TBS

The government is going to decrease allocations for some mega projects and increase for a few others in the revised Annual Development Programme. 

The Padma bridge, the Padma bridge rail link, the metro rail and the Rooppur nuclear power plant will see a drop in allocations while Karnaphuli Tunnel, Dohazari-Cox's Bazar rail line, Matarbari 1200-megawatt coal-fired power plant and the improvement of Joydevpur-Chandra-Tangail-Elenga Road to a 4-lane Highway will get more funds.

The revised ADP with an outlay of Tk192,921 crore will be placed before a meeting of the National Economic Council today for its final approval.  Prime Minister Sheikh Hasina will preside over the meeting to be held at the NEC auditorium in the capital's Sher-e-Bangla Nagar area.

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

The government will trim the ADP size by Tk9,800 crore from Tk202,721 crore initially allocated for the current fiscal year owing to complexities over land acquisition and tender invitation, and lack of efficiency in project implementation. 

The Padma Multipurpose Bridge Project is going to be allocated Tk4,015 crore which is T1,355.69 crore lower than the original allocation of Tk5,370.69 crore.

Bridges division officials said about one-third of the Chinese workers of the project could not join their work as they were either kept in quarantine or not allowed to leave their country.

Project Director Shafiqul Islam said, "Work on the Padma bridge site could not be carried out in January and February as per the plan. The implementation speed has slowed down greatly."

The allocation for Padma rail link project will also drop by Tk698 crore from Tk3,995 crore.

The allocation for the Mass Rapid Transit (MRT) line-6) will be reduced to Tk4,226.73 from the original allocation of Tk7212.63 crore. 

Additionally, the allocation for the Rooppur Nuclear Power Plant project will drop by Tk134 crore from the original allocation of Tk14,980 crore in the revised ADP.

On the other hand, despite the absence of 288 Chinese technical personnel, allocation for the Karnaphuli Tunnel project will rise about 15 percent to Tk1549.08 crore in the revised ADP. 

In the revised ADP, the newly-approved projects – MRT Line-1 and MRT Line-5 (north) – will get Tk487.84 crore and Tk140 crore in fresh allocations respectively. 

Planning Minister MA Mannan said there is not much time left in the current fiscal year. The implementation speed of many projects is very good. But work on some projects is being affected for the coronavirus outbreak. 

"When the situation becomes normal, we will run project works in double shifts," he added. 

In the absence of foreign engineers at the Matarbari coal-fired plant, the allocation for it in the revised ADP will increase by Tk179 crore. The original allocation was Tk3056 crore.

With no headway in acquiring land for the Maheshkhali power hub for the last three years, the project has been given a token fund of Tk1 lakh to help it survive.

The improvement of Joydevpur-Chandra-Tangail-Elenga Road to a 4-lane Highway will see a rise in allocation by 33 percent to Tk1,000 crore. 

On the other hand, the allocation for Elenga-Hatikumrul-Rangpur 4-lane highway will increase by Tk119 crore. The original allocation was Tk1050 crore.

The Dohazari-Cox's Bazar-Gundum rail line construction project will see a Tk30 crore hike in allocation with the original amount of Tk1,105 crore. 

Dr Ahsan H Mansur, executive director of Policy Research Institute, said coronavirus is now slowing down in China. The problem will be solved within one or two months.

When the Chinese experts arrive, project works will be accelerated after keeping them in quarantine for a certain period.

Top News

ADP / mega projects

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Protesting NBR officials observe “Complete Shutdown” programme at the NBR headquarters in Agargaon, Dhaka on 28 June 2025. Photo: TBS
    Protesting NBR officials to continue shutdown tomorrow
  • Planning Adviser Wahiduddin Mahmud attends a views-exchange meeting at the Chattogram Circuit House on 28 June 2025. Photo: TBS
    Ensure law and order, prepare for credible election: Adviser Wahiduddin tells govt officials
  • News of The Day, 28 JUNE 2025
    News of The Day, 28 JUNE 2025

MOST VIEWED

  • A crane loads wheat grain into the cargo vessel Mezhdurechensk before its departure for the Russian city of Rostov-on-Don in the course of Russia-Ukraine conflict in the port of Mariupol, Russian-controlled Ukraine, October 25, 2023. REUTERS/Alexander Ermochenko/File Photo
    Ukraine calls for EU sanctions on Bangladeshi entities for import of 'stolen grain'
  • Illustration: TBS
    US Embassy Dhaka asks Bangladeshi student visa applicants to make social media profiles public
  • M Niaz Asadullah among 3 new members now on Nagad’s management board
    M Niaz Asadullah among 3 new members now on Nagad’s management board
  • Sketch: TBS
    Transforming healthcare: How Parisha Shamim is redefining patient care at Labaid
  • Officials from Bangladesh and Japan governments during an agreement signing ceremony on 27 June 2025. Photo: Courtesy
    Bangladesh signs $630m loan deal with Japan for Joydebpur-Ishwardi rail project
  • Representational image. Photo: Collected
    Biman flight to Singapore returns to Dhaka shortly after takeoff due to engine issue

Related News

  • Mega projects were tools for looting, not rural development: Adviser Fouzul
  • ADP spending drops Tk24,718cr in Jul-Mar
  • Tk2.16 lakh crore allocated for revised ADP
  • Revised ADP set for 11.83% YoY lower
  • Costs of Hasina govt's 8 mega projects overran by $7b. Task force finds 8 reasons

Features

Graphics: TBS

Drop of poison, sea of consequences: How poison fishing is wiping out Sundarbans’ ecosystems and livelihoods

1d | Panorama
Photo: Collected

The three best bespoke tailors in town

1d | Mode
Zohran Mamdani gestures as he speaks during a watch party for his primary election, which includes his bid to become the Democratic candidate for New York City mayor in the upcoming November 2025 election, in New York City, US, June 25, 2025. REUTERS/David 'Dee' Delgado

What Bangladesh's young politicians can learn from Zohran Mamdani

2d | Panorama
Footsteps Bangladesh, a development-based social enterprise that dared to take on the task of cleaning a canal, which many considered a lost cause. Photos: Courtesy/Footsteps Bangladesh

A dead canal in Dhaka breathes again — and so do Ramchandrapur's residents

2d | Panorama

More Videos from TBS

News of The Day, 28 JUNE 2025

News of The Day, 28 JUNE 2025

17m | TBS News of the day
Business leaders demand resolution to NBR deadlock today, warn of daily Tk2,500cr trade disruption

Business leaders demand resolution to NBR deadlock today, warn of daily Tk2,500cr trade disruption

2h | TBS Today
What did Trump say about the ceasefire in Gaza?

What did Trump say about the ceasefire in Gaza?

1h | TBS World
Supreme Court ruling expands Trump's power

Supreme Court ruling expands Trump's power

3h | TBS World
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net