Ctg link road risky as rain erodes soil for lack of retaining walls | The Business Standard
Skip to main content
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
The Business Standard

Sunday
July 13, 2025

Sign In
Subscribe
  • Latest
  • Economy
    • Banking
    • Stocks
    • Industry
    • Analysis
    • Bazaar
    • RMG
    • Corporates
    • Aviation
  • Videos
    • TBS Today
    • TBS Stories
    • TBS World
    • News of the day
    • TBS Programs
    • Podcast
    • Editor's Pick
  • World+Biz
  • Features
    • Panorama
    • The Big Picture
    • Pursuit
    • Habitat
    • Thoughts
    • Splash
    • Mode
    • Tech
    • Explorer
    • Brands
    • In Focus
    • Book Review
    • Earth
    • Food
    • Luxury
    • Wheels
  • Subscribe
    • Epaper
    • GOVT. Ad
  • More
    • Sports
    • TBS Graduates
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • Gallery
    • Long Read
    • Interviews
    • Offbeat
    • Magazine
    • Climate Change
    • Health
    • Cartoons
  • বাংলা
SUNDAY, JULY 13, 2025
Ctg link road risky as rain erodes soil for lack of retaining walls

Bangladesh

TBS Report
07 August, 2021, 09:45 am
Last modified: 07 August, 2021, 12:15 pm

Related News

  • Water Development Board launches drive in Ctg to recover govt land from 39 influential grabbers
  • Dismembering woman's body: Husband arrested in Ctg
  • Padma erosion: Shariatpur homeless families face eviction from govt land
  • Swechchhasebak League leader found dead in Ctg
  • Three-year-old child dies after falling into open drain in Chattogram

Ctg link road risky as rain erodes soil for lack of retaining walls

The soil on both sides of the bridges is being washed away in rain as the retaining walls have not been constructed

TBS Report
07 August, 2021, 09:45 am
Last modified: 07 August, 2021, 12:15 pm
Several parts of the bridge built on the Faujdarhat-Bayezid link road have collapsed due to heavy rain and landslides. The photo was taken on Thursday. Photo: Mohammad Minhaj Uddin
Several parts of the bridge built on the Faujdarhat-Bayezid link road have collapsed due to heavy rain and landslides. The photo was taken on Thursday. Photo: Mohammad Minhaj Uddin

Bridges on the Faujdarhat-Baizid Bostami link road in Chattogram have become risky for traffic due to erosion of soil by heavy rain in absence of retaining walls.   

There are six bridges on the road, and more than a foot of the road on the west side of the bridge no 5 has been eroded by rainwater.

The Chattogram Development Authority (CDA) built the six-kilometer road cutting 16 hills. The hills have often been collapsing on it since the construction began.  

The Business Standard Google News Keep updated, follow The Business Standard's Google news channel

The soil on both sides of the bridges has been washed away as the construction company did not build the retaining walls. 

Earlier on 8 June, the CDA, which constructed the link road, suspended traffic on it for three months terming it dangerous.

Several parts of the bridge built on the Faujdarhat-Bayezid link road have collapsed due to heavy rain and landslides. The photo was taken on Thursday. Photo: Mohammad Minhaj Uddin
Several parts of the bridge built on the Faujdarhat-Bayezid link road have collapsed due to heavy rain and landslides. The photo was taken on Thursday. Photo: Mohammad Minhaj Uddin

CDA chief engineer Kazi Hassan bin Shams said the retaining walls next to the bridge were not constructed as there was no allocation for that in the previous budget.

A development project proposal (DPP) has been sent, seeking allocation for construction of the retaining wall, he added. 

CDA constructed the link road without environmental clearance from the Department of Environment (DoE). It has also not determined what kind of damage may occur to the environment once the project is implemented. Later, the DoE accused them of violating the hill management plan and fined them Tk103,829,553 in two phases.

CDA cut 10.30 lakh cubic metres of hill for the construction of this road. But even then, as the road was risky, the company applied to the DoE in March 2020 to cut another 3.32 lakh cubic metres of hill. The CDA has not yet received the approval.

The project was undertaken in 1997. The Executive Committee of the National Economic Council (Ecnec) approved it in 1999 at a cost of Tk33.81 crore. In 2004, 55 acres of land were acquired.

File photo. Several parts of the bridge built on the Faujdarhat-Bayezid link road have collapsed due to heavy rain and landslides. The photo was taken on Thursday. Photo: Mohammad Minhaj Uddin
File photo. Several parts of the bridge built on the Faujdarhat-Bayezid link road have collapsed due to heavy rain and landslides. The photo was taken on Thursday. Photo: Mohammad Minhaj Uddin

Work on the road had started at Faujdarhat with the construction of overbridges on the rail tracks.  At that time, the government allotted land to the Asian University for Women (AUW) for construction of its own campus in the same place. Facing the objection of the university authorities, the road construction work was stopped, leaving the whole project abandoned.

After a while, the CDA was able to convince the government that the project was important and the work resumed.

This time the construction cost was increased to Tk210 crore from Tk33.81 crore. In 2015, Spectra Engineers Limited got the work order. Later, the cost was reduced to Tk172 crore.

But due to various complications, the cost was further revised upward and it stood at Tk320 crore. The road was opened to traffic in 2020.

Top News

Faujdarhat-Baizid Bostami link road / Chattogram / bridges / Heavy Rain / soil erosion / erosion / Chattogram Development Authority (CDA)

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • BNP Secretary General Mirza Fakhrul Islam Alamgir speaks at a book unveiling event in Dhaka on 13 July 2025. Photo: Collected
    Fakhrul alleges conspiracy to eliminate Tarique from politics
  • Representational image. Photo: Mohammad Minhaj Uddin/TBS
    Navy-run Dry Dock takeover boosts Ctg Port container handling, daily avg up 7%
  • Bangladesh level the series with dominant 83-run win
    Bangladesh level the series with dominant 83-run win

MOST VIEWED

  • RAB Director General AKM Shahidur Rahman speaks at the press briefing on a fake bomb threat on Biman Bangladesh flight on Saturday, 12 July 2025. Photo: TBS
    Mother faked bomb threat on Biman flight to stop married son from flying with girlfriend: RAB
  • Bangladeshi garment workers make clothing in the sewing section of a factory in Gazipur, Bangladesh, April 9, 2025. Photo: REUTERS/Mohammad Ponir Hossain/File Photo
    Some Walmart garment orders from Bangladesh on hold due to US tariff threat
  • Infographic: TBS
    Dollar price plummets by Tk2.9 in a week as demand wanes
  • Bangladesh and US hold tariff talks on 11 July 2025. Photo: CA Press Wing
    Dhaka, Washington yet to agree on 20% of US tariff conditions: BGMEA
  • Infograph: TBS
    Matarbari power plant eyes G2G coal deal with Indonesia after quality setbacks
  • Dr Mohammad Zakir Hossain, managing director of Delta Pharma Ltd and secretary general of the Bangladesh Association of Pharmaceutical Industries (BAPI). Sketch: TBS
    Pharma industry grew with policy support, needs it again to survive: BAPI secretary general

Related News

  • Water Development Board launches drive in Ctg to recover govt land from 39 influential grabbers
  • Dismembering woman's body: Husband arrested in Ctg
  • Padma erosion: Shariatpur homeless families face eviction from govt land
  • Swechchhasebak League leader found dead in Ctg
  • Three-year-old child dies after falling into open drain in Chattogram

Features

Photo: Collected

Grooming gadgets: Where sleek tools meet effortless styles

5h | Brands
The 2020 Harrier's Porsche Cayenne coupe-like rear roofline, integrated LED lighting with the Modellista special bodykit all around, and a swanky front grille scream OEM Plus for the sophisticated enthusiast looking for a bigger family car that isn’t boring. PHOTO: Ahbaar Mohammad

2020 Toyota Harrier Hybrid: The Japanese Macan

1d | Wheels
The showroom was launched through a lavish event held there, and in attendance were DHS Motors’ Managing Director Nafees Khundker, CEO Imran Zaman Khan, and GMs Arman Rashid and Farhan Samad. PHOTO: Akif Hamid

GAC inaugurate flagship showroom in Dhaka

1d | Wheels
After India's visa restriction, China's Kunming is drawing Bangladeshi patients

After India's visa restriction, China's Kunming is drawing Bangladeshi patients

2d | Panorama

More Videos from TBS

Shooting in Pallabi: What the police are saying

Shooting in Pallabi: What the police are saying

1h | TBS Stories
News of The Day, 13 JULY 2025

News of The Day, 13 JULY 2025

3h | TBS News of the day
Countries where Bangladeshis are not getting positive responses to their visa applications

Countries where Bangladeshis are not getting positive responses to their visa applications

2h | TBS Stories
Has Trump's view on the Russia-Ukraine war changed?

Has Trump's view on the Russia-Ukraine war changed?

4h | Others
EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Advertisement
  • Privacy Policy
  • Comment Policy
Copyright © 2025
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net